CONDITIONS
|
|
Wording
|
| | |
1. The applicant shall obtain a building permit from the Jefferson County Department of Community Development prior to any excavation and construction activities.
2. Prior to issuance of the Jefferson County Building Permit, the applicant will be required to submit the following: A Temporary Drainage, Sediment and Erosion Control (TESC) Plan as required and described by JCC 18.30.070(3) Development and Redevelopment Minimum Requirements & JCC 18.15.380 Drainage and erosion control plan, and incorporating the mitigation measures outlined below. Once the subject permit has been issued, the applicant shall fully implement the provisions of the submitted TESC Plan. The following mitigation measures submitted by the Department of Ecology and identified during SEPA review are required and shall be incorporated into the TESC plan:
a. Erosion control measures must be in place prior to any clearing, grading or construction. These control measures must be effective to prevent soil from being carried into surface water by stormwater runoff. Sand, silt, clay particles, and soil will damage aquatic habitat and are considered pollutants when discharged to waters of the state.
b. Any discharge of sediment-laden runoff or other pollutants to waters of the state is in violation of Chapter 90.48, Water Pollution Control, and WAC 173-201A, Water Quality Standards for Surface Waters of the State of Washington, and is subject to enforcement action.
c. During construction, all releases of oils, hydraulic fluids, fuels, other petroleum products, paints, solvents, and other deleterious materials must be contained and removed in a manner that will prevent their discharge to waters and soils of the state. The cleanup of spills should take precedence over other work on the site.
d. Proper disposal of construction debris must be on land in such a manner that debris cannot enter the Port Townsend Bay or cause water quality degradation of state waters.
e. All trenches, depressions, or holes created in the intertidal area shall be backfilled prior to inundation by tidal waters.
f. All stormwater discharges must be constructed in a manner that will not cause scouring on the beach.
g. Fresh uncured concrete in direct contact with the water is toxic to aquatic life. All concrete shall be poured in the dry and allowed to cure a minimum of seven (7) days before contact with water.
h. If utilities, such as water and sewer lines, will be exposed under a pier adjacent to or over surface waters subject to tidal influence, the lines should be protected from damage from waterborne debris by nets, screens, or other devices.
3. Prior to commencing development activity, proponent is responsible for informing the Washington Department of Fish and Wildlife (WDFW) in order for WDFW to determine whether this action is subject to the Washington State Hydraulic Code (Chapter 220-10 WAC). Hydraulic Project Approval (HPA) is required for all hydraulic projects, which are defined as construction or performance of other work that will use, divert, obstruct, or change the natural flow or bed of any of the salt or fresh waters of the state.
4. In addition to Jefferson County permit conditions, the project proponent shall comply with all conditions set forth by the Washington Department of Fish and Wildlife through Hydraulic Project Approval.
5. Prior to commencing development activity, the proponent is responsible for informing the US Army Corps of Engineers (COE) in order for COE to determine whether a Department of the Army permit or review is required. Generally, review is required for construction and dredging in or around navigable waters of the US and for work or fill in hydrologically connected wetlands. Contact the US Army Corps of Engineers, Seattle District Regulatory Branch, PO Box 3755, Seattle WA 98124, (206) 764-3495, for more information.
6. All lumber and other materials treated with preservative shall be sufficiently cured to mini
|
|