Permit Case Summary

Case Number: Search Help

Case Number:XMP1998-00025 Case Status: Date Received:6/29/1998
Description:Construction of a 150 foot long rip-rap wall and an H-pile retaining wall for road repair purposes. Date Issued:8/13/1998
Applicant: JEFFERSON COUNTY DEPT OF PW Expiration Date:8/13/1999 12:00:00 AM
Site Address: Case Finaled:
Parcel No:HOODCANAL Other Cases Parcel Data Map It Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Status updtd - Energov Convrsn
Date Completed: 10/4/2022
Disposition: DONE
Description: Miscellaneous Action
Date Completed: 6/2/2000
Disposition: DONE
Description: (F) Issue exemption
Date Completed: 8/13/1998
Disposition: A
Description: Planner Review
Date Completed: 8/13/1998
Disposition: A

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: FINDING: EXEMPTION SECTIONS
Wording The proposal is consistent with Exemptons Section 3.402(6) of the Jefferson-Port Townsend Shoreline Management Master Program.

Title: proximity to shoreline
Wording The proposed rip-rap would be placed between Shine Road and an upland 'bench' where a recreation area is located. The proposal would be located over fifty (50) feet from the Ordinary High Water Mark.

Title: driven H-pile wall
Wording As part of the same project, the proponent is considering replacing a timber pile wall which has deteriated. It will be replaced by an H-pile wall composed of driven steel, will be 8-feet in height, and located a minimum of 25 feet upland of the ordinary high water mark.

Title: APPROVAL ONLY FOR J-PTSMMP
Wording This approval pertains to Jefferson-Port Townsend Shoreline Management Master Program requirements only. The approval of any other agency with jurisdiction or any other required permits shall be obtained prior to undertaking the project.

Title: OTHER WORK/SEPARATE APPROVAL
Wording Work within the jurisdiction of the Shoreline Program other than as described above shall receive separate review from this office.

Title: NO FILL OR OTHER MATERIAL
Wording No fill or other material may be placed in the waters or intertidal areas of Jefferson County.

Title: FISHERIES & HYDRAULICS CODE
Wording Prior to commencing construction, proponent should contact the Washington State Department of Fisheries at (360) 895-4757 to determine whether this action is subject to the Washington State Hydraulics Code.

Title: NOTIFICATION PRIOR TO BEGINNING
Wording The proponent shall notify the Jefferson County Permit Center, (360) 379-4450, Development Review Division 48 hours in advance prior to commencing construction in order to allow monitoring and ensure conformance with project conditions.

Title: CUSTOM CONDITION
Wording The Public Works Dept. shall submit a copy of the approved small parcel erosion control plan to the Permit Center for project compliance with the Jefferson County Storm Water Ordinance.