Permit Case Summary

Case Number: Search Help

Case Number:SEP2019-00060 Case Status:Finaled Date Received:3/19/2019
Description:Adding an ATU ONLY for new BLD that will be processing apples into cider. Effluent pumped to SEP16-09 main drainfield Date Issued:2/25/2020
Applicant: FINNRIVER NORTH LLC Expiration Date:2/25/2023 12:00:00 AM
Site Address:124 CENTER RD Case Finaled:2/26/2020
Parcel No:901151004 Other Cases Parcel Data Map It More Details Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: SEPTIC PERMIT FINALED "F"
Date Completed: 2/26/2020
Disposition: DONE
Description: INSTALLATION START NOTICE
Date Completed:
Disposition:
Description: Issue permit (Fm) "A"
Date Completed: 6/19/2019
Disposition: DONE
Description: Monitoring Agreemt Sent (Fm)
Date Completed: 2/20/2020
Disposition: DONE
Description: REDESIGN SUBMITTED (Fm) "P"
Date Completed: 6/17/2019
Disposition: DONE
Description: Pending letter; add inf (Fm)
Date Completed: 6/17/2019
Disposition: DONE
Description: Septic Permit Application (Fm)
Date Completed: 3/27/2019
Disposition: DONE
Description: PRESSURE-PUMP TEST REQUEST
Date Completed: 2/20/2020
Disposition: DONE
Description: Asbuilt drawing submitted
Date Completed: 2/20/2020
Disposition: DONE
Description: Initial Site Inspection by HD
Date Completed: 4/18/2019
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 6/7/2019
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 4/18/2019
Disposition: DONE
Description: Case Entered "P"
Date Completed: 3/19/2019
Disposition:

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: pressure test observation
Wording Health Dept. required to observe pressure test with system designer when system fully installed/complete, 48 hours notice to be provided for scheduling.

Title: alternative-asbuilt required
Wording H - An asbuilt drawing and certification of completion by the designer is required prior to final approval.

Title: protection from vehicular traffic
Wording All components of the septic system are to be completely protected from vehicular traffic or mechanical disturbance.

Title: divert drainage
Wording Divert all sources of drainage, including roof drains away from all tanks.

Title: UDC compliance
Wording Approval of this sewage disposal permit does not preclude the permit holder from complying with the Unified Development Code for other/future development on the site.

Title: BOD-WASTE STRENGTH MONITORING
Wording Waste Strength (BOD, TSS, Grease and oils) MUST to be monitored midway through a production cycle annually. Responsibility is that of the owner. Results are to be submitted to the Jefferson County Health Dept.

Title: design flow/water usage monitorin
Wording Dose counter monitoring results shall be submitted to the Jefferson County Health Dept. no less than annually.

Title: RISER ON D-BOX IF INSTALLED
Wording IF the Distribution box is installed, it shall be fitted with a riser to grade, constructed of durable materials and a secured lid, adequately sized to allow visible inspection of the liquid level in the box.

Title: Water line setback
Wording 10' separation required between a Water line and all portions of the onsite sewage system; effluent transport line, tanks, treatment and disposal components.

Title: O & M Manual required
Wording Before final approval is given, the designer shall provide an operations and maintenance manual to the property owner and the Health Department. The manual must instruct the owner of the on site sewage system on the ways to properly operate and maintain all components of the system.

Title: System capacity/uses
Wording Approval of this permit does not assure the existing septic system has capacity for all uses allowed by current code.

Title: Designer Notification/inspections
Wording Designer must be contacted prior to start of construction and for inspections during installation. DESIGNER IS REQUIRED TO DO A PRECOVER INSPECTION ON ALL TYPES OF SYSTEMS.

Title: Installation Inspection
Wording Notification of the start of construction shall be faxed or emailed to Jefferson County Public Health ONE WORKING DAY prior to start.

Title: No Building Permit Guaranteed
Wording Approval/issuance of a sewage disposal permit or installation of a septic system does not guarantee the approval of other development or a building permit on this site. Future buildings that require connection to an on-site sewage system (OSS) shall only be approved if the OSS meets the current standards and codes in effect at the time of the building application.

Title: Code Compliance
Wording All construction and development activities must comply with all permit conditions, Washington State and Jefferson County Codes and Recommended Standards and Guidance documents in effect when the permit is issued.

Title: PERMIT ISSED WITH UNDERSTANDING
Wording Should future waste strength testing show that the effluent is not meeting treatment level "E" standards, the second ATU will be installed or other measure taken, via a modification permit, to lower the waste strength prior to the following production year.

Title: RECOMMEND TRACE WIRE
Wording recommend installing a tone or trace wire in the transport line trench.

Title: SEPTIC/PUMP TANK
Wording H - The septic tank with the pump in the 2nd chamber must be a septic tank that has its 4" wall opening at the top, not 2/3 down as is typical.

Title: FLOOR DRAINS
Wording H - The building this OSS serves must have screened floor drains. These screens must be in place prior to final approval of this permit.

Title: ATU AUTHORIZED O&M PROVIDER
Wording H - A maintenance and management contract is required with the manufacturers authorized representative prior to final approval of this permit. Maintenance of the system shall be completed by a manufacturers authorized representative at the frequency required by the manufacturer.

Title: Stormwater BMPs
Wording The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-No ESAs Found
Wording Jefferson County Department of Community Development reviewed the application and the county GIS mapping system for the presence of critical areas and concluded that the property DOES NOT contain critical areas. However, future proposals will be subject to a new critical area review and conditions may be added if critical areas are found on the property.