Case Number:XMP1996-00010 Case Status: Date Received:3/19/1996
Description:Removal of existing deteriorated wooded and concrete dockage in the area referred to as "C" dock; and replacement with new concrete fingers and headwalk per plans provided in file. The plan calls for utilization of existing pilings. Date Issued:2/3/1997
Applicant: PLEASANT HARBOR CORPORATION Expiration Date:3/22/1997 12:00:00 AM
Site Address: Case Finaled:
Parcel No:HOODCANAL Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Status updtd - Energov Convrsn
Date Completed: 10/4/2022
Disposition: DONE
Description: (F) Issue exemption
Date Completed: 2/3/1997
Disposition: A
Description: (F) Issue exemption
Date Completed: 3/22/1996
Disposition: A
Description: Planner Review
Date Completed:
Disposition:

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: FINDING: EXEMPTION SDP
Wording The department finds this project is a substantial development and is exempt from permitting under Section 3.40(6) of the Jefferson County Shoreline Management Master Program.

Title: CUSTOM FINDING
Wording On January 24, 1997, the applicant requested that the shoreline substantial development permit exemption be modified to include the replacement of two existing pilings. The two pilings were damaged and replacement will not consist of any additional pilings. The new pilings will be concrete;whereas the prior material was creosote.

Title: CUSTOM FINDING
Wording The applicant has obtained a Hydrallic Project Approval (control #00-B8201-02) for the replacement of the pilings, dated January 17, 1997.

Title: APPROVAL ONLY FOR J-PTSMMP
Wording This approval pertains to Jefferson-Port Townsend Shoreline Management Master Program requirements only. The approval of any other agency with jurisdiction or any other required permits shall be obtained prior to undertaking the project.

Title: OTHER WORK/SEPARATE APPROVAL
Wording Work within the jurisdiction of the Shoreline Program other than described above shall receive separate review and approval from this office.

Title: NOTIFICATION PRIOR TO BEGINNING
Wording The proponent shall notify the Jefferson County Permit Center, Development Review Division 48 hours in advance prior to commencing construction in order to allow monitoring and ensure conformance with project conditions.

Title: CUSTOM CONDITION
Wording All conditions of the Hyraulic Project Approval shall be followed; including that completion of the project shall be conducted prior to March 14, 1997; as this shoreline exemption expires March 22, 1997.