Case Number | | CAM2022-00493
|
|
Description | | Current permitted mining operation that would like to expand operations by 15 acres. Operations would be conducted in phases with 10 acres of active mining occurring at a time. Please see attached documents for quick reference.
What is required to expand operations?
Can operations mine within the water table? If so what requirements will be needed for approval?
How long does the permitting process take?
|
|
Last Name | | MAHR
|
|
Received Date | | 11/9/2022 4:20:13 PM
|
|
Status | | Pending
|
|
| | |
|
|
Case Number | | BLD2018-00301
|
|
Description | | INSTALLATION OF ABOVE GROUND LIQUEFIED NATURAL GAS CONTAINER
1 15KG/GAL LNG FUEL TANK & 2 AMBIENT VAPORISER TOWERS
|
|
Last Name | | MILE SAND AND GRAVEL
|
|
Received Date | | 7/13/2018 11:42:19 AM
|
|
Status | | R
|
|
| | |
|
|
Case Number | | CAM2018-00026
|
|
Description | | WHAT PERMITS, FEES, DOCUMENTS, PROCESSES AND PROCEDURES ARE REQUIRED FOR THE INSTALLATION OF A NATURAL GAS/LIQUIFIED NATURAL FUELING SYSTEM FOR USE IN INDUSTRIAL APPLICATIONS (ASPHALT PLANT BURNER FUEL)? (2X) 15K-20K GALLLON ABOVE GROND LNG TANK. (2X) VERTICAL AMBIENT VAPORIZER TOWERS.
|
|
Last Name | | PENCE
|
|
Received Date | | 1/16/2018 2:02:21 PM
|
|
Status | | M
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | FPA2615094
|
|
Description | | Harvest 122.6 acres
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 9/11/2017 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | SEP2015-00015
See SOM case for current septic system activity.
|
|
Description | | tank & transport line only to SEP12-104 filed here
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 2/10/2015 3:42:37 PM
|
|
Status | | Finaled
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | FPA2613325
|
|
Description | | Harvest 59 acres, 6100 ft of road construction
Amendment 4/8/2015 - Add Biomass harvest on Unit 3
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 12/3/2014 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | BLD2014-00262
|
|
Description | | COMMERICAL SHOP with bathroom (no MLA filed)
1 48x60 pole building - 2 12x60 lean too- 1 6x24' lean too with 12x60 2nd floor only
|
|
Last Name | | MILES SAND & GRAVEL COMPANY
|
|
Received Date | | 7/24/2014 3:02:47 PM
|
|
Status | | Finaled
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | WAT-AD080
|
|
Description | |
|
|
Last Name | | SHINE FACILITY
|
|
Received Date | | 4/7/2014 11:21:51 AM
|
|
Status | | Pending
|
|
| | |
|
|
Case Number | | SOM2012-00104
|
|
Description | | Tank and Transport Line added to system under SEP15-00015.
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 2/11/2014 3:49:12 PM
|
|
Status | | RNC
|
|
| | |
|
|
Case Number | | BLD2013-00337
|
|
Description | | Construction of 26x72x12' cover over existing office building, no walls
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 10/24/2013 11:19:14 AM
|
|
Status | | Finaled
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | BLD2013-00171
|
|
Description | | Manufactured home for security personnel.
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 6/4/2013 3:37:39 PM
|
|
Status | | Finaled
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | FPA2612202
|
|
Description | | 129-acre spray.
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 2/25/2013 2:14:19 PM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | ZON2013-00006
|
|
Description | | CONDITIONAL USE PERMIT WITH SEPA to install a concrete batch plant and an asphalt batch plant located off the Wahl Lake Road (T-1000) that connects to SR 104 at milepost 8.52. SR 104 has turn lanes which were designed for all traffic that will utilize the Shine Facility. The proposed facility is in conjunction with a permitted surface mine (DNR reclamation permit 70-013024).
The concrete and asphalt batch plants will be on the west side of the Wahl Lake Road located within an existing 18-acre Mineral Resource Land Overlay (MRLO). The proposed asphalt batch plant will replace the existing batch plant that is currently located at the Shine HUB. The 18-acre MRLO lies at the northeast corner of an existing156-acre MRLO known as the Wahl Lake Extraction Area where mining takes place. Silo heights will be between 65 feet to 80 feet. Noise and lighting will be suppressed by the existing commercial forest. The batch plants will have air pollution control systems in compliance with ORCAA regulations. Proposed primary hours of operation are 6am to 5pm Monday through Saturday
Scales, office, security office, parking, septic tank and drainfields, and stormwater drainage detention will be located on the east side of Wahl Lake Road outside of the MRLOs.
|
|
Last Name | | MILES SAND & GRAVEL COMPANY
|
|
Received Date | | 2/6/2013 3:32:49 PM
|
|
Status | | CLS
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | BLD2012-00293
|
|
Description | | COMMERCIAL MODULAR OFFICE
|
|
Last Name | | MILES SAND & GRAVEL COMPANY
|
|
Received Date | | 9/25/2012 2:48:17 PM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | SEP2012-00104
See SOM case for current septic system activity.
|
|
Description | | info filed to SEP15-15
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 9/6/2012 1:35:14 PM
|
|
Status | | Finaled
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | FPA2611900
|
|
Description | | AMENDMENT: add additional chemical (Drift Control Agent).
403-acre spray. (3 year approval).
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 7/17/2012 10:51:20 AM
|
|
Status | | Finaled
|
|
| | |
|
|
|
Case Number | | FPA2611866
|
|
Description | | 93 ac Harvest / 1,050ft Road Const.
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 6/28/2012 9:51:24 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2611580
|
|
Description | | 2012 fertilization: 435-acres.
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 1/25/2012 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2611500
|
|
Description | | 48-acre timber harvest and 1800 feet of road construction.
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 11/8/2011 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2611268
|
|
Description | | 470-acre spray.
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 7/5/2011 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | PRE2011-00016
|
|
Description | | PRE APPLICATION TO INSTALL ASPHALT & CONCRETE BATCH PLANTS
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 6/29/2011 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2611173
|
|
Description | | 17-acre timber harvest and 980 feet of road construction (See MLA11-54/BLD11-63 for stormwater permit w/SEPA)
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 5/24/2011 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2611125
|
|
Description | | 43-acre timber harvest
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 5/10/2011 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | BLD2011-00063
|
|
Description | | Stormwater Permit with SEPA: The proposal is to grade and construct improvements in the 18-acres lying adjacent to and north of the 156-acre Wahl Extraction Area. These 18-acres recently obtained a Mineral Resource Lands Overlay (MRLO) designation through the Jefferson County Comprehensive Plan Amendment process and is also the location for Miles' new Shine Facility. Prior to grading, the 18-acres will be logged by Pope Resources (land owner) as part of their commercial forestry business. The new portion of T-1000 is located in an area that has been recently logged by Pope Resources.
The new Shine facility is proposed to access SR 104 from private Forestry Road T-1000. The intersection of T-1000 with SR 104 is proposed to be relocated to MP 8.52 (approximately 1800 feet west of its current location). This application also includes grading and constructing the new intersection at SR 104 and approximately 1,000 feet of new road from the WSDOT right-of-way to the exiting T-1000 road. Approximately 9,000 feet of the exiting T-1000 road to the new Shine Facility will follow the existing route and grades. The northernmost portion will be improved with an asphalt surface for approximately 7200 feet.
Proposed grading within the new Shine Facility includes 365,600 cubic yards of cut and 5,000 cubic yards of fill (360,600 net cut). Significant grading is not anticipated on the T-1000 except for the northernmost 1,000 feet of the new access road located at the new intersection with SR 104. Grading quantities for this 1,000 foot section of T-1000 are estimated at 2,300 cubic yards of cut and 20,600 cubic yards of fill (18,300 cubic yards net fill).
Water quantity management of stormwater associated with the new intersection with SR 104 and 1000 feet of new road will be through the use of an infiltration pond designed according to the 2005 Department of Ecology Stormwater Management Manual for Western Washington. The remaining improvements to T-1000 will not result in any new impervious surfaces; and therefore, do not require any new stormwater management. Existing ditches and culverts will be cleaned and maintained as necessary to ensure continuous drainage of the roadway. The north portion of the new Shine Facility will be graded and will continue to drain to the east through the existing drainage pattern. New buildings proposed for this area will require stormwater management and could include roof downspout infiltration. The southern portion of the new Shine Facility will be graded to drain to an infiltration pond located in the NE corner of the Wahl Extraction Area.
|
|
Last Name | | MILES SAND & GRAVEL COMPANY
|
|
Received Date | | 3/21/2011 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2610872
|
|
Description | | 69-acre timber harvest and 700 feet of road construction
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 12/15/2010 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | ZON2010-00026
|
|
Description | | COMP PLAN AMENDMENT
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 3/1/2010 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2610302
|
|
Description | | 26-acre timber harvest and 950 feet of road construction
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 12/30/2009 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2608876
|
|
Description | | 1900 feet of road construction
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 9/17/2007 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2607937
|
|
Description | | 853.5 acre spray
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 8/21/2006 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2607628
|
|
Description | | 113 acre timber harvest, 2400 ft road construction
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 4/11/2006 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2606391
|
|
Description | | Harvest of 503 acres.
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 10/15/2004 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2605703
|
|
Description | | Aerial Chemical Application
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 10/15/2003 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2605611
|
|
Description | | Aerial Chemical Application
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 8/18/2003 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2605386
|
|
Description | | Aerial Chemical Application
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 5/29/2003 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2605256
|
|
Description | | Aerial Chemical Application
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 4/21/2003 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2605105
|
|
Description | | Salvage Harvest
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 4/16/2003 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2604910
|
|
Description | | Aerial Chemical Application
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 9/26/2002 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2604834
|
|
Description | | Aerial Chemical Application
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 8/20/2002 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | ZON2002-00049
|
|
Description | | Comprehensive Plan Land Use Map designation of approximately 6,240 acres as Mineral Resource Overlay District.
|
|
Last Name | | FRED HILL MATERIALS INC
|
|
Received Date | | 4/30/2002 12:00:00 AM
|
|
Status | | DAP
|
|
| | |
|
|
Case Number | | FPA2604293
|
|
Description | | Chemical application
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 12/5/2001 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2604135
|
|
Description | | Chemical application
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 8/15/2001 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2604058
|
|
Description | | Road Construction for access to future conveyor belt and future gravel mining
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 6/19/2001 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2603989
|
|
Description | | Even age harvest
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 5/8/2001 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2603857
|
|
Description | |
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 4/18/2001 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2602047
|
|
Description | | Renewal for road construction portion of original permit
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 12/21/2000 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2603443
|
|
Description | | Forest practice application.
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 7/19/2000 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2603214
|
|
Description | | Forest Practice Application.
|
|
Last Name | |
|
|
Received Date | | 3/6/2000 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|