Case Number:SDP2008-00040 Case Status: Date Received:6/10/2008
Description:Renewal of Shoreline Exemption MLA08-00279/SDP08-00040 previously MLA07-00263/SDP07-00039 for dredging marina entrance - Shoreline Exemption to conduct hydraulic dredging to remove approximately 1000 cubic yards of material which will be placed on the beach as stipulated through the conditions described in HPA 109023-4 issued by the Washington Department of Fish and Wildlife on June 17, 2009, and a Section 10 & 404 permit number NWS 2004-00887 by the US Army Corps of Engineers. The proposal also includes the routine maintenance of docks, ramps, and other infrastructure of the marina. A threshold determination for routine maintenance dredging was completed on June 2, 1999. Date Issued:6/16/2010
Applicant:GARY ROSSOW Expiration Date:6/16/2011 12:00:00 AM
Site Address:360 MARINA DR Case Finaled:
Parcel No:002123003 Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Status updtd - Energov Convrsn
Date Completed: 10/4/2022
Disposition: DONE
Description: File Archived
Date Completed: 4/4/2018
Disposition: DONE
Description: Approve Exemption-UF
Date Completed: 6/16/2010
Disposition: DONE
Description: Approve Exemption-UF
Date Completed: 6/11/2009
Disposition: DONE
Description: Approve Exemption-UF
Date Completed: 6/20/2008
Disposition: DONE
Description: Review Complete-U
Date Completed: 6/20/2008
Disposition: DONE
Description: Case Entered
Date Completed: 6/17/2008
Disposition:
Description: App Substantially Complete-U
Date Completed: 6/20/2008
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 6/20/2008
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 6/20/2008
Disposition: DONE
Description: Consistency Review-U
Date Completed: 6/20/2008
Disposition: DONE
Description: RAP Review Complete-U
Date Completed: 6/20/2008
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: Other Work/Separate Approval
Wording Work within the jurisdiction of the Shoreline Master Program other than as described above shall receive separate review from this Department.

Title: Treated Materials Must be Cured
Wording All lumber and other materials treated with preservative shall be sufficiently cured to minimize leaching into the water or shore bed, in accordance with the Best Management Practices approved by the Washington Department of Fish and Wildlife.

Title: Exempt Maintenance Condition
Wording The development shall be essentially the same as the original in location, size, configuration, and external appearance.

Title: No Fill or Other Material
Wording No fill or other material may be placed in the waters or intertidal areas of Jefferson County.

Title: ARMY CORPS
Wording The Army Corps of Engineers (COE) issued a permit on May 10, 2006 under Permit Number NWS 2004-887 that expires on May 10, 2011. Applicant shall comply with said conditions of permit.

Title: DOE APPROVAL
Wording The applicant shall comply with the Water Quality Certification #2521 issued July 29, 2005 from the WA State Dept. of Ecology regarding the WA Coastal Zone Management Program. This approval expires on July 29, 2010.

Title: BMPs
Wording The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.

Title: Comply with HPA
Wording In addition to Jefferson County permit conditions, the project proponent shall comply with all conditions set forth by the Washington Department of Fish and Wildlife through Hydraulic Project Approval.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-CASE HISTORY
Wording A Shoreline Exemption Permit (SDP06-12) was issued on June 26, 2006. Because a shoreline exemption is only valid for one year (SMMP- Section 18.25.080 of the Jefferson County Code) this permit is required even though the HPA from WDFW, Water Quality Certification from the DOE, and the Section 10 & 404 Permits from the U.S. Army Corp of Engineers may be granted for a longer period for this maintenance dredging activity.

Title: F-SEPA
Wording The proposal has received review under the State Environmental Policy Act (SEPA) through a Final Mitigated Determination of Non-Significance issued by Jefferson County on June 2, 1999. The mitigation measures are address through existing development regulations and required permits. This threshold determination was for routine maintenance dredging of the marina access channel (20 foot wide and 3-5 feet MLLW) of accumulated sediments and disposal on an approved upland location. Because the proposal has not changed from what was analyzed through the previous threshold determination, no additional SEPA review is required for this proposal (WAC 197-11-600).

Title: F-Confirmed ESAs
Wording The application was reviewed by the Jefferson County Department of Community Development staff on May 21, 2007 for the potential presence of Environmentally Sensitive Areas under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review, the following ESAs were confirmed to be present on the subject property: Fish and Wildlife Habitat Areas Conservancy - Aquatic Shore Designation (overwater-marine).

Title: F-HPA Issued
Wording The Washington Department of Fish and Wildlife issued Hydraulic Project Approval (HPA) for this activity on June 17, 2009 under Control Number 109023-4. The HPA expires on February 15, 2012.

Title: F-Site Plan Changes
Wording The site plan as submitted with the shoreline exemption (SDP07-39) application on May 1, 2007 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated June 11, 2009 & JARPA dated May 22, 2007 shall be resubmitted for review and approval by Jefferson County Department of Community Development.

Title: F-Approval for _____ Only
Wording This approval is for removal of approximately 1000 cubic yards of sediment from the marina access channel (maintenance dredging) and routine maintenance to existing docks, ramps, and infrastructure related to the marina only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.

Title: F-SDP Exemption Section
Wording The Development Review Division finds that this proposal is consistent with Jefferson County Shoreline Managment Master Program, Section 18.25.090(6) of the Jefferson County Code, and is consequently exempt from the substantial development permit (SDP) requirements. Exemptions from the substantial development permit requirements do not exempt a proposed development from compliance with the applicable policies and standards of the Shoreline Master Program or other applicable Federal, State, or local permit or license requirements.