Title:
|
| | |
FINDING: EXEMPTION SECTIONS
|
|
Wording
|
| | |
The proposal is consistent with Exemptons Section 3.402(6) of the Jefferson-Port Townsend Shoreline Management Master Program. The proposal is not a substantial development.
|
|
|
Title:
|
| | |
FINDING: HPA NUMBER
|
|
Wording
|
| | |
A Hydraulic Project Approval was issued May 24, 1994 under Control Number 00-54982-03. The HPA expires on March 15, 1995.
|
|
|
Title:
|
| | |
APPROVAL ONLY FOR J-PTSMMP
|
|
Wording
|
| | |
This approval pertains to Jefferson-Port Townsend Shoreline Management Master Program requirements only. The approval of any other agency with jurisdiction or any other required permits shall be obtained prior to undertaking the project.
|
|
|
Title:
|
| | |
OTHER WORK/SEPARATE APPROVAL
|
|
Wording
|
| | |
Work within the jurisdiction of the Shoreline Program other than described above shall receive separate review and approval from this office.
|
|
|
Title:
|
| | |
NO FILL OR OTHER MATERIAL
|
|
Wording
|
| | |
No fill or other material may be placed in the waters or intertidal areas of Jefferson County.
|
|
|
Title:
|
| | |
NOTIFICATION PRIOR TO BEGINNING
|
|
Wording
|
| | |
The proponent shall notify the Jefferson County Permit Center, Development Review Division 48 hours in advance prior to commencing construction in order to allow monitoring and ensure conformance with project conditions.
|
|
|
Title:
|
| | |
CUSTOM CONDITION
|
|
Wording
|
| | |
The proponent shall comply with the 22 conditions as set forth in the Hydraulic Project Approval Permit of May 24, 1994.
|
|