Description:
|
| | |
Monitoring Agreemt Sent (Fm)
|
|
Date Completed:
|
| | |
12/19/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
SEPTIC PERMIT FINALED "F"
|
|
Date Completed:
|
| | |
10/26/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue permit (Fm) "A"
|
|
Date Completed:
|
| | |
4/21/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
A Clock Interrupt
|
|
Date Completed:
|
| | |
4/10/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-DRD
|
|
Date Completed:
|
| | |
4/10/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Invoice for DCD Sent
|
|
Date Completed:
|
| | |
4/7/2017
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Up Front Review
|
|
Date Completed:
|
| | |
4/10/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Permit Application (Fm)
|
|
Date Completed:
|
| | |
4/6/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Initial Site Inspection by HD
|
|
Date Completed:
|
| | |
4/21/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Asbuilt drawing submitted
|
|
Date Completed:
|
| | |
10/23/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
4/21/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
4/21/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered "P"
|
|
Date Completed:
|
| | |
4/6/2017
|
|
Disposition:
|
| | |
|
|
|
Title:
|
| | |
pressure test observation
|
|
Wording
|
| | |
Health Dept. required to observe pressure test with system designer when system fully installed/complete, 48 hours notice to be provided for scheduling.
|
|
|
Title:
|
| | |
alternative-asbuilt required
|
|
Wording
|
| | |
H - An asbuilt drawing and certification of completion by the designer is required prior to final approval.
|
|
|
Title:
|
| | |
Tank Abandonment
|
|
Wording
|
| | |
H - Existing tank shall be properly abandoned. It shall be pumped and filled with clean fill. Documentation to be provided to Health Dept. prior to final.
|
|
|
Title:
|
| | |
divert drainage
|
|
Wording
|
| | |
Divert all sources of drainage, including roof drains away from septic tank and drainfield area.
|
|
|
Title:
|
| | |
water tight tank
|
|
Wording
|
| | |
Septic tank and pump chamber to be water tight. Extra protection (i.e. Bentonite) to be used around inlet, outlet, and risers due to high water table.
|
|
|
Title:
|
| | |
UDC compliance
|
|
Wording
|
| | |
Approval of this sewage disposal permit does not preclude the permit holder from complying with the Unified Development Code for other/future development on the site.
|
|
|
Title:
|
| | |
holding tank
|
|
Wording
|
| | |
Risers to grade with secured lids shall be located over all compartments. Access ports intended for use as pump-out sites shall be fitted with an impervious pad that slopes towards the access. All pumping and related service must be performed by a Jefferson County licensed septic system pumper. Permit Holder shall maintain and keep operational records which include pumping intervals, sewage volume, disposal site, service and repair records. These records shall be available upon request of the Health officer representative. A high water float with an audio visual alarm shall be provided. The alarm shall be located within view of the holding tank in a watertight enclosure and approved by the State Electrical Inspector.
|
|
|
Title:
|
| | |
surface water setback
|
|
Wording
|
| | |
Setback to surface waters- 60' required from tanks.
|
|
|
Title:
|
| | |
protective barriers
|
|
Wording
|
| | |
H - Permanent barriers are required along/around primary and reserve drainfield areas to protect from parking, driving, and other land disturbing activities prior to final.
|
|
|
Title:
|
| | |
Water line setback
|
|
Wording
|
| | |
10' separation required between a Water line and all portions of the onsite sewage system; effluent transport line, tanks, treatment and disposal components.
|
|
|
Title:
|
| | |
VIOLATION-limited permit life
|
|
Wording
|
| | |
This permit was issued to correct a violation of WAC 246-272A for a leaking holding tank. The permit must be completed within 90 days of the date of issuance.
|
|
|
Title:
|
| | |
O & M Manual required
|
|
Wording
|
| | |
Before final approval is given, the designer shall provide an operations and maintenance manual to the property owner and the Health Department. The manual must instruct the owner of the on site sewage system on the ways to properly operate and maintain all components of the system.
|
|
|
Title:
|
| | |
Designer Notification/inspections
|
|
Wording
|
| | |
Designer must be contacted prior to start of construction and for inspections during installation. DESIGNER IS REQUIRED TO DO A PRECOVER INSPECTION ON ALL TYPES OF SYSTEMS.
|
|
|
Title:
|
| | |
Installation Inspection
|
|
Wording
|
| | |
Notification of the start of construction shall be faxed or emailed to Jefferson County Public Health ONE WORKING DAY prior to start.
|
|
|
Title:
|
| | |
Certified Installer Required
|
|
Wording
|
| | |
This system must be constructed by an installer certified by the Jefferson County Public Health Department per Jefferson County Code 8.15.120 (9) and state code WAC246-272A-0250 for distance to a shoreline.
|
|
|
Title:
|
| | |
No Building Permit Guaranteed
|
|
Wording
|
| | |
Approval/issuance of a sewage disposal permit or installation of a septic system does not guarantee the approval of other development or a building permit on this site. Future buildings that require connection to an on-site sewage system (OSS) shall only be approved if the OSS meets the current standards and codes in effect at the time of the building application.
|
|
|
Title:
|
| | |
Code Compliance
|
|
Wording
|
| | |
All construction and development activities must comply with all permit conditions, Washington State and Jefferson County Codes and Recommended Standards and Guidance documents in effect when the permit is issued.
|
|
|
Title:
|
| | |
PRESSURE TEST TRANSPORT
|
|
Wording
|
| | |
H - The Entire transport line must be pressure tested at 50psi for one hour as per design.
|
|
|
Title:
|
| | |
LEAK TEST HOLDING TANK
|
|
Wording
|
| | |
H -The new holding tank must be leak tested as per design requirements.
|
|
|
Title:
|
| | |
EXISTING TRANSPORT LINE
|
|
Wording
|
| | |
H -The existing transport line under the pier out to the pump out float needs to be re-secured in places. This work must take place prior to final sign off of this permit.
|
|
|
Title:
|
| | |
CONFIRMED CA’S
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County Department of Community Development staff on April 7th, 2017 for the potential presence of Critical Areas under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following Critical Areas were confirmed to be present on the subject property: Type F Stream, Fish and Wildlife Habitat Conservation Area, Wetlands, Special Aquifer Recharge Protection Area, High Risk SIPZ.
|
|
|
Title:
|
| | |
SHORELINE EXEMPTION
|
|
Wording
|
| | |
This project was reviewed and approved as a Shoreline Exemption under JCC 18.25.560(2).
|
|
|
Title:
|
| | |
SEPTIC CODE INTERPRETATION
|
|
Wording
|
| | |
The proposed septic system replacement is exempt from Critical Area review under JCC 18.22.070(6) & (21) per Code Interpretation dated August 26, 2014.
|
|
|
Title:
|
| | |
SDP CASE
|
|
Wording
|
| | |
Associated SDP Case is SDP17-00001/MLA17-00004
|
|
|
Title:
|
| | |
APPROVAL FOR ______ ONLY
|
|
Wording
|
| | |
This approval is for a Maintenance and Repair of a Holding Tank only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
SITE PLAN CHANGES
|
|
Wording
|
| | |
The site plan as submitted with the Maintenance and Repair of a Holding Tank application on March 30th, 2017 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the approved site plan shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
Stormwater BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|