Permit Case Summary

Case Number: Search Help

Case Number:SDP2017-00011 Case Status: Date Received:8/17/2017
Description:SHORELINE SUBSTANTIAL DEVELOPMENT & SHORELINE CONDITIONAL USE PERMIT WITH SEPA REVIEW (SUBJECT TO A STORMWATER MANAGEMENT PERMIT) The Western Federal Lands Highway Division (WFLHD) of the Federal Highway Administration (FHWA), in partnership with Jefferson County, proposes to construct bank stabilization and bridge and culvert improvements in six locations along the Upper Hoh River Road (UHRR). The proposed project will develop and implement bank stabilization solutions at three locations along the UHRR, and will replace or improve three existing bridge or culvert locations. The roadway at these sites is at risk of washing away in a large flood. Bank stabilization will consist of installing engineered log jams (ELJs) with dolosse at the three sites. ELJs are collections of large woody debris (LWD) that when placed in a river or other water body, redirect flow and increase stability to a bank or downstream gravel bar. Installation is patterned after stable, naturally-occurring log jams, which are usually formed by large trees with rootwads attached that stabilize and anchor other debris that accumulate against the trees. Specifically, bank stabilization activities will occur at Sites C1, C2, and C4 and will occur in and directly adjacent to the Hoh River. Culvert replacement will occur at MP 4.38 of the UHRR. Bridge replacement will occur at Sites C3 and C5. The application submittal includes construction plans and a temporary erosion and sediment control plan prepared by FHWA for the project as well as the Lindner Creek Mitigation Site. Permanent riparian and wetland impacts are shown in JARPA figures. The project is proposed to occur between Summer 2018 and Fall 2020. The submittal includes a Joint Aquatic Resource Protection Application, Biological Assessment and Survey, 2015 Wetland Delineation Report, 2017 Wetland Addendum and a Wetland Mitigation Plan, Hydraulic Report, Upper Hoh River Bank Failure Risk Reduction Study, Logs and Soils Test Results, and WDNR Mass Wasting Module Level II Assessment. Final authority for shoreline conditional use permit decisions rests with the Washington State Department of Ecology. The project is subject to a Washington Department of Fish and Wildlife Hydraulic Project Approval, Clean Water Act Section 404 and 401 Water Quality Certification administered by Department of Ecology, Dept. of Natural Resources Aquatic Lease Authorization, Section 7 of the Endangered Species Act administered by NOAA fisheries; Section 106 of the National Historic Preservation Act administered by Dept. of Archaeological and Historic Preservation, and Coastal Zone Management Certification by Department of Ecology. Date Issued:5/10/2018
Applicant: JEFFERSON CO. PUBLIC WORKS Expiration Date:5/10/2023 12:00:00 AM
Site Address: .................... Case Finaled:
Parcel No:712253000 Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Status updtd - Energov Convrsn
Date Completed: 10/4/2022
Disposition: DONE
Description: File Archived
Date Completed: 11/7/2019
Disposition: DONE
Description: Issue CUP/Variance Permit
Date Completed: 5/10/2018
Disposition:
Description: Print Dummy UDC Permit-UF
Date Completed: 5/3/2018
Disposition:
Description: Override - Parcel Holds
Date Completed: 5/3/2018
Disposition:
Description: Override - Parcel Holds
Date Completed: 5/3/2018
Disposition:
Description: Override - Parcel Holds
Date Completed: 5/3/2018
Disposition:
Description: Override - Parcel Holds
Date Completed: 5/3/2018
Disposition:
Description: DRD Reviewer Letter (F)
Date Completed: 3/7/2018
Disposition:
Description: Updated/Add'l Info Recv'd
Date Completed: 3/7/2018
Disposition:
Description: A Clock Interrupt
Date Completed: 3/7/2018
Disposition: DONE
Description: Additional Info Request-DRD
Date Completed: 3/7/2018
Disposition: DONE
Description: DRD Reviewer Letter (F)
Date Completed: 11/7/2017
Disposition:
Description: Ntc of App +30-Publish-UF
Date Completed: 8/31/2017
Disposition:
Description: Ntc of App +30-APO-UF
Date Completed: 8/31/2017
Disposition: DONE
Description: Consistency Review-U
Date Completed: 5/3/2018
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 5/3/2018
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 5/3/2018
Disposition: DONE
Description: App Substantially Complete-U
Date Completed: 8/29/2017
Disposition: DONE
Description: Case Entered
Date Completed: 8/17/2017
Disposition:

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: STAFF REPORT CONDITIONS
Wording See Staff Report for conditions


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-STAFF REPORT
Wording See staff report for findings.