Description:
|
| | |
Status updtd - Energov Convrsn
|
|
Date Completed:
|
| | |
10/4/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
4/6/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Exemption-UF
|
|
Date Completed:
|
| | |
1/15/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Review Complete-U
|
|
Date Completed:
|
| | |
1/15/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
12/10/2008
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
1/15/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
1/15/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
1/15/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
1/15/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
Progress towards completion
|
|
Wording
|
| | |
Substantial progress towards completion of the project shall be performed within two years of the issuance of the permit.
|
|
|
Title:
|
| | |
Exempt Maintenance Condition
|
|
Wording
|
| | |
The development shall be essentially the same as the original in location, size, configuration, and external appearance.
|
|
|
Title:
|
| | |
BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
Hydraulic Code/HPA Check
|
|
Wording
|
| | |
Prior to commencing development activity, proponent is responsible for informing the Washington Department of Fish and Wildlife (WDFW) in order for WDFW to determine whether this action is subject to the Washington State Hydraulic Code (Chapter 220-10 WAC). Hydraulic Project Approval (HPA) is required for all hydraulic projects, which are defined as construction or performance of other work that will use, divert, obstruct, or change the natural flow or bed of any of the salt or fresh waters of the state.
|
|
|
Title:
|
| | |
Comply with HPA
|
|
Wording
|
| | |
In addition to Jefferson County permit conditions, the project proponent shall comply with all conditions set forth by the Washington Department of Fish and Wildlife through Hydraulic Project Approval.
|
|
|
Title:
|
| | |
F-CRITICAL AREAS
|
|
Wording
|
| | |
This project is exempt from critical area review and protection standards under JCC 18.22.070(3) when undertaken persuant to best management practices to minimize impacts to critical areas and to immediately restore any disturbed area or its buffer.
|
|
|
Title:
|
| | |
F-Confirmed ESAs
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County Department of Community Development staff on January 15, 2009 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: Conservancy Shoreline Designation; Unstable Shoreline Slope Stability; Type "S" & "F" (3) Stream; Seismic Hazard Zone; Coastal SIPZ.
|
|
|
Title:
|
| | |
F-Geohazard Area
|
|
Wording
|
| | |
Geologically Hazardous Areas in Jefferson County are characterized by slope, soil type, geologic material, and groundwater that may combine to create problems with slope stability, erosion, and water quality during and after construction or during natural events such as earthquakes or severe rainstorms.
|
|
|
Title:
|
| | |
F-Coastal SIPZ
|
|
Wording
|
| | |
The parcel is located within a coastal SIPZ (seawater intrusion protection zone) according to the County GIS map. There are voluntary and mandatory measures identified in the Jefferson County Seawater Intrusion Policy (Resolution 44-22, effective September 23, 2002) that apply to well drilling proposals and building permit applications on existing lots of record.
A Coastal SIPZ is defined as: all islands and area within one-quarter mile of marine shoreline, but no history of chloride concentration above 100 mg/L in groundwater sources within 1000 feet.
|
|
|
Title:
|
| | |
F-SEPA Exempt
|
|
Wording
|
| | |
Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(2)(c).
|
|
|
Title:
|
| | |
F-Site Plan Changes
|
|
Wording
|
| | |
The site plan as submitted with the Shoreline Exemption application on December 10, 2009 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated January 15, 2009 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
F-Approval for _____ Only
|
|
Wording
|
| | |
This approval is for a Shoreline Exemption for road improvements on SR 116 only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
F-SDP Exemption Section
|
|
Wording
|
| | |
The Development Review Division finds that this proposal is consistent with Shoreline Master Program Section JCC 18.25.090(6) and is consequently exempt from the substantial development permit (SDP) requirements. Exemptions from the substantial development permit requirements do not exempt a proposed development from compliance with the applicable policies and standards of the Shoreline Master Program or other applicable Federal, State, or local permit or license requirements.
|
|