Case Number:SDP2004-10004 Case Status: Date Received:3/2/2004
Description:The proposal is for maintenance dredging for the Bridgehaven Marina. The applicant is proposing to extract approximately 7,000 cubic yards of material, of which approximately 2,000 cubic yards of the sandy dredged material will be placed on the upper intertidal beach and backshore area south of the Bridgehaven spit near the old South Point ferry terminal. The remaining 5,000 cubic yards of material will be placed in the approved deep water disposal site near Port Townsend. The applicant has received a Hydraulic Project Approval (HPA) permit issued from WDFW. In addition, the applicant will be required to obtain a permit from the US Army Corps of Engineers. This notice includes the Final Threshold Determination that a Determination of Non-Significance (DNS) has been issued. The optional DNS process of WAC 197-11-355 is being used. Parties of record can appeal the Final Threshold Determination by 4 p.m. on July 14, 2004. The specifications for appeals are outlined by Section 8.5.1(e) of the UDC, and require a $612 appeal fee. If an appeal of the Final Threshold Determination is received, it will be incorporated into the Hearing Examiners open record hearing for this proposal. The applicant subsequently modified the proposal to deposit all 7,000 cubic yards of material in open water per the Army Corp of Engineers approval. Date Issued:8/24/2004
Applicant: BRIDGEHAVEN COMMUNITY CLUB Expiration Date:8/25/2010 12:00:00 AM
Site Address: Case Finaled:
Parcel No:HOODCANAL Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Status updtd - Energov Convrsn
Date Completed: 10/4/2022
Disposition: DONE
Description: File Archived
Date Completed: 2/16/2011
Disposition: DONE
Description: Approve Exemption-UF
Date Completed: 8/24/2004
Disposition: DONE
Description: Approve SDP Permit-UF
Date Completed: 8/25/2009
Disposition: DONE
Description: Miscellaneous Action
Date Completed: 6/20/2008
Disposition: DONE
Description: File Archived
Date Completed: 12/28/2007
Disposition: DONE
Description: Close case
Date Completed: 9/20/2004
Disposition: DONE
Description: Approve SDP Permit-UF
Date Completed: 8/24/2004
Disposition: DONE
Description: Approve SDP Permit-UF
Date Completed: 8/24/2004
Disposition: DONE
Description: Ntc of Dec Apprvl/Appl Inst-UF
Date Completed: 8/2/2004
Disposition: DONE
Description: Ntc of Dec Apprvl/Appl Inst-UF
Date Completed: 8/2/2004
Disposition: DONE
Description: Ntc of Dec Apprvl/Appl Inst-UF
Date Completed: 8/2/2004
Disposition: DONE
Description: Hearing Exam PH Notice-Pub-UF
Date Completed: 6/28/2004
Disposition: DONE
Description: Hearing Exam PH Notice-APO-UF
Date Completed: 6/28/2004
Disposition: DONE
Description: Ntc of App +30-Publish-UF
Date Completed: 4/8/2004
Disposition: DONE
Description: Ntc of App +30-APO-UF
Date Completed: 4/8/2004
Disposition: DONE
Description: Det. of Completeness-UF
Date Completed: 4/7/2004
Disposition: DONE
Description: Incomplete App Request Info
Date Completed: 4/7/2004
Disposition: DONE
Description: Application Received-UF
Date Completed: 3/3/2004
Disposition: DONE
Description: Case Entered
Date Completed: 3/2/2004
Disposition:
Description: Septic Review Complete-U
Date Completed: 6/18/2004
Disposition: DONE
Description: App Substantially Complete-U
Date Completed: 4/7/2004
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 6/18/2004
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 6/18/2004
Disposition: DONE
Description: Consistency Review-U
Date Completed: 6/18/2004
Disposition: DONE
Description: RAP Review Complete-U
Date Completed: 6/18/2004
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: WATER QUALITY
Wording Dredging and disposal of sediment shall comply with the Department of Ecology water quality certification dated April 30, 2007 and amended July 29, 2009.

Title: HPA
Wording All work shall comply with the Hydraulic Project Approval issued July 30, 2009.

Title: FISH
Wording Dredging operations shall be scheduled so as to not materially interfere with the migratory movements of anadromous fish

Title: ADJACENT SHORELINE USES
Wording Dredging shall not cause unnecessary interference with navigation or unnecessary infringement upon adjacent shoreline uses, properties, or values.

Title: DEPOSITING MATERIALS
Wording Depositing of dredge materials in water areas shall be allowed in an area consistent with Army Corp of Engineers approval.

Title: MAINTENANCE DREDGING
Wording Maintenance dredging shall only be conducted upon the completion of a dredge materials management plan for the site based on compliance with the policies and performance standards of this subsection.

Title: OBTAIN AQ LAND LEASE
Wording Prior to commencing development activity, the proponent is responsible for contacting the Washington Department of Natural Resources to obtain and Aquatics Land Lease.

Title: MONITORING PLAN
Wording A monitoring plan shall be filed with Jefferson County and WDFW.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-Site Plan Changes
Wording The site plan as approved by the Army Corp of Engineers on August 6, 2009 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated August 25, 2009 shall be resubmitted for review and approval by Jefferson County Department of Community Development.

Title: F-Approval for _____ Only
Wording This approval is for dredging and open water disposal only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.

Title: F-General PMT Notice
Wording NOTICE: This permit does not excuse the proponent from complying with other local, state, and federal ordinances, regulations, or statutes applicable to the proposed development, but consistent with RCW 90.58. Development pursuant to this permit shall be undertaken subject to the applicable policies and performance standards of the Jefferson County Shoreline Management Master Program and the Jefferson County Unified Development Code. If during excavation or development of the site an area of potential archaeological significance is uncovered, all activity in the immediate area shall be halted, and the Administrator shall be notified at once. The Federal Endangered Species Act rules to protect threatened Chinook and Summer-run Chum salmon became effective on January 8, 2001. Bull trout have been listed as threatened since early 2000. Under the ESA, any person may bring lawsuit against any individual or agency that "takes" listed species (defined as causing harm, harassing, or damaging habitat for the listed species). In addition, the National Marine Fisheries Service can levy penalties. All areas in Jefferson County are included as "critical habitat" for a listed species. Development of property along any marine shoreline, freshwater shoreline, or floodplains could harm habitat if protective measures are not taken. To minimize the potential to damage habitat, all property owners developing adjacent to marine shoreline, freshwater shoreline, or floodplains are advised to do the following: - All development activities should avoid unstable slopes, wetlands, and forested areas near surface waters - Remove minimal vegetation for site development, especially large trees - Allow trees that have fallen into surface waters to remain there - Infiltrate stormwater from buildings and driveways onsite through drywells rather than discharging directly into surface waters or roadside ditches Any individual, group, or agency can bring suit for a listed species "taking", even if you are in compliance with Jefferson County development codes. The risk of a lawsuit against you can be reduced by consulting with a professional fisheries habitat biologist, and following the recommendations for site development provided by the biologist. For more information, contact the National Marine Fisheries Service in Seattle, or the U.S. Fish and Wildlife Service.