Permit Case Summary

Case Number: Search Help

Case Number:SDP2005-00014 Case Status: Date Received:5/3/2005
Description:Marrowstone Island water system: This proposal includes installation of 8, 6, 4 and 2-inch public water mains, with accoutrements, in and along the road ditches throughout Marrowstone Island. The Unified Development Code identifies water pipelines as minor utilities requiring a Conditional Administrative use permit subject to a Type II process. Proposed utilities within shoreline jurisdiction require a Shoreline Conditional Use and Substantial Development Permit subject to a Type III process involving noticing and a public hearing. The proposal is exempt from review under the State Environmental Policy Act pursuant to WAC 197-11-800(23)(b). The Conditional Use permit (ZON05-00027) for a minor utility was originally to be reviewed collectively with the Shoreline Permit SDP05-00014. Due to timing constraints the applicant has decided to process the permits individually. The public hearing will be for the Shoreline permit only. Date Issued:6/5/2006
Applicant: PUD#1 OF JEFF COUNTY Expiration Date:6/5/2008 12:00:00 AM
Site Address:SR 116 Case Finaled:
Parcel No:000000220 Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Status updtd - Energov Convrsn
Date Completed: 10/4/2022
Disposition: DONE
Description: File Archived
Date Completed: 2/16/2011
Disposition: DONE
Description: Issue SDP Permit
Date Completed: 6/5/2006
Disposition:
Description: (F) Appeal of Final DNS
Date Completed: 7/6/2006
Disposition: DONE
Description: Issue SDP Permit
Date Completed: 6/5/2006
Disposition: DONE
Description: Ntc of Dec Apprvl/Appl Inst-UF
Date Completed: 6/5/2006
Disposition: DONE
Description: Hearing Exam PH Notice-Pub-UF
Date Completed: 4/25/2006
Disposition: DONE
Description: Hearing Exam PH Notice-APO-UF
Date Completed: 4/25/2006
Disposition: DONE
Description: Hearing Exam PH Notice-Pub-UF
Date Completed: 3/29/2006
Disposition: DONE
Description: Hearing Exam PH Notice-APO-UF
Date Completed: 3/29/2006
Disposition: DONE
Description: Additional Info Request-U
Date Completed: 1/9/2006
Disposition: DONE
Description: Ntc of App +30-Publish-UF
Date Completed: 11/28/2005
Disposition: DONE
Description: Det. of Completeness-UF
Date Completed: 11/18/2005
Disposition: DONE
Description: Ntc of App +30-APO-UF
Date Completed: 11/17/2005
Disposition: DONE
Description: Additional Info Request-U
Date Completed: 11/14/2005
Disposition: DONE
Description: Ntc of App +14-Publish-U
Date Completed: 6/6/2005
Disposition: DONE
Description: Ntc of App +14-Publish-U
Date Completed: 6/6/2005
Disposition: DONE
Description: Ntc of App +14-APO-U
Date Completed: 6/6/2005
Disposition: DONE
Description: Det. of Completeness-UF
Date Completed: 5/31/2005
Disposition: DONE
Description: Case Entered
Date Completed: 5/4/2005
Disposition:
Description: Septic Review Complete-U
Date Completed: 3/29/2006
Disposition: DONE
Description: App Substantially Complete-U
Date Completed: 5/31/2005
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 3/29/2006
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 3/29/2006
Disposition: DONE
Description: Consistency Review-U
Date Completed: 3/29/2006
Disposition: DONE
Description: RAP Review Complete-U
Date Completed: 3/29/2006
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: Custom Case Specific Condition
Wording 1. The applicant shall obtain an Administrative Conditional Use permit (ZON05-00027) for the complete installation of the proposed Marrowstone Island Water System. This permit is necessary for all minor utilities. 2. The applicant shall obtain a permit from the Jefferson County Department of Public Works to place water lines within County rights-of-way. 3. The applicant shall receive a Franchise Amendment from the Washington State Department of Transportation to place water lines within State rights-of-way. 4. Substantial progress towards completion of the project shall be performed within two years of the issuance of the permit. 5. The applicant shall consult the area WDFW Eagle Biologist before construction and time construction to avoid disturbance of nesting Eagles. 6. Water lines shall be located a minimum of 10 feet from all onsite sewage system components. Where a water line and wastewater line cross the water line shall be placed above the wastewater line a minimum of 18 inches. If this separation cannot be maintained and the water line is still above the wastewater line, the water line shall be cased. If the water line is below the wastewater line then both lines shall be cased. All casing shall meet the standards set forth in the DOE Criteria for Sewage Works. It is the responsibility of the applicant to locate any drainfields or wastewater lines that they will be coming into proximity with or crossing. 7. The applicant shall install water lines on the landward side of the roadway when within 200 feet of the shoreline OHWM whenever feasible. 8. The applicant shall implement the pollution and erosion control measures listed in Section 5.2 of the Impact Assessment (Log Item 197) 9. The applicant shall contact Public Works and schedule a pre-construction meeting and implement the Stormwater Pollution Prevention Plan as approved by Public Works. 10. The applicant shall immediately restore the installation sites to their per-project condition to the maximum extent possible. 11. The applicant shall submit plans and/or information regarding this proposal to the Army Corps of Engineers to determine if any permits are required through that agency. 12. The decision set forth herein is based upon representations made and exhibits, including plans and proposals submitted at the hearing conducted by the hearing examiner. Any substantial change(s) or deviation(s) in such plans, proposals, or conditions of approval imposed shall be subject to the approval of the hearing examiner and may require further and additional hearings. 13. The authorization granted herein is subject to all applicable federal, state, and local laws, regulations, and ordinances. Compliance with such laws, regulations, and ordinances is a condition precedent to the approvals granted and is a continuing requirement of such approvals. By accepting this/these approvals, the applicant represents that the development and activities allowed will comply with such laws, regulations, and ordinances. If, during the term of the approval granted, the development and activities permitted do not comply with such laws, regulations, or ordinances, the applicant agrees to promptly bring such development or activities into compliance.