Title:
|
| | |
FINDING: EXEMPTION SECTIONS
|
|
Wording
|
| | |
The proposal is consistent with Exemptons of E2SSB 5632 enacted July 24, 1995 for flood damage reduction issues. The proposal is exempt under E2SSB 5632.
|
|
|
Title:
|
| | |
FINDING: HPA NUMBER
|
|
Wording
|
| | |
A Hydraulic Project Approval was issued September 15, 1995 under Control Number 00-C3602-02. The HPA expires on October 15, 1996.
|
|
|
Title:
|
| | |
CUSTOM FINDING
|
|
Wording
|
| | |
Trees for fish habitat will be attached to several key areas of the bank with cabled "dead-men" bolts. Technical assistance and materials for the project will be provided by Jefferson County, while the Brinnon Flood Board will donate equipment and volunteer labor.
|
|
|
Title:
|
| | |
APPROVAL ONLY FOR J-PTSMMP
|
|
Wording
|
| | |
This approval pertains to Jefferson-Port Townsend Shoreline Management Master Program requirements only. The approval of any other agency with jurisdiction or any other required permits shall be obtained prior to undertaking the project.
|
|
|
Title:
|
| | |
OTHER WORK/SEPARATE APPROVAL
|
|
Wording
|
| | |
Work within the jurisdiction of the Shoreline Program other than described above shall receive separate review and approval from this office.
|
|
|
Title:
|
| | |
NOTIFICATION PRIOR TO BEGINNING
|
|
Wording
|
| | |
The proponent shall notify the Jefferson County Permit Center, Development Review Division 48 hours in advance prior to commencing construction in order to allow monitoring and ensure conformance with project conditions.
|
|
|
Title:
|
| | |
CUSTOM CONDITION
|
|
Wording
|
| | |
Work shall be in accordance with the hydraulic project approval, number 00-C3602-02, issued on September 15, 1995 and expiring on October 15, 1996.
|
|