Permit Case Summary

Case Number: Search Help

Case Number:SDP2010-00007 Case Status: Date Received:1/20/2010
Description:SHORELINE EXEMPTION FOR RUMBLE STRIP FROM MP 165.05 TO MP 184.62 Date Issued:3/23/2010
Applicant: STATE OF WASHINGTON-DOT Expiration Date:3/23/2011 12:00:00 AM
Site Address:HWY 101 Case Finaled:
Parcel No:000000220 Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Status updtd - Energov Convrsn
Date Completed: 10/4/2022
Disposition: DONE
Description: File Archived
Date Completed: 4/11/2018
Disposition: DONE
Description: Approve Exemption-UF
Date Completed: 3/23/2010
Disposition: DONE
Description: Review Complete-U
Date Completed: 3/23/2010
Disposition: DONE
Description: Case Entered
Date Completed: 1/20/2010
Disposition:
Description: App Substantially Complete-U
Date Completed: 3/23/2010
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 3/23/2010
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 3/23/2010
Disposition: DONE
Description: Consistency Review-U
Date Completed: 3/23/2010
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: Other Work/Separate Approval
Wording Work within the jurisdiction of the Shoreline Master Program other than as described above shall receive separate review from this Department.

Title: Progress towards completion
Wording Substantial progress towards completion of the project shall be performed within two years of the issuance of the permit.

Title: Exempt Maintenance Condition
Wording The development shall be essentially the same as the original in location, size, configuration, and external appearance.

Title: JCC 18.22 CRITICAL AREAS
Wording This project is exempt from critical area review and protection standards under JCC 18.22.070(3) when undertaken persuant to best management practices to minimize impacts to critical areas and to immediately restore any disturbed area or its buffer.

Title: BMPs
Wording The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-Confirmed ESAs
Wording The application was reviewed by the Jefferson County Department of Community Development staff on March 23, 2010 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: Fish & Wildlife Habitat Areas; Wetlands. This project is exempt from the protection standards under JCC 18.22.070.

Title: F-SEPA Exempt
Wording Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(1)(u).

Title: F-Site Plan Changes
Wording The site plan as submitted with the Shoreline Exemption application on January 20, 2010 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated March 23, 2010 shall be resubmitted for review and approval by Jefferson County Department of Community Development.

Title: F-Approval for _____ Only
Wording This approval is for a Installation of Road Rumble Strips on Highway 101 from milepost 165.05 to milepost 184.62 only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.

Title: F-SDP Exemption Section
Wording The Development Review Division finds that this proposal is consistent with Shoreline Master Program Section JCC 18.25.090(6) and is consequently exempt from the substantial development permit (SDP) requirements. Exemptions from the substantial development permit requirements do not exempt a proposed development from compliance with the applicable policies and standards of the Shoreline Master Program or other applicable Federal, State, or local permit or license requirements.