Case Number:SDP2016-00027 Case Status: Date Received:9/23/2016
Description:SHORLINE EXEMPTION with Stormwater Management Permit and Flood Development Permit: Upgrade stormwater managment facilities to include on-site infiltration of stormwater into below-grade infiltration bed, with large storm event overflow into the marina (mimicking existing conditions). The project development consists of replacing a failed stormwater catch basin and infiltration trench with 2 new catch basins and a new 40’ long x 15’ wide x 1.5’ deep infiltration bed. The elevation of the trench bottom is proposed to maintain 12” of vertical separation above a tidally influenced ground water table. The stormwater flowing into the existing catch basin is from approximately 11,000 sf of paved parking lot. The new stormwater system is proposed to replace the existing, and increase its size to receive stormwater from 15,000 sf of paved and gravel driving surfaces. Date Issued:1/5/2017
Applicant: CAPE GEORGE COLONY CLUB Expiration Date:1/5/2022 12:00:00 AM
Site Address:312 MARINA DR Case Finaled:
Parcel No:002123003 Other Cases Parcel Data Map It Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Status updtd - Energov Convrsn
Date Completed: 10/4/2022
Disposition: DONE
Description: File Archived
Date Completed: 11/6/2019
Disposition: DONE
Description: Updated/Add'l Info Recv'd
Date Completed: 1/5/2017
Disposition:
Description: Updated/Add'l Info Recv'd
Date Completed: 1/5/2017
Disposition:
Description: A Clock Interrupt
Date Completed: 1/5/2017
Disposition: DONE
Description: Additional Info Request-DRD
Date Completed: 1/5/2017
Disposition: DONE
Description: A Clock Interrupt
Date Completed: 12/22/2016
Disposition:
Description: Additional Info Request-DRD
Date Completed: 12/22/2016
Disposition: DONE
Description: Updated/Add'l Info Recv'd
Date Completed: 12/22/2016
Disposition: DONE
Description: DRD Reviewer Letter (F)
Date Completed: 12/5/2016
Disposition:
Description: Invoice for DPW Sent
Date Completed: 12/1/2016
Disposition:
Description: Updated/Add'l Info Recv'd
Date Completed: 11/23/2016
Disposition: DONE
Description: Updated/Add'l Info Recv'd
Date Completed: 11/10/2016
Disposition: DONE
Description: Additional Info Request-DRD
Date Completed: 11/10/2016
Disposition:
Description: A Clock Interrupt
Date Completed: 11/10/2016
Disposition:
Description: Updated/Add'l Info Recv'd
Date Completed: 10/19/2016
Disposition: DONE
Description: A Clock Interrupt
Date Completed: 10/19/2016
Disposition:
Description: Incomplete App Request Info
Date Completed: 10/19/2016
Disposition:
Description: Consistency Review-U
Date Completed: 1/5/2017
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 1/5/2017
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 1/5/2017
Disposition: DONE
Description: App Substantially Complete-U
Date Completed: 1/3/2017
Disposition: DONE
Description: Case Entered
Date Completed: 9/23/2016
Disposition:

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: CONSTRUCTION METHODS AND MATERIAL
Wording Construction Materials and Methods: (1) All new construction and substantial improvements shall be constructed with materials and utility equipment resistant to flood damage; and (2) All new construction and substantial improvements shall be constructed using methods and practices that minimize flood damage.

Title: FILL MATERIALS
Wording Fill materials placed within shoreline jurisdiction shall be from an approved source and shall consist of clean sand, gravel, soil, rock or similar material. The use of contaminated material or construction debris shall be prohibited.ditions.

Title: PW PRE-CONSTRUCTION MEETING
Wording The proponent shall notify Jefferson County Public Works (JCPW) regarding the date of a Preconstruction Meeting.

Title: BMP'S INSTALLED PRIOR TO START
Wording All applicable temporary erosion control measures shall be installed prior to the start of construction.

Title: PUBLIC WORKS INSPECTION
Wording In accordance with the Jefferson County Unified Development Code, Section 18.30.080 (1) (f): Clearing, grading, and construction of roads, bridges, utilities, and stormwater management facilities shall be inspected by JCPW. In order to enable the department to conduct inspections in a timely manner, the applicant shall notify the department in a timely manner regarding the project construction schedule. Typical Inspections: • Installation of temporary erosion and sediment control measures • Construction of stormwater management facilities; • (Additional inspections may be deemed necessary as project progresses.)

Title: SWT CERTIFICATION
Wording After construction is complete and prior to final DCD project approval, the proponent shall submit a letter to the Public Works Department and Department of Community Development, from the Engineer of Record (EOR), certifying that the stormwater management facilities have been constructed per the approved plans & specifications. It is the responsibility of the proponent to schedule inspections with the E.O.R., his designee &/or qualified inspection firm(s), approved by the E.O.R., to provide for said final certification.

Title: PROGRESS TOWARDS COMPLETION
Wording Substantial progress towards completion of the project shall be performed within two years of the issuance of the permit.

Title: MIN REQ #2
Wording The parcel area is approximately 8 acres. It has approximately 39% of its area covered with hard surfaces consisting of buildings, trafficked gravel and pavement. The construction of the proposed stormwater facility will have approximately 700 square feet (sf) of land disturbing activity. As such, in accordance with the flow charts Figures 2.4.1 and 2.4.2 of the 2014 SWMMWW, the project needs to meet Minimum Requirement #2.

Title: Follow Flood Ordinance
Wording Flood hazard reduction measures are to be used as required by the Jefferson County Flood Damage Prevention Ordinance 07-0515-06 (Jefferson County Code Chapter 15.15).

Title: Utilities-Flood
Wording Utilities shall be designed as specified in 15.15.080(c) of Jefferson County Flood Damage Prevention Ordinance 07-0515-06 (Jefferson County Code Chapter 15.15) which states: (i) All new and replacement water supply systems shall be designed to minimize or eliminate infiltration of flood waters into the systems; (ii) Water wells shall be located on high ground that is not in the floodway; (iii) New and replacement sanitary sewage systems shall be designed to minimize or eliminate infiltration of flood waters into the systems and discharges from the systems into flood waters; (iv) Onsite waste disposal systems shall be located to avoid impairment to them or contamination from them during flooding.

Title: Anchoring-Flood
Wording 1) All new construction and substantial improvements shall be anchored to prevent flotation, collapse, or lateral movement of the structure. 2) All manufactured homes shall be anchored to prevent flotation, collapse, or lateral movement, and shall be installed using methods and practices that minimize flood damage. Anchoring methods may include, but are not limited to, use of over-the top or frame ties to ground anchors.

Title: Coastal & At Risk SIPZ-Water Con
Wording VOLUNTARY MEASURES OF COASTAL & AT RISK SIPZ: Water conservation measures: 1. Roof and other intercepted precipitation shall be routed to on-site detention ponds and/or other approved means and allowed to be released to the soil slowly. 2. Water collected from Storm water and roof catchments may be used for watering lawns and gardens. Unless catchment water has been treated to meet drinking water standards, there shall be no cross connections allowed between the potable supply and impounded water. 3. Water withdrawn from wells on each property shall not be used for watering of lawns and/or gardens. 4. Ground water withdrawn from each property shall be restricted to a rate of three (3) gallons per minute. 5. Installation of water conserving fixtures such as low flow toilets, faucets and shower restrictors and other water saving plumbing fixtures. 6. Landscaping plan (xeriscaping, native vegetation with minimal amounts of irrigation). Please NOTE that the above listed measures are not intended to be exhaustive, but rather is intended to be illustrative of the types of water conservation measures.

Title: Coastal & At Risk SIPZ-Measures
Wording VOLUNTARY MEASURES OF COASTAL & AT RISK SIPZ: 1. Installation of a flow meter. 2. On-going well monitoring for chloride concentration. 3. Submittal of monitoring data to County.

Title: BMPs
Wording The proponent shall install the stormwater management facilities and implement the Best Management Practices (BMP’s) per the approved Stormwater Site Plan.The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.

Title: Stormwater Plan
Wording Plans for stormwater improvements with a Construction Storwmater Pollution Prevention Plan were submitted by Streamline Environmental, Everett Sorensen PE engineer of record, starting September 13, 2016, with final revisions received December 22, 2016 and have been approved by the Department of Community Development. Once the subject permit has been issued the applicant shall fully implement the provisions of the submitted plan.

Title: Hydraulic Code/HPA Check
Wording Prior to commencing development activity, proponent is responsible for informing the Washington Department of Fish and Wildlife (WDFW) in order for WDFW to determine whether this action is subject to the Washington State Hydraulic Code (Chapter 220-10 WAC). Hydraulic Project Approval (HPA) is required for all hydraulic projects, which are defined as construction or performance of other work that will use, divert, obstruct, or change the natural flow or bed of any of the salt or fresh waters of the state.

Title: Army Corps Check
Wording Prior to commencing development activity, the proponent is responsible for informing the US Army Corps of Engineers (COE) in order for COE to determine whether a Department of the Army permit or review is required. Generally, review is required for construction and dredging in or around navigable waters of the US and for work or fill in hydrologically connected wetlands. Contact the US Army Corps of Engineers, Seattle District Regulatory Branch, PO Box 3755, Seattle WA 98124, (206) 764-3495, for more information.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-FLOOD DEVELOPMENT
Wording The proposal will be located in Discovery Bay, in an area that is mapped on the Federal Emergency Management Agency Flood Insurance Rate Map (panel 5300690135B) as Zone A. The proposed project is subject to the requirement for a flood development permit, which is incorporated into this decision. The proposal meets the definition of development but not structure in the flood damage prevention ordinance, as codified in JCC 15.15.050.

Title: F-NO FLOOD LEVEL INCREASE
Wording The proposed project will not result in any increase in flood levels during the occurrence of base flood discharges

Title: F-FEMA BI-OP EXEMPT
Wording The project is exempt from compliance with the FEMA Habitat Assessment requirements under Model Ordinance 7.2 subsection A. The repair of the drainage system is not a substantial improvement or a repair of substantial damage.

Title: F-SHORELINE EXEMPTION
Wording This project was reviewed and approved as a Shoreline Exemption under JCC 18.25.560(2).

Title: F-STORMWATER CODE INTERPRETATION
Wording This proposal is consistent with the Jefferson County Code Interpretation dated November 3, 2015 for stormwater improvement repairs to an existing legal non-confomring structure in shoreline jurisdiction within the standard shoreline buffer. The proposed stormwater improvement is exempt from critical area review under JCC 18.22.070(6) and (21).

Title: F-COMMERCIAL FACILITY
Wording The associated parcel (002 123 003) is located within the shoreline of Discovery Bay and subject to UDC Section 18.25 Shoreline Master Program. The Maintenance Shop and associated paved parking area are considered a commercial facility owned by the Cape George Colony Club

Title: F-Confirmed ESAs
Wording The application was reviewed by the Jefferson County Department of Community Development staff on September 28, 2016 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property:nearshore marine habitat (Fish and Wildlife Habitat Conservation Area), unstable shoreline slope stability, seismic hazard area, FEMA special flood hazard area, susceptible aquifer recharge area, coastal seawater intrusion protection zone.

Title: F-Aquifer Recharge Area
Wording Aquifer Recharge Areas in Jefferson County are characterized by porous geological formations that allow percolation of the surface water into the soils and the underlying zone of saturation. Aquifers are geologic formations that contain sufficient saturated permeable material to yield significant quantities of water to wells and springs. Aquifers serve as the source of drinking water within most of the rural portions of Jefferson County.

Title: F-Susc. Aquifer Recharge Area
Wording Susceptible Aquifer Recharge Areas are those with geologic and hydrologic conditions that promote rapid infiltration of recharge waters to groundwater aquifers.

Title: F-Geohazard Area
Wording Geologically Hazardous Areas in Jefferson County are characterized by slope, soil type, geologic material, and groundwater that may combine to create problems with slope stability, erosion, and water quality during and after construction or during natural events such as earthquakes or severe rainstorms.

Title: F-SIPZ
Wording Marine shorelines and islands are susceptible to a condition that is known as seawater intrusion. Seawater intrusion is a condition in which the saltwater/freshwater interface in an aquifer moves inland so that wells drilled on upland areas cannot obtain freshwater suitable for public consumption without significant additional treatment and cost. Maintaining a stable balance in the saltwater/freshwater interface is primarily a function of the rate of aquifer recharge (primarily through rainfall) and the rate of groundwater withdrawals (primarily through wells). The Washington Department of Ecology is the agency with statutory authority to regulate groundwater withdrawal for individual wells in Jefferson County. New development, redevelopment, and land use activities on islands and in close proximity to marine shorelines in particular should be developed in such a manner to maximize aquifer recharge and maintain the saltwater/freshwater balance to the maximum extent possible by infiltrating stormwater runoff so that it recharges the aquifer.

Title: F-Coastal SIPZ
Wording The parcel is located within a coastal SIPZ (seawater intrusion protection zone) according to the County GIS map. There are voluntary and mandatory measures identified in the Jefferson County Seawater Intrusion Policy (Resolution 61-02, effective September 23, 2002) that apply to well drilling proposals and building permit applications on existing lots of record. A Coastal SIPZ is defined as: all islands and area within one-quarter mile of marine shoreline, but no history of chloride concentration above 100 mg/L in groundwater sources within 1000 feet.

Title: F-SEPA Exempt
Wording Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(3).

Title: F-Site Plan Changes
Wording The revised site plan as submitted with the replacement stormwater system application on December 22, 2016 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved revised site plan dated January 5, 2017 shall be resubmitted for review and approval by Jefferson County Department of Community Development.

Title: F-Approval for _____ Only
Wording This approval is for a replacement stormwater system only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.

Title: F-General PMT Notice
Wording NOTICE: This permit does not excuse the proponent from complying with other local, state, and federal ordinances, regulations, or statutes applicable to the proposed development, but consistent with RCW 90.58. Development pursuant to this permit shall be undertaken subject to the applicable policies and performance standards of the Jefferson County Shoreline Management Master Program and the Jefferson County Unified Development Code. If during excavation or development of the site an area of potential archaeological significance is uncovered, all activity in the immediate area shall be halted, and the Administrator shall be notified at once. The Federal Endangered Species Act rules to protect threatened Chinook and Summer-run Chum salmon became effective on January 8, 2001. Bull trout have been listed as threatened since early 2000. Under the ESA, any person may bring lawsuit against any individual or agency that "takes" listed species (defined as causing harm, harassing, or damaging habitat for the listed species). In addition, the National Marine Fisheries Service can levy penalties. Portions of Jefferson County, including marine environments are included as "critical habitat" for listed species. Development of property along any marine shoreline, freshwater shoreline, or floodplains could harm habitat if protective measures are not taken. To minimize the potential to damage habitat, all property owners developing adjacent to marine shoreline, freshwater shoreline, or floodplains are advised to do the following: - All development activities should avoid unstable slopes, wetlands, and forested areas near surface waters - Remove minimal vegetation for site development, especially large trees - Allow trees that have fallen into surface waters to remain there - Infiltrate stormwater from buildings and driveways onsite through drywells rather than discharging directly into surface waters or roadside ditches The Federal Bald and Golden Eagle Protection Act requires landowners within 660 feet (1/8th of a mile) of an eagle nest to consult with the US Fish and Wildlife Service. This Eagle Act prohibits anyone from "taking" bald eagles. This federal law defines the term "take" and describes the possible legal consequences when a "take" occurs. Among other actions, "take" includes a disturbance of bald eagles or their habitat. Under federal law a permit may still be required for activities that impact bald eagles or their habitat. Contact the US Fish and Wildlife Service (http://www.fws.gov/pacific/eagle/) to learn more about how this law affects your project. Any individual, group, or agency can bring suit for a listed species "taking", even if you are in compliance with Jefferson County development codes. The risk of a lawsuit against you can be reduced by consulting with a professional fisheries habitat biologist, and following the recommendations for site development provided by the biologist. For more information, contact the National Marine Fisheries Service in Seattle, or the U.S. Fish and Wildlife Service.