Description:
|
| | |
Cancel/withdraw application
|
|
Date Completed:
|
| | |
1/27/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue permit (F)
|
|
Date Completed:
|
| | |
1/7/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Pending letter; add inf (F)
|
|
Date Completed:
|
| | |
1/7/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
5/16/2000
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Stormwater Review
|
|
Date Completed:
|
| | |
12/3/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Review Case
|
|
Date Completed:
|
| | |
12/10/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Critical Area Review
|
|
Date Completed:
|
| | |
12/3/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Pressure test required
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Septic Permit Application (F)
|
|
Date Completed:
|
| | |
5/16/2000
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
pud monitoring
|
|
Wording
|
| | |
AS PER WAC 246-272 ALL ALTERNATIVE SYSTEMS REQUIRE MONITORING. THIS MONITORING IS PROVIDED BY AGREEMENT BETWEEN THE JEFFERSON COUNTY ENVIRONMENTAL HEALTH DIVISION AND THE JEFFERSON COUNTY PUBLIC UTILITY DISTRICT #1. THIS SEWAGE DISPOSAL SYSTEM WILL REQUIRE AN ACTIVE MONITORING CONTRACT WITH THE PUD #1 PRIOR TO FINAL APPROVAL OF THE SEWAGE DISPOSAL SYSTEM.
|
|
|
Title:
|
| | |
pressure test observation
|
|
Wording
|
| | |
Health Dept. required to observe pressure test when system fully installed/complete, 48 hours notice to be provided for scheduling.
|
|
|
Title:
|
| | |
alternative-asbuilt required
|
|
Wording
|
| | |
An asbuilt drawing and certification of completion by the designer is required prior to final approval.
|
|
|
Title:
|
| | |
well setback requirement
|
|
Wording
|
| | |
Setbacks to all wells- 100' required from drainfield and reserve areas. 50' required from tanks and effluent transport lines. Property abandoned well setbacks are 10' from any portion of system.
|
|
|
Title:
|
| | |
other setbacks req.
|
|
Wording
|
| | |
10' min. horizontal separation between any portion of drainfield and reserve areas and any water lines. Compliance with Department of Ecology Sewage Works Design criteria required if not conforming to minimum setbacks.
|
|
|
Title:
|
| | |
trench depth
|
|
Wording
|
| | |
MAXIMUM TRENCH DEPTH 12 INCHES, no sand lining.
|
|
|
Title:
|
| | |
reserve area, alternative
|
|
Wording
|
| | |
When/if designated reserve area is utilized an alternative system providing an additional level of treatment may be required.
|
|
|
Title:
|
| | |
protection from vehicular traffic
|
|
Wording
|
| | |
All components of the septic system are to be completely protected from vehicular traffic or mechanical disturbance.
|
|
|
Title:
|
| | |
staking of drainfield
|
|
Wording
|
| | |
Contact designer prior to installation for staking of drainfield area.
|
|
|
Title:
|
| | |
dose counter
|
|
Wording
|
| | |
Dose counters are required in the control panel for all drainfield components.
|
|
|
Title:
|
| | |
divert drainage
|
|
Wording
|
| | |
Divert all sources of drainage, including roof drains away from septic tank and drainfield area.
|
|
|
Title:
|
| | |
transport line double cased
|
|
Wording
|
| | |
Any portion of transport line under a driven way is to be double cased or equivalent.
|
|
|
Title:
|
| | |
water tight tank
|
|
Wording
|
| | |
Septic tank and pump chamber to be water tight. Extra protection (i.e. Bentonite) to be used around inlet, outlet, and risers due to high water table.
|
|
|
Title:
|
| | |
treatment standard
|
|
Wording
|
| | |
This system meets Treatment Standard II as required for mitigation in an aquifer recharge area. Annual monitoring required.
|
|
|
Title:
|
| | |
no building permit guarantee
|
|
Wording
|
| | |
Approval/issuance of a sewage disposal permit does not guarantee the approval of other development or a building permit on this site. Compliance with other Jefferson County and Washington State Codes is required.
|
|
|
Title:
|
| | |
UDC compliance
|
|
Wording
|
| | |
Approval of this sewage disposal permit does not preclude the permit holder from complying with the Unified Development Code for other/future development on the site.
|
|
|
Title:
|
| | |
env. sensitive area conditions
|
|
Wording
|
| | |
Compliance with the Environmentally Sensitive Areas Review conditions is required.
|
|
|
Title:
|
| | |
risers
|
|
Wording
|
| | |
Risers are required to grade with secured lids over the inlet and outlet of the septic tank. Minimum 24" riser over inlet.
|
|
|
Title:
|
| | |
reduced size df
|
|
Wording
|
| | |
Performance monitoring schedule for treatment systems followed by reduced sized drainfield/infiltrative area shall be :1) Two times per year (once every six months) during the first and second year following installation. 2) One time per year beginning with the third year following installation. 3) In response to complaints or problems.
Observation ports to the bottom of the trench are to be installed in at least two places on each drainfield line: One within 10 feet of the end of each line.
|
|
|
Title:
|
| | |
surface water setback
|
|
Wording
|
| | |
Setback to surface waters- 100' required from drainfield and reserve areas. 50' required from tanks.
|
|
|
Title:
|
| | |
protective barriers
|
|
Wording
|
| | |
Permanent barriers are required along/around primary and reserve drainfield areas to protect from parking, driving, and other land disturbing activities prior to final.
|
|
|
Title:
|
| | |
FLOOD -NO HOLD
|
|
Wording
|
| | |
Additional measured to be taken to assure that no infiltration occurs into tanks and sand filter during flood events. Risers to be fitted with water tight seal, no vented lids. Designed to meet flood damage prevention per ordinance #18-1120-95
|
|
|
Title:
|
| | |
ARCHEOLOGIC -NO HOLD
|
|
Wording
|
| | |
The area is know to have historical and cultural deposits. In the event of discovery of such deposits, including shell middens, work shall CEASE. Contact engineer and the health department.
|
|
|
Title:
|
| | |
ROAD CROSSING-NO HOLD
|
|
Wording
|
| | |
Compliance with conditions of road crossing permit is required.
|
|
|
Title:
|
| | |
BLA-NO HOLD
|
|
Wording
|
| | |
The site has been modified through an approved boudaary line adjustment, recorded on 8/10/01.
|
|
|
Title:
|
| | |
Stormwater BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|