Permit Case Summary

Case Number: Search Help

Case Number:SDP2020-00021 Case Status:Pending Date Received:1/1/2021
Description:Shoreline conditional use, shoreline substantial development, and flood development application to improve an existing public boat launch at Point Whitney. Washington Department of Fish and Wildlife (WDFW) is proposing to leave the existing launch in place and to install new planks with steel bars/rails. This will raise the elevation of the ramp while keeping it in the same footprint. The improved ramp would not be above the average existing beach grade. The proposed ramp will be raised to improve safety and reduce impacts on beach substrates in the area. Mitigation proposed by WDFW includes previously-completed grading at the west end of the point to match the beach grade and use of the Hood Canal Coordinating Council In-lieu Fee program. The applicant submitted an Eelgrass Delineation report, a Coastal Processes Assessment and Design Considerations report, and a Habitat Management Plan. The applicant also submitted WDFW government-government consultation letters with Washington Department of Archaeology and Historic preservation and with Tribes. The proposal is subject to review under the State Environmental Policy Act (SEPA) and WDFW acted as the lead agency for SEPA. Date Issued:
Applicant: STATE OF WASHINGTON -FISH/WDLF Expiration Date:
Site Address:1000 POINT WHITNEY RD Case Finaled:
Parcel No:601071001 Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: DRD Reviewer Letter (F)
Date Completed: 11/3/2021
Disposition: DONE
Description: Ntc of App +30-Publish-UF
Date Completed:
Disposition:
Description: Ntc of App +30-APO-UF
Date Completed:
Disposition:
Description: Ntc of App +30-APO-UF
Date Completed:
Disposition:
Description: A Clock Interrupt
Date Completed: 10/27/2021
Disposition: DONE
Description: Additional Info Request-DRD
Date Completed: 10/27/2021
Disposition: DONE
Description: Updated/Add'l Info Recv'd
Date Completed: 1/21/2021
Disposition: DONE
Description: Updated/Add'l Info Recv'd
Date Completed: 1/19/2021
Disposition: DONE
Description: Updated/Add'l Info Recv'd
Date Completed: 1/7/2021
Disposition: DONE
Description: Consistency Review-U
Date Completed:
Disposition:
Description: Env. Sensitive Area Review-U
Date Completed:
Disposition:
Description: Stormwater Review-U
Date Completed:
Disposition:
Description: App Substantially Complete-U
Date Completed: 10/27/2021
Disposition: DONE
Description: Case Entered
Date Completed: 1/1/2021
Disposition: