Permit Case Summary

Case Number: Search Help

Case Number:SDP2009-00020 Case Status: Date Received:3/3/2009
Description:Water line connection between Indian Island and the Marrowstone Island Water System. This project permit originally approved on April 6, 2010 to be amended to include additional water line running from the SR116 causeway to the Portage Canal Bridge (milepost 2.93 to 4.57). The original proposal was for installation of a four inch HDPE water line within the right-of-way of the State Route 116 Causeway (elevated earthen roadway) that connects the southern end of Indian Island to Marrowstone Island. The project will utilize Horizontal Directional Drilling (HDD) to pass the line underneath the Causeway culverts. The new water line will provide better hydraulics for the system as well as create a "loop" for the Marrowstone water system and act as a supply backup for that system should the existing supply line from Northern Indian Island fail. The proposal requires State Environmental Policy Act (SEPA) review, approval from the State Departments of Transportation and Fish & Wildlife, as well as a Type III Shoreline Substantial Development Conditional Use permit from Jefferson County which requires public notice and a public hearing. Date Issued:10/21/2010
Applicant: PUD#1 OF JEFFERSON COUNTY Expiration Date:10/21/2012 12:00:00 AM
Site Address:SR 116 Case Finaled:
Parcel No:000000220 Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Status updtd - Energov Convrsn
Date Completed: 10/4/2022
Disposition: DONE
Description: File Archived
Date Completed: 4/6/2018
Disposition: DONE
Description: Approve SDP Permit-UF
Date Completed: 10/21/2010
Disposition: DONE
Description: Hearing Exam PH Notice-Pub-UF
Date Completed: 9/27/2010
Disposition: DONE
Description: Hearing Exam PH Notice-APO-UF
Date Completed: 9/27/2010
Disposition: DONE
Description: Ntc of Dec Apprvl/Appl Inst-UF
Date Completed: 4/13/2010
Disposition: DONE
Description: Hearing Exam PH Notice-Pub-UF
Date Completed: 3/5/2010
Disposition: DONE
Description: Hearing Exam PH Notice-APO-UF
Date Completed: 3/5/2010
Disposition: DONE
Description: Additional Info Request-U
Date Completed: 4/13/2010
Disposition: DONE
Description: Additional Info Request-U
Date Completed: 2/16/2010
Disposition: DONE
Description: Det. of Completeness-UF
Date Completed: 4/29/2009
Disposition: DONE
Description: Ntc of App +30-Publish-UF
Date Completed: 4/27/2009
Disposition: DONE
Description: Ntc of App +30-APO-UF
Date Completed: 4/27/2009
Disposition: DONE
Description: Case Entered
Date Completed: 3/3/2009
Disposition:
Description: App Substantially Complete-U
Date Completed: 4/27/2009
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 2/24/2010
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 2/24/2010
Disposition: DONE
Description: Consistency Review-U
Date Completed: 2/24/2010
Disposition: DONE
Description: RAP Review Complete-U
Date Completed: 2/24/2010
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: Custom Universal Condition
Wording 1. The applicant shall obtain a Hydraulic Project Approval (HPA) from the Department of Fish & Wildlife. 2. The applicant shall obtain a permit from the Jefferson County Department of Public Works to place water lines within County rights-of-way. 3. The applicant shall receive a Franchise Amendment from the Washington State Department of Transportation to place water lines within State rights-of-way. 4. Substantial progress towards completion of the project shall be performed within two years of the issuance of the permit. 5. The applicant shall consult the area WDFW Eagle Biologist before construction and time construction to avoid disturbance of nesting Eagles. 6. Water lines shall be located a minimum of 10 feet from all onsite sewage system components. Where a water line and wastewater line cross the water line shall be placed above the wastewater line a minimum of 18 inches. If this separation cannot be maintained and the water line is still above the wastewater line, the water line shall be cased. If the water line is below the wastewater line then both lines shall be cased. All casing shall meet the standards set forth in the DOE Criteria for Sewage Works. It is the responsibility of the applicant to locate any drainfields or wastewater lines that they will be coming into proximity with or crossing. 7. The applicant shall implement the pollution and erosion control measures outlined in the Stormwater Plan (Log Item 6) 8. The applicant shall contact Public Works to schedule a pre-construction meeting if necessary to implement the Stormwater Pollution Prevention Plan as approved by Public Works. 9. A Representative of the PUD #1 shall be on-site to supervise all phases of installation at all times to insure compliance with these conditions to prevent turbid stormwater run-off from entering marine waters. 10. The applicant shall immediately restore the installation sites to their per-project condition to the maximum extent possible. 11. In accordance with the Cultural Resources Report prepared by Gary Wessen and Wessen and Associates Inc., and subsequent Archaelolgical Survey, the applicant shall use caution when working within the vicinity of archeological site 45 JE, and comply with the recommendations of the Report and Survey and acqurie any necessary approval from local Tribes or the Department of Archaeology and Historic Preservation.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-Custom Universal Finding