Permit Case Summary

Case Number: Search Help

Case Number:SEP2015-00001 Case Status:Finaled Date Received:1/6/2015
Description:Adding Septic tank, permitting an unpermitted pump tank, Re-locating unpermitted transport line, adding a 2" gravity line from maint building. Existing SEP83-6 filed here. Date Issued:5/20/2015
Applicant: CAPE GEORGE COLONY CLUB Expiration Date:10/4/2015 12:00:00 AM
Site Address:360 MARINA DR Case Finaled:5/13/2016
Parcel No:002123003 Other Cases Parcel Data Map It More Details Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: SEPTIC PERMIT FINALED "F"
Date Completed: 5/13/2016
Disposition: DONE
Description: INSTALLATION START NOTICE
Date Completed: 4/11/2016
Disposition: DONE
Description: Monitoring Agreemt Sent (Fm)
Date Completed: 2/22/2016
Disposition: DONE
Description: INSTALLATION START NOTICE
Date Completed: 12/9/2015
Disposition: DONE
Description: Issue permit (Fm) "A"
Date Completed: 5/20/2015
Disposition: DONE
Description: Issue permit (Fm) "A"
Date Completed: 5/20/2015
Disposition: DONE
Description: Issue permit (Fm) "A"
Date Completed: 3/4/2015
Disposition: DONE
Description: REDESIGN SUBMITTED (Fm) "P"
Date Completed: 3/4/2015
Disposition: DONE
Description: DCD Review Time
Date Completed: 1/30/2015
Disposition: PEND
Description: Septic Permit Application (Fm)
Date Completed: 1/6/2015
Disposition: DONE
Description: Pressure test required
Date Completed: 4/11/2016
Disposition: DONE
Description: Asbuilt drawing submitted
Date Completed: 3/16/2016
Disposition: DONE
Description: Initial Site Inspection by HD
Date Completed: 2/12/2015
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 2/12/2015
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 1/30/2015
Disposition: DONE
Description: Case Entered "P"
Date Completed: 1/8/2015
Disposition:

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: ONGOING MONITORING
Wording H - AS PER WAC 246-272A AND JEFFERSON COUNTY CODE 8.15 ALL ONSITE SEWAGE SYSTEMS REQUIRE THAT A RESTRICTIVE COVENANT REGARDING THE MONITORING OF THE ONSITE SEPTIC SYSTEM BE RECORDED TO THE PROPERTY TITLE. THE PROPERTY OWNER SHALL ASSURE THAT MONITORING IS PROVIDED BY AN APPROVED ENTITY AT THE FREQUENCY DEFINED PER STATE WAC 246-272A AND JEFFERSON COUNTY CODE 8.15 AS ADOPTED OR AMENDED. A COPY OF THE RECORDED OPERATIONS AND MONITORING AGREEMENT IS REQUIRED PRIOR TO FINAL APPROVAL OF THE SEWAGE DISPOSAL PERMIT

Title: pressure test observation
Wording Health Dept. required to observe pressure test with system designer when system fully installed/complete, 48 hours notice to be provided for scheduling.

Title: alternative-asbuilt required
Wording H - An asbuilt drawing and certification of completion by the designer is required prior to final approval.

Title: transport line double cased
Wording Any portion of transport line under a driven way is to be sleeved/cased or equivalent.

Title: water tight tank
Wording Septic tank and pump chamber to be water tight. Extra protection (i.e. Bentonite) to be used around inlet, outlet, and risers due to high water table.

Title: UDC compliance
Wording Approval of this sewage disposal permit does not preclude the permit holder from complying with the Unified Development Code for other/future development on the site.

Title: surface water setback
Wording Setback to surface waters or ordinary high water line is 50' required from tanks.

Title: VIOLATION-limited permit life
Wording This permit was issued to correct a violation of WAC 246-272A for installation of septic components without an approved permit. The permit must be completed within 90 days of the date of issuance.

Title: O & M Manual required
Wording Before final approval is given, the designer shall provide an operations and maintenance manual to the property owner and the Health Department. The manual must instruct the owner of the on site sewage system on the ways to properly operate and maintain all components of the system.

Title: Designer Notification/inspections
Wording Designer must be contacted prior to start of construction and for inspections during installation. DESIGNER IS REQUIRED TO DO A PRECOVER INSPECTION ON ALL TYPES OF SYSTEMS.

Title: Installation Inspection
Wording Notification of the start of construction shall be faxed or emailed to Jefferson County Public Health ONE WORKING DAY prior to start.

Title: Certified Installer Required
Wording This system must be constructed by an installer certified by the Jefferson County Public Health Department per Jefferson County Code 8.15.120 (9) and state code WAC246-272A-0250 due to proximity o the shoreline.

Title: No Building Permit Guaranteed
Wording Approval/issuance of a sewage disposal permit or installation of a septic system does not guarantee the approval of other development or a building permit on this site. Future buildings that require connection to an on-site sewage system (OSS) shall only be approved if the OSS meets the current standards and codes in effect at the time of the building application.

Title: Code Compliance
Wording All construction and development activities must comply with all permit conditions, Washington State and Jefferson County Codes and Recommended Standards and Guidance documents in effect when the permit is issued.

Title: THIS PERMIT
Wording This permit is for: 1) new septic tank, 2) Re-route existing transport line, 3) Add a 2" gravity line from maintenance building. 4) Permitting an un-permitted pump tank

Title: WATER TIGHT
Wording H -All septic components associated with this permit shall be made water tight to prevent flood waters from entering the system.

Title: Follow Flood Ordinance
Wording Flood hazard reduction measures are to be used as required by the Jefferson County Flood Damage Prevention Ordinance 07-0515-06 (Jefferson County Code Chapter 15.15).

Title: Flood Proof Requirement
Wording The applicant shall comply with the following requires per JCC 15.15.080(c) Utilities: (iii) New and replacement sanitary sewage systems shall be designed to minimize or eliminate infiltration of flood waters into the systems and discharges from the systems into flood waters; (iv) On-site waste disposal systems shall be located to avoid impairment to them or contamination from them during flooding.

Title: Stormwater BMPs
Wording The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-FLOOD DEV PERMIT
Wording The proposed septic tank replacement is subject to a flood development permit per Chapter 15.15 Flood Damage Prevention which is incorporated into this permit decision.

Title: F-SHORELINE EXEMPTION
Wording The proposal has been reviewed under JCC 18.25 and approved as an exemption under JCC 18.25.560(2) and per Code Interpretation dated August 26, 2014.

Title: F-CRITICAL AREAS
Wording The proposed septic tank replacement is exempt from Critical Area review under JCC 18.22.070(6) & (21) per Code Interpretation dated August 26, 2014.