Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
12/28/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Close case
|
|
Date Completed:
|
| | |
12/28/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Ntc of App +14-APO-U
|
|
Date Completed:
|
| | |
5/2/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Exemption-UF
|
|
Date Completed:
|
| | |
6/9/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Exemption-UF
|
|
Date Completed:
|
| | |
6/9/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Print Dummy UDC Permit-UF
|
|
Date Completed:
|
| | |
6/9/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Review Complete-U
|
|
Date Completed:
|
| | |
6/9/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
5/20/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Application Received-UF
|
|
Date Completed:
|
| | |
5/10/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
5/10/2004
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
6/9/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
5/20/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
6/9/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
6/9/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
6/9/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
6/9/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
Other Work/Separate Approval
|
|
Wording
|
| | |
Work within the jurisdiction of the Shoreline Master Program other than as described above shall receive separate review from this Department.
|
|
|
Title:
|
| | |
C-SDP REQUIRED
|
|
Wording
|
| | |
The applicant is required to undergo Shoreline Substantial Development permiting (SDP) after the emergency has been abated. Exemptions from the substantial development permit requirements do not exempt a proposed development from compliance with the applicable policies and standards of the Shoreline Master Program or other applicable Federal, State, or local permit or license requirements.
|
|
|
Title:
|
| | |
Site Plan
|
|
Wording
|
| | |
Construction shall be in substantial compliance with the site plan submitted on April 23, 2004, as it exists now or is hereafter amended by Jefferson County and/or the Washington Department of Ecology.
|
|
|
Title:
|
| | |
COMPLY WITH HPA
|
|
Wording
|
| | |
In addition to Jefferson County permit conditions, the project proponent shall comply with all conditions set forth by the Washington Department of Fish and Wildlife through Hydraulic Project Approval.
|
|
|
Title:
|
| | |
BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
Army Corps Check
|
|
Wording
|
| | |
Prior to commencing development activity, the proponent is responsible for informing the US Army Corps of Engineers (COE) in order for COE to determine whether a Department of the Army permit or review is required. Generally, review is required for construction and dredging in or around navigable waters of the US and for work or fill in hydrologically connected wetlands. Contact the US Army Corps of Engineers, Seattle District Regulatory Branch, PO Box 3755, Seattle WA 98124, (206) 764-3495, for more information.
|
|
|
Title:
|
| | |
F-HPA Issued
|
|
Wording
|
| | |
The Washington Department of Fish and Wildlife issued Hydraulic Project Approval (HPA) for this activity on May 27, 2004 under Log Number ST-G1201-02. The HPA expires on November 1, 2004.
|
|
|
Title:
|
| | |
F-APPROVAL FOR SDP-04-0009 ONLY
|
|
Wording
|
| | |
This approval is for the emergency work specified in the JARPA application dated April 23, 2004 only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
F-Custom Case Specific Finding
|
|
Wording
|
| | |
Washington Department of Transportation (DOT), as the lead agency, conducted SEPA on this proposal. Pursuant to the Jefferson County Unified Development Code, Environmental Sensitive Areas (ESA) will be reviewed with the subsequent required SDP.
|
|
|
Title:
|
| | |
F-Custom Case Specific Finding
|
|
Wording
|
| | |
Under the Jefferson County Unified Development Code, Section 8.4.C, Jefferson County will use and consider the SEPA determination made by the lead agency, DOT, dated February 27, 2004.
|
|
|
Title:
|
| | |
F-SDP Exemption Section
|
|
Wording
|
| | |
The Development Review Division finds that this proposal is consistent with Shoreline Master Program Section 3.402.8 and is considered an emergency exemption. The applicant is required to undergo Shoreline Substantial Development permiting (SDP) after the emergency has been abated. Exemptions from the substantial development permit requirements do not exempt a proposed development from compliance with the applicable policies and standards of the Shoreline Master Program or other applicable Federal, State, or local permit or license requirements.
|
|