Permit Case Summary

Case Number: Search Help

Case Number:SDP2012-00017 Case Status: Date Received:3/26/2012
Description:SHORELINE EXEMPTION for chip seal w/guardrail repair to Highway 101 from Mile Post MP 296.65 - 296.88. Repair consists of chip sealing existing HMA lanes and shoulders and to raise existing guardrails as needed. MP 296.70 to MP 296.88 chip seal existing HMA lanes and shoulders and raise existing guardrail as needed. MP 296.79 to MP 296.81 remove existing guardrail anchor, install guardrail pad and non-flared terminal and MP 296.69 to MP 299.5 add centerline rumble strips; fill above ordinary high water mark. Date Issued:4/6/2012
Applicant: STATE OF WASHINGTON-DOT Expiration Date:4/6/2013 12:00:00 AM
Site Address:HWY 101 Case Finaled:
Parcel No:000000220 Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Status updtd - Energov Convrsn
Date Completed: 10/4/2022
Disposition: DONE
Description: File Archived
Date Completed: 8/2/2018
Disposition: DONE
Description: Approve Exemption-UF
Date Completed: 4/6/2012
Disposition: DONE
Description: Review Complete-U
Date Completed: 4/6/2012
Disposition: DONE
Description: Det. of Completeness-UF
Date Completed: 4/6/2012
Disposition: DONE
Description: Case Entered
Date Completed: 3/26/2012
Disposition:
Description: App Substantially Complete-U
Date Completed: 4/6/2012
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 4/6/2012
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 4/6/2012
Disposition: DONE
Description: Consistency Review-U
Date Completed: 4/6/2012
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: Discharge oil: state & fed regs
Wording The proponents shall comply with all relevant state and federal regulations pertaining to the discharge of oil.

Title: Other Work/Separate Approval
Wording Work within the jurisdiction of the Shoreline Master Program other than as described above shall receive separate review from this Department.

Title: Progress towards completion
Wording Substantial progress towards completion of the project shall be performed within two years of the issuance of the permit.

Title: Exempt Maintenance Condition
Wording The development shall be essentially the same as the original in location, size, configuration, and external appearance.

Title: BMPs
Wording The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.

Title: Hydraulic Code/HPA Check
Wording Prior to commencing development activity, proponent is responsible for informing the Washington Department of Fish and Wildlife (WDFW) in order for WDFW to determine whether this action is subject to the Washington State Hydraulic Code (Chapter 220-10 WAC). Hydraulic Project Approval (HPA) is required for all hydraulic projects, which are defined as construction or performance of other work that will use, divert, obstruct, or change the natural flow or bed of any of the salt or fresh waters of the state.

Title: Comply with HPA
Wording In addition to Jefferson County permit conditions, the project proponent shall comply with all conditions set forth by the Washington Department of Fish and Wildlife through Hydraulic Project Approval.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-PROJECT DESCRIPTION
Wording Rehabilitate the exisitng pavement with bituminous surface treatment (BST) to extend the service of the roadway an dincrease the pavement rating. Chip seal w/guardrail repair to Highway 101 from Mile Post MP 296.65 - 296.88. Repair consists of chip sealing existing HMA lanes and shoulders and to raise existing guardrails as needed. MP 296.70 to MP 296.88 chip seal existing HMA lanes and shoulders and raise existing guardrail as needed. MP 296.79 to MP 296.81 remove existing guardrail anchor, install guardrail pad and non-flared terminal and MP 296.69 to MP 299.5 add centerline rumble strips; fill above ordinary high water mark.

Title: F-18.22 EXEMPT
Wording This project is exemption from Critical Area protection standards under JCC 18.22.070(3).

Title: F-Confirmed ESAs
Wording The application was reviewed by the Jefferson County Department of Community Development staff on April 5, 2012 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: conservancy shoreline designation; spotted owl, eagle, osprey; wetlands; seismic; slight and moderate landslide hazard area; erosion; SUSC aquifer recharge area; high risk channel migration zone.

Title: F-Aquifer Recharge Area
Wording Aquifer Recharge Areas in Jefferson County are characterized by porous geological formations that allow percolation of the surface water into the soils and the underlying zone of saturation. Aquifers are geologic formations that contain sufficient saturated permeable material to yield significant quantities of water to wells and springs. Aquifers serve as the source of drinking water within most of the rural portions of Jefferson County.

Title: F-Susc. Aquifer Recharge Area
Wording Susceptible Aquifer Recharge Areas are those with geologic and hydrologic conditions that promote rapid infiltration of recharge waters to groundwater aquifers.

Title: F-Geohazard Area
Wording Geologically Hazardous Areas in Jefferson County are characterized by slope, soil type, geologic material, and groundwater that may combine to create problems with slope stability, erosion, and water quality during and after construction or during natural events such as earthquakes or severe rainstorms.

Title: F-SEPA Exempt
Wording Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(2)(c).

Title: F-Site Plan Changes
Wording The site plan as submitted with the shoreline substantial development permit exemption application on March 26, 2012 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated April 6, 2012 shall be resubmitted for review and approval by Jefferson County Department of Community Development.

Title: F-Approval for _____ Only
Wording This approval is for a SR 101 road repair from MP 296.65 to MP 299.50 only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.

Title: F-General PMT Notice
Wording NOTICE: This permit does not excuse the proponent from complying with other local, state, and federal ordinances, regulations, or statutes applicable to the proposed development, but consistent with RCW 90.58. Development pursuant to this permit shall be undertaken subject to the applicable policies and performance standards of the Jefferson County Shoreline Management Master Program and the Jefferson County Unified Development Code. If during excavation or development of the site an area of potential archaeological significance is uncovered, all activity in the immediate area shall be halted, and the Administrator shall be notified at once. The Federal Endangered Species Act rules to protect threatened Chinook and Summer-run Chum salmon became effective on January 8, 2001. Bull trout have been listed as threatened since early 2000. Under the ESA, any person may bring lawsuit against any individual or agency that "takes" listed species (defined as causing harm, harassing, or damaging habitat for the listed species). In addition, the National Marine Fisheries Service can levy penalties. All areas in Jefferson County are included as "critical habitat" for a listed species. Development of property along any marine shoreline, freshwater shoreline, or floodplains could harm habitat if protective measures are not taken. To minimize the potential to damage habitat, all property owners developing adjacent to marine shoreline, freshwater shoreline, or floodplains are advised to do the following: - All development activities should avoid unstable slopes, wetlands, and forested areas near surface waters - Remove minimal vegetation for site development, especially large trees - Allow trees that have fallen into surface waters to remain there - Infiltrate stormwater from buildings and driveways onsite through drywells rather than discharging directly into surface waters or roadside ditches The Federal Bald and Golden Eagle Protection Act requires landowners within 660 feet (1/8th of a mile) of an eagle nest to consult with the US Fish and Wildlife Service. This Eagle Act prohibits anyone from "taking" bald eagles. This federal law defines the term "take" and describes the possible legal consequences when a "take" occurs. Among other actions, "take" includes a disturbance of bald eagles or their habitat. Under federal law a permit may still be required for activities that impact bald eagles or their habitat. Contact the US Fish and Wildlife Service (http://www.fws.gov/pacific/eagle/) to learn more about how this law affects your project. Any individual, group, or agency can bring suit for a listed species "taking", even if you are in compliance with Jefferson County development codes. The risk of a lawsuit against you can be reduced by consulting with a professional fisheries habitat biologist, and following the recommendations for site development provided by the biologist. For more information, contact the National Marine Fisheries Service in Seattle, or the U.S. Fish and Wildlife Service.

Title: F-SDP Exemption Section
Wording The Development Review Division finds that this proposal is consistent with Shoreline Master Program Section JCC 18.25.090(6) and is consequently exempt from the substantial development permit (SDP) requirements. Exemptions from the substantial development permit requirements do not exempt a proposed development from compliance with the applicable policies and standards of the Shoreline Master Program or other applicable Federal, State, or local permit or license requirements.