Permit Case Summary

Case Number: Search Help

Case Number:ZON2013-00006 Case Status: Date Received:2/6/2013
Description:CONDITIONAL USE PERMIT WITH SEPA to install a concrete batch plant and an asphalt batch plant located off the Wahl Lake Road (T-1000) that connects to SR 104 at milepost 8.52. SR 104 has turn lanes which were designed for all traffic that will utilize the Shine Facility. The proposed facility is in conjunction with a permitted surface mine (DNR reclamation permit 70-013024). The concrete and asphalt batch plants will be on the west side of the Wahl Lake Road located within an existing 18-acre Mineral Resource Land Overlay (MRLO). The proposed asphalt batch plant will replace the existing batch plant that is currently located at the Shine HUB. The 18-acre MRLO lies at the northeast corner of an existing156-acre MRLO known as the Wahl Lake Extraction Area where mining takes place. Silo heights will be between 65 feet to 80 feet. Noise and lighting will be suppressed by the existing commercial forest. The batch plants will have air pollution control systems in compliance with ORCAA regulations. Proposed primary hours of operation are 6am to 5pm Monday through Saturday Scales, office, security office, parking, septic tank and drainfields, and stormwater drainage detention will be located on the east side of Wahl Lake Road outside of the MRLOs. Date Issued:10/21/2013
Applicant: MILES SAND & GRAVEL COMPANY Expiration Date:10/21/2023 12:00:00 AM
Site Address:1501 WAHL LAKE RD Case Finaled:
Parcel No:801361001 Other Cases Parcel Data Map It Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Status updtd - Energov Convrsn
Date Completed: 10/4/2022
Disposition: DONE
Description: Ntc of Dec Apprvl/Appl Inst-UF
Date Completed: 10/21/2013
Disposition:
Description: Override - Parcel Holds
Date Completed: 10/21/2013
Disposition:
Description: Approve Permit-UF
Date Completed: 10/21/2013
Disposition: DONE
Description: Override - Parcel Holds
Date Completed: 10/21/2013
Disposition:
Description: Review Complete-U
Date Completed: 10/21/2013
Disposition: DONE
Description: Override - Parcel Holds
Date Completed: 10/21/2013
Disposition:
Description: DCD Review Time
Date Completed: 10/1/2013
Disposition: PEND
Description: Hearing Exam PH Notice-Pub-UF
Date Completed: 9/23/2013
Disposition: DONE
Description: Hearing Exam PH Notice-APO-UF
Date Completed: 9/23/2013
Disposition: DONE
Description: A Clock Interrupt
Date Completed: 9/23/2013
Disposition: DONE
Description: Additional Info Request-DRD
Date Completed: 9/23/2013
Disposition: DONE
Description: DRD Reviewer Letter (F)
Date Completed: 4/15/2013
Disposition: DONE
Description: Ntc of App +14-Publish-U
Date Completed: 4/15/2013
Disposition: DONE
Description: Ntc of App +14-APO-U
Date Completed: 4/15/2013
Disposition: DONE
Description: Det. of Completeness-UF
Date Completed: 4/15/2013
Disposition: DONE
Description: RAP Review Complete-U
Date Completed: 4/15/2013
Disposition: DONE
Description: Consistency Review-U
Date Completed: 9/23/2013
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 4/15/2013
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 9/23/2013
Disposition: DONE
Description: App Substantially Complete-U
Date Completed: 4/15/2013
Disposition: DONE
Description: Potable Water Approval Req
Date Completed: 5/1/2013
Disposition: DONE
Description: Case Entered
Date Completed: 2/6/2013
Disposition:
Description: Septic Review Complete-U
Date Completed: 6/12/2013
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: Custom Universal Condition
Wording 1. It shall be the affirmative duty of the applicant to determine if any state or federal permits or licenses are necessary and then obtain those permits or licenses at their own expense. 2. The applicant shall update and keep current their Sand and Gravel General Permit (WAG 50 1120) and WAG 50-1120 (asphalt plant) and DNR Reclamation Permit (70-013024). Permit WAG 50-1120 will be revised to include the concrete batch plant when the plant is constructed. Copies of both permits will be sent to the Department of Community Development (DCD). Copies of monitoring and inspections reports will be sent to the County on compliance of the NPDES permits and the reclamation plan. 3. The applicant shall comply with groundwater standards under WAC 173-200. 4. The applicant shall obtain and comply with ORCAA permit requirements. 5. The applicant shall comply with the Best Management Practices Report (log item #28), and provide the County with a written agreement that all employees shall be notified of the critical aquifer recharge area and that annual training for BMPs shall be conducted. 6. The applicant shall comply with the Storm Drainage Report (log item #16) and shall implement stormwater BMPs during the development of the project. 7. After construction, the applicant shall submit a stamped letter to DCD from the project or stormwater engineer certifying that the stormwater management facilities have been constructed as per the approved plans (log items #16 & #18). 8. Security lighting for the equipment enclosure shall be minimized. The batch plants and surrounding areas will utilize lighting for security and safety and when required during operations to meet project specific demands. Lighting will primarily be controlled by photocell and will operate from dust to dawn. Lighting fixtures shall be designed and hooded to prevent the light source from being directly visible from outside the boundaries of the property. The intensity or brightness of all lighting, during construction and after project completion shall not adversely affect the use of surrounding properties or adjoining rights-of-way. The applicant will submit a lighting plan that meets the above requirements for staff's approval. 9. Noise generated by the project shall not exceed the maximum environmental noise levels established in Chapter 173-60, Washington Administrative Code, as it is now in effect or hereafter amended. All noise emitting equipment that cannot in any way operate below the maximum permitted noise level shall be housed in a sound-attenuating structure, unless otherwise stipulated in the project approval. The applicant may be required to submit sound attenuation plans for review and approval by the department, and conduct sound monitoring at the applicant’s expense. 10. Signs shall be reviewed administratively by the Department of Development Review. An administrative determination to approve a sign application shall be made when the proposal is consistent with the goals, policies, and provisions of the Comprehensive Plan, and/or applicable community development plan, and Jefferson County Code. 11. The applicant shall comply with the a Cultural Resources Survey (log item #10) prepared by Geoengineers dated February 1, 2010, and with the Treatment Plan for Unanticipated Cultural and Archaeological Discoveries (log item # 8) 12. The applicant shall comply with all relevant performance and development standards as outlined in section (7) of the staff report. 13. The use requires a Group B public water system per the Environmental Health Department (log item #14). Completion of this water system is required prior to issuance of BLD13-00171. 14. The site development shall comply with the approved site plan as depicted on log item #3. 15. A conditional use permit automatically expires and becomes void if the applicant fails to file for a building permit or other necessary development permit within three (3) years of the effective date (the date of the decision granting the permit) in the case of the asphalt batch plant permit, and ten (10) years in the case of the concrete batch plant. 16. Extensions to the duration of the original permit approval are prohibited. 17. The Department of Community Development shall not be responsible for notifying the applicant of an impending expiration. 18. The county may modify an approved conditional use permit as follows: the county may delete, modify or impose additional conditions upon finding that the use for which the approval was granted has been intensified, changed or modified by the property owner or by person(s) who control the property without approval so as to significantly impact surrounding land uses. A modification will be processed as a Type II land use decision pursuant to JCC 18.40.270 of this Code. 19. A conditional use permit granted under this Section 18.40 shall continue to be valid upon a change of ownership of the site, business, service, use or structure that was the subject of the permit application. No other use is allowed without approval of an additional conditional use permit. 20. The County may suspend or revoke an approved conditional use permit pursuant to Section 18.50 of this Code only upon finding that: The use for which the approval was granted has been abandoned for a period of at least one (1) year; approval of the permit was obtained by misrepresentation of material fact; or the permit is being exercised contrary to the terms of approval. 21. Primary hours of operation will be 6:00am to 5:00pm Monday through Saturday, with operations before/after primary hours allowed as required to meet project specific demands. 22. The site plan (log item # 34) as submitted with the Zoning Conditional Use Permit application been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated October 21, 2013 shall be resubmitted for review and approval by Jefferson County Department of Community Development.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-Custom Universal Finding
Wording See the Hearing Examiner's Report and Decision dated received October 18, 2013 for findings of fact and conclusions of law.