Description:
|
| | |
Status updtd - Energov Convrsn
|
|
Date Completed:
|
| | |
10/4/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
2/16/2011
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue SDP Permit
|
|
Date Completed:
|
| | |
6/5/2006
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
(F) Appeal of Final DNS
|
|
Date Completed:
|
| | |
7/6/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue SDP Permit
|
|
Date Completed:
|
| | |
6/5/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Ntc of Dec Apprvl/Appl Inst-UF
|
|
Date Completed:
|
| | |
6/5/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Hearing Exam PH Notice-Pub-UF
|
|
Date Completed:
|
| | |
4/25/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Hearing Exam PH Notice-APO-UF
|
|
Date Completed:
|
| | |
4/25/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Hearing Exam PH Notice-Pub-UF
|
|
Date Completed:
|
| | |
3/29/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Hearing Exam PH Notice-APO-UF
|
|
Date Completed:
|
| | |
3/29/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-U
|
|
Date Completed:
|
| | |
1/9/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Ntc of App +30-Publish-UF
|
|
Date Completed:
|
| | |
11/28/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
11/18/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Ntc of App +30-APO-UF
|
|
Date Completed:
|
| | |
11/17/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-U
|
|
Date Completed:
|
| | |
11/14/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Ntc of App +14-Publish-U
|
|
Date Completed:
|
| | |
6/6/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Ntc of App +14-Publish-U
|
|
Date Completed:
|
| | |
6/6/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Ntc of App +14-APO-U
|
|
Date Completed:
|
| | |
6/6/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
5/31/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
5/4/2005
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
3/29/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
5/31/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
3/29/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
3/29/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
3/29/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
3/29/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
Custom Case Specific Condition
|
|
Wording
|
| | |
1. The applicant shall obtain an Administrative Conditional Use permit (ZON05-00027) for the complete installation of the proposed Marrowstone Island Water System. This permit is necessary for all minor utilities.
2. The applicant shall obtain a permit from the Jefferson County Department of Public Works to place water lines within County rights-of-way.
3. The applicant shall receive a Franchise Amendment from the Washington State Department of Transportation to place water lines within State rights-of-way.
4. Substantial progress towards completion of the project shall be performed within two years of the issuance of the permit.
5. The applicant shall consult the area WDFW Eagle Biologist before construction and time construction to avoid disturbance of nesting Eagles.
6. Water lines shall be located a minimum of 10 feet from all onsite sewage system components. Where a water line and wastewater line cross the water line shall be placed above the wastewater line a minimum of 18 inches. If this separation cannot be maintained and the water line is still above the wastewater line, the water line shall be cased. If the water line is below the wastewater line then both lines shall be cased. All casing shall meet the standards set forth in the DOE Criteria for Sewage Works. It is the responsibility of the applicant to locate any drainfields or wastewater lines that they will be coming into proximity with or crossing.
7. The applicant shall install water lines on the landward side of the roadway when within 200 feet of the shoreline OHWM whenever feasible.
8. The applicant shall implement the pollution and erosion control measures listed in Section 5.2 of the Impact Assessment (Log Item 197)
9. The applicant shall contact Public Works and schedule a pre-construction meeting and implement the Stormwater Pollution Prevention Plan as approved by Public Works.
10. The applicant shall immediately restore the installation sites to their per-project condition to the maximum extent possible.
11. The applicant shall submit plans and/or information regarding this proposal to the Army Corps of Engineers to determine if any permits are required through that agency.
12. The decision set forth herein is based upon representations made and exhibits, including plans and proposals submitted at the hearing conducted by the hearing examiner. Any substantial change(s) or deviation(s) in such plans, proposals, or conditions of approval imposed shall be subject to the approval of the hearing examiner and may require further and additional hearings.
13. The authorization granted herein is subject to all applicable federal, state, and local laws, regulations, and ordinances. Compliance with such laws, regulations, and ordinances is a condition precedent to the approvals granted and is a continuing requirement of such approvals. By accepting this/these approvals, the applicant represents that the development and activities allowed will comply with such laws, regulations, and ordinances. If, during the term of the approval granted, the development and activities permitted do not comply with such laws, regulations, or ordinances, the applicant agrees to promptly bring such development or activities into compliance.
|
|