Permit Case Summary

Case Number: Search Help

Case Number:SEP2012-00104 Case Status:Finaled Date Received:9/6/2012
Description:info filed to SEP15-15 Date Issued:11/2/2012
Applicant: POPE RESOURCES Expiration Date:11/2/2015 12:00:00 AM
Site Address:1501 WAHL LAKE RD Case Finaled:8/19/2013
Parcel No:801361001 Other Cases Parcel Data Map It More Details Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: SEPTIC PERMIT FINALED "F"
Date Completed: 8/19/2013
Disposition: DONE
Description: Monitoring Agreemt Sent (Fm)
Date Completed: 8/29/2013
Disposition: DONE
Description: INSTALLATION START NOTICE
Date Completed:
Disposition:
Description: Redesign OK-retain date(Fm)"A"
Date Completed: 2/25/2013
Disposition: DONE
Description: REDESIGN SUBMITTED (Fm) "P"
Date Completed: 2/25/2013
Disposition: DONE
Description: Issue permit (Fm) "A"
Date Completed: 11/2/2012
Disposition: DONE
Description: REDESIGN SUBMITTED (Fm) "P"
Date Completed: 11/1/2012
Disposition: DONE
Description: Pending letter; add inf (Fm)
Date Completed: 11/2/2012
Disposition: DONE
Description: Septic Permit Application (Fm)
Date Completed:
Disposition:
Description: Pressure test required
Date Completed: 9/12/2013
Disposition: DONE
Description: Asbuilt drawing submitted
Date Completed: 8/20/2013
Disposition: DONE
Description: Initial Site Inspection by HD
Date Completed: 10/15/2012
Disposition:
Description: Env. Sensitive Area Review-U
Date Completed: 11/2/2012
Disposition: DONE
Description: Case Entered "P"
Date Completed: 9/6/2012
Disposition:
Description: Stormwater Review-U
Date Completed: 11/2/2012
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: ONGOING MONITORING
Wording H - AS PER WAC 246-272A AND JEFFERSON COUNTY CODE 8.15 ALL ONSITE SEWAGE SYSTEMS REQUIRE THAT A RESTRICTIVE COVENANT REGARDING THE MONITORING OF THE ONSITE SEPTIC SYSTEM BE RECORDED TO THE PROPERTY TITLE. THE PROPERTY OWNER SHALL ASSURE THAT MONITORING IS PROVIDED BY AN APPROVED ENTITY AT THE FREQUENCY DEFINED PER STATE WAC 246-272A AND JEFFERSON COUNTY CODE 8.15 AS ADOPTED OR AMENDED. A COPY OF THE RECORDED OPERATIONS AND MONITORING AGREEMENT IS REQUIRED PRIOR TO FINAL APPROVAL OF THE SEWAGE DISPOSAL PERMIT

Title: pressure test observation
Wording Health Dept. required to observe pressure test with system designer when system fully installed/complete, 48 hours notice to be provided for scheduling.

Title: alternative-asbuilt required
Wording H - An asbuilt drawing and certification of completion by the designer is required prior to final approval.

Title: reserve area, alternative
Wording When/if designated reserve area is utilized an alternative system providing an additional level of treatment may be required and must comply with code at the time of application for use.

Title: divert drainage
Wording Divert all sources of drainage, including roof drains away from septic tank and drainfield area.

Title: transport line double cased
Wording The portion of transport line under road is to be sleeved/cased or equivalent.

Title: NO BUILDING PERMIT GUARANTEE
Wording Approval/issuance of a sewage disposal permit does not guarantee the approval of other development or additional building permits on this site. Compliance with other Jefferson County and Washington State Codes is required.

Title: UDC compliance
Wording Approval of this sewage disposal permit does not preclude the permit holder from complying with the Unified Development Code for other/future development on the site.

Title: domestic strength waste
Wording This onsite sewage system is designed for domestic strength wastewater only. Disposal of any other waste strength is considered a violation of this permit.

Title: riser on d-box
Wording Distribution boxes shall be fitted with a riser to grade, constructed of durable materials and a secured lid, adequately sized to allow visible inspection of the liquid level in the box.

Title: Water line setback
Wording 10' separation required between a Water line and all portions of the onsite sewage system; effluent transport line, tanks, treatment and disposal components.

Title: PUMP CHAMBER
Wording Pump chamber shall be water tight and equipped with a control panel outside within line of sight of the pump chamber. The panel shall have an audio and visual alarm, a cycle counter, a Dose counter and elapsed time meter. It shall be UL listed and meet L&I requirements.

Title: O & M Manual required
Wording Before final approval is given, the designer shall provide an operations and maintenance manual to the property owner and the Health Department. The manual must instruct the owner of the on site sewage system on the ways to properly operate and maintain all components of the system.

Title: System capacity/uses
Wording Approval of this permit does not assure the existing septic system has capacity for all uses allowed by current code. Approval of this permit does not assure multiple sewage connections will be allowed in the future.

Title: Designer Notification/inspections
Wording Designer must be contacted prior to start of construction and for inspections during installation. DESIGNER IS REQUIRED TO DO A PRECOVER INSPECTION ON ALL TYPES OF SYSTEMS.

Title: Installation Inspection
Wording Notification of the start of construction shall be faxed or emailed to Jefferson County Public Health ONE WORKING DAY prior to start.

Title: Code Compliance
Wording All construction and development activities must comply with all permit conditions, Washington State and Jefferson County Codes and Recommended Standards and Guidance documents in effect when the permit is issued.

Title: Stormwater BMPs
Wording The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.