Permit Case Summary

Case Number: Search Help

Case Number:SDP2009-00039 Case Status: Date Received:5/18/2009
Description:SHORELINE EXEMPTION FOR RUMBLE STRIP ON SR 20 - PROJECT BETWEEN MILEPOST 0.02 AND 11.09 Date Issued:6/8/2009
Applicant: STATE OF WASHINGTON-DOT Expiration Date:6/8/2010 12:00:00 AM
Site Address:HWY 20 Case Finaled:
Parcel No:000000220 Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Status updtd - Energov Convrsn
Date Completed: 10/4/2022
Disposition: DONE
Description: File Archived
Date Completed: 4/6/2018
Disposition: DONE
Description: Approve Exemption-UF
Date Completed: 6/8/2009
Disposition: DONE
Description: Review Complete-U
Date Completed: 6/8/2009
Disposition: DONE
Description: Case Entered
Date Completed: 5/18/2009
Disposition:
Description: App Substantially Complete-U
Date Completed: 5/28/2009
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 5/28/2009
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 5/28/2009
Disposition: DONE
Description: Consistency Review-U
Date Completed: 5/28/2009
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: Other Work/Separate Approval
Wording Work within the jurisdiction of the Shoreline Master Program other than as described above shall receive separate review from this Department.

Title: Progress towards completion
Wording Substantial progress towards completion of the project shall be performed within two years of the issuance of the permit.

Title: Exempt Maintenance Condition
Wording The development shall be essentially the same as the original in location, size, configuration, and external appearance.

Title: BMPs
Wording The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-CRITICAL AREAS
Wording This project is exempt from critical area review and protection standards under JCC 18.22.070(3) when undertaken persuant to best management practices to minimize impacts to critical areas and to immediately restore any disturbed area or its buffer.

Title: F-Confirmed ESAs
Wording The application was reviewed by the Jefferson County Department of Community Development staff on May 28, 2009 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: Conservancy Shoreline Designation; Unstable Shoreline Slope Stability; Eagle Habitat; Landslide Hazard Area; Aquifer Recharge Area; Coastal SIPZ.

Title: F-Aquifer Recharge Area
Wording Aquifer Recharge Areas in Jefferson County are characterized by porous geological formations that allow percolation of the surface water into the soils and the underlying zone of saturation. Aquifers are geologic formations that contain sufficient saturated permeable material to yield significant quantities of water to wells and springs. Aquifers serve as the source of drinking water within most of the rural portions of Jefferson County.

Title: F-Susc. Aquifer Recharge Area
Wording Susceptible Aquifer Recharge Areas are those with geologic and hydrologic conditions that promote rapid infiltration of recharge waters to groundwater aquifers.

Title: F-Geohazard Area
Wording Geologically Hazardous Areas in Jefferson County are characterized by slope, soil type, geologic material, and groundwater that may combine to create problems with slope stability, erosion, and water quality during and after construction or during natural events such as earthquakes or severe rainstorms.

Title: F-SEPA Exempt
Wording Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(1)(u).

Title: F-Site Plan Changes
Wording The site plan as submitted with the Shoreline Exemption application on May 26, 2009 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated May 28, 2009 shall be resubmitted for review and approval by Jefferson County Department of Community Development.

Title: F-Approval for _____ Only
Wording This approval is for Road Maintenance to include Rumble-strips along the center line only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.

Title: F-SDP Exemption Section
Wording The Development Review Division finds that this proposal is consistent with Shoreline Master Program Section JCC 18.25.090(6) and is consequently exempt from the substantial development permit (SDP) requirements. Exemptions from the substantial development permit requirements do not exempt a proposed development from compliance with the applicable policies and standards of the Shoreline Master Program or other applicable Federal, State, or local permit or license requirements.