Case Number:XMP1999-00001 Case Status:Finaled Date Received:1/5/1999
Description:Installation of a single buoy for anchorage of a personal vessel within the waters of the State. Date Issued:4/19/1999
Applicant:JACK GRAHAM Expiration Date:4/19/2000 12:00:00 AM
Site Address: Case Finaled:
Parcel No:DISCOVERYBAY Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Close case
Date Completed: 10/12/2007
Disposition: DONE
Description: Miscellaneous action
Date Completed: 9/19/2003
Disposition: DONE
Description: Close case
Date Completed: 11/16/2000
Disposition: DONE
Description: Miscellaneous action
Date Completed: 11/16/2000
Disposition: DONE
Description: Construction Commencement
Date Completed:
Disposition:
Description: (F) Issue exemption
Date Completed: 4/19/1999
Disposition: A
Description: App Substantially Complete (F)
Date Completed: 2/21/1999
Disposition: P
Description: (F) XMP Application Notice +30
Date Completed: 3/27/1999
Disposition: P
Description: Planner Review
Date Completed: 1/14/1999
Disposition: P

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: FINDING: EXEMPTION SECTIONS
Wording The proposal is consistent with Exemptons Section 3.402(11) of the Jefferson-Port Townsend Shoreline Management Master Program.

Title: XMP LESS THAN $2500
Wording The development review division finds this project is exempt from a substantial development permit under Section 3.40(1) of the Jefferson County Shoreline Management Master Program. The total cost or fair market value does not exceed $2,500, and the development does not materially interfere with the normal public use of the water or shorelines of the State.

Title: CUSTOM CONDITION
Wording Land based retrieval lines from mooring buoys shall be designed and operated to present no hazard to navigation or public use of the water and shall extend no more than thirty (30) feet off-shore.

Title: CUSTOM CONDITION
Wording Mooring buoys shall not be authorized where such installations will significantly interfere with navigation.

Title: CUSTOM CONDITION
Wording Mooring buoys shall be located as close to the shore as feasible. They shall not be located farther waterward than adjacent mooring buoys unless the draft and/or swing path of the boat dictates it.

Title: CUSTOM CONDITION
Wording Buoys shall be discernible under normal daylight conditions at a minimum of 100 yards.

Title: CUSTOM CONDITION
Wording Mooring buoys shall be located no closer than 100 feet from another mooring buoy, dock, pier, float, or other fixed navigational obstruction, unless there is a written agreement with the parties affected, including the subtidal property owner, that will allow for said encroachment.

Title: CUSTOM CONDITION
Wording Buoys shall be marked with the owner's name, address, and telephone number.

Title: CUSTOM CONDITION
Wording The applicant for a buoy shall demonstrate that the buoy system proposed is adequate to withstand the maximum expected physical stress that the environment and moored craft will place on the buoy.

Title: CUSTOM CONDITION
Wording The inshore adjacent property owner shall be given preference for mooring buoys located shoreward of the minus six foot or one fathom tidal elevation unless otherwise authorized. If the shoreline property owner does not own the tidelands, access across the tidelands shall be secured in writing prior to buoy placement.

Title: CUSTOM CONDITION
Wording No more than two (2) boats shall be secured by a mooring buoy.

Title: CUSTOM CONDITION
Wording The applicant shall obtain a mooring buoy license from the Departmetn of Natural Resources prior to placement of the buoy.

Title: CUSTOM CONDITION
Wording The applicant shall notify Jefferson County at least 48 hours in advance of construction.

Title: CUSTOM CONDITION
Wording Mooring buoys that are placed by exemption shall not be rented or leased.