Case Number:SDP2004-00042 |
Case Status:Finaled |
Date Received:8/23/2004 |
|
Description:SHORELINE EXEMPTION to replace concrete anchors with helix anchors systems for 31 mooring buoys located in state parks, which include Fort Worden, Fort Flagler, Mystery Bay, Old Fort Townsend, and Shine Tidelands. These state parks are located in the following water bodies: Admiralty inlet, Kilisut Harbor, Port Townsend Bay, Bywater Bay, Hood Canal, and Puget Sound. |
Date Issued:9/19/2005 |
|
Applicant: WA STATE PARKS AND RECREATION |
Expiration Date:9/19/2006 12:00:00 AM |
|
Site Address: |
Case Finaled: |
|
Parcel No:ADMIRALTYINLET
|
Other Cases |
Parcel Data |
Map It |
|
Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
12/28/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Close case
|
|
Date Completed:
|
| | |
12/28/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Exemption-UF
|
|
Date Completed:
|
| | |
10/11/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Review Complete-U
|
|
Date Completed:
|
| | |
10/11/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Application Received-UF
|
|
Date Completed:
|
| | |
8/24/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
8/23/2004
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
10/11/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
10/11/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
10/11/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
10/11/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
10/11/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
10/11/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
Other Work/Separate Approval
|
|
Wording
|
| | |
Work within the jurisdiction of the Shoreline Master Program other than as described above shall receive separate review from this Department.
|
|
|
Title:
|
| | |
Site Plan
|
|
Wording
|
| | |
Construction shall be in substantial compliance with the site plan submitted on August 20, 2004 as it exists now or is hereafter amended by Jefferson County and/or the Washington Department of Ecology.
|
|
|
Title:
|
| | |
Exempt Maintenance Condition
|
|
Wording
|
| | |
The development shall be essentially the same as the original in location, size, configuration, and external appearance.
|
|
|
Title:
|
| | |
No Fill or Other Material
|
|
Wording
|
| | |
No fill or other material may be placed in the waters or intertidal areas of Jefferson County.
|
|
|
Title:
|
| | |
Hydraulic Code/HPA Check
|
|
Wording
|
| | |
Prior to commencing development activity, proponent is responsible for informing the Washington Department of Fish and Wildlife (WDFW) in order for WDFW to determine whether this action is subject to the Washington State Hydraulic Code (Chapter 220-10 WAC). Hydraulic Project Approval (HPA) is required for all hydraulic projects, which are defined as construction or performance of other work that will use, divert, obstruct, or change the natural flow or bed of any of the salt or fresh waters of the state.
|
|
|
Title:
|
| | |
Comply with HPA
|
|
Wording
|
| | |
In addition to Jefferson County permit conditions, the project proponent shall comply with all conditions set forth by the Washington Department of Fish and Wildlife through Hydraulic Project Approval.
|
|
|
Title:
|
| | |
Army Corps Check
|
|
Wording
|
| | |
Prior to commencing development activity, the proponent is responsible for informing the US Army Corps of Engineers (COE) in order for COE to determine whether a Department of the Army permit or review is required. Generally, review is required for construction and dredging in or around navigable waters of the US and for work or fill in hydrologically connected wetlands. Contact the US Army Corps of Engineers, Seattle District Regulatory Branch, PO Box 3755, Seattle WA 98124, (206) 764-3495, for more information.
|
|
|
Title:
|
| | |
F-Confirmed ESAs
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County Department of Community Development staff on October 11, 2004 for the potential presence of Environmentally Sensitive Areas (ESAs) the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: Shoreline (Overwater marine - fish & wildlife habitat)
|
|
|
Title:
|
| | |
F-SEPA Exempt
|
|
Wording
|
| | |
Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(3)- Repair, remodeling, and maintenance activities.
|
|
|
Title:
|
| | |
F-Site Plan Changes
|
|
Wording
|
| | |
The site plan as submitted with the Shoreline Exemption application on August 20, 2004 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated October 11, 2004 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
F-Approval for _____ Only
|
|
Wording
|
| | |
This approval is for a replacement of concrete anchors with helix screw achors for 31 existing buoys located in state parks in Jefferson County only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
F-NATURE OF PROPOSAL
|
|
Wording
|
| | |
The buoys located in state parks are on a two year maintenance schedule. To obtain the required HPA from WA State Dept. of Fish and permits from the Corp of Engineers the anchor system is required to utilize best available technology and environmentally friendly designs. This includes the removal of the existing two concrete block anchors (typically 2,000 lbs and 500 lbs) that take up habitat area and cause scour and replace them with the helix screw anchors (See figure 12 & 13 of JARPA).
|
|
|
Title:
|
| | |
F-SDP Exemption Section
|
|
Wording
|
| | |
The Development Review Division finds that this proposal is consistent with Shoreline Master Program Section 3.402.(6) and is consequently exempt from the substantial development permit (SDP) requirements. Exemptions from the substantial development permit requirements do not exempt a proposed development from compliance with the applicable policies and standards of the Shoreline Master Program or other applicable Federal, State, or local permit or license requirements.
|
|