Permit Case Summary

Case Number: Search Help

Case Number:SDP2003-00003 Case Status:Finaled Date Received:1/22/2003
Description:To replace two anchor cables (CN & DS). The existing cables have significant number of broken strands. In addition, the proposal will include repairing cracked and spalled girders on the west half of the bridge. WSDOT has assumed the SEPA lead and determined the application categorically exempt per WAC 197-11-800(18). In addition, the proposal is classified as a shoreline exemption per Section 3.402(6) of the Jefferson County Shoreline Master Program. Date Issued:2/12/2003
Applicant: WA STATE DOT Expiration Date:2/12/2004 12:00:00 AM
Site Address:HWY 104 Case Finaled:
Parcel No:000000220 Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: File Archived
Date Completed: 1/12/2006
Disposition: DONE
Description: Approve Exemption-UF
Date Completed: 2/12/2003
Disposition: DONE
Description: Approve Exemption-UF
Date Completed: 2/7/2003
Disposition: DONE
Description: Close case
Date Completed: 2/7/2003
Disposition: DONE
Description: Case Entered
Date Completed: 1/22/2003
Disposition:
Description: Septic Review Complete-U
Date Completed: 2/7/2003
Disposition: DONE
Description: App Substantially Complete-U
Date Completed: 1/22/2003
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 2/7/2003
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 2/7/2003
Disposition: DONE
Description: Consistency Review-U
Date Completed: 2/7/2003
Disposition: DONE
Description: RAP Review Complete-U
Date Completed: 2/7/2003
Disposition: DONE
Description: Application Received-UF
Date Completed: 1/22/2003
Disposition: DONE
Description: Det. of Completeness-UF
Date Completed: 1/22/2003
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: Other Work/Separate Approval
Wording Work within the jurisdiction of the Shoreline Master Program other than as described above shall receive separate review from this Department.

Title: Exempt Maintenance Condition
Wording The development shall be essentially the same as the original in location, size, configuration, and external appearance.

Title: No Fill or Other Material
Wording No fill or other material may be placed in the waters or intertidal areas of Jefferson County.

Title: Hydraulic Code/HPA Check
Wording Prior to commencing development activity, proponent is responsible for informing the Washington Department of Fish and Wildlife (WDFW) in order for WDFW to determine whether this action is subject to the Washington State Hydraulic Code (Chapter 220-10 WAC). Hydraulic Project Approval (HPA) is required for all hydraulic projects, which are defined as construction or performance of other work that will use, divert, obstruct, or change the natural flow or bed of any of the salt or fresh waters of the state.

Title: Comply with HPA
Wording In addition to Jefferson County permit conditions, the project proponent shall comply with all conditions set forth by the Washington Department of Fish and Wildlife through Hydraulic Project Approval.

Title: Army Corps Check
Wording Prior to commencing development activity, the proponent is responsible for informing the US Army Corps of Engineers (COE) in order for COE to determine whether a Department of the Army permit or review is required. Generally, review is required for construction and dredging in or around navigable waters of the US and for work or fill in hydrologically connected wetlands. Contact the US Army Corps of Engineers, Seattle District Regulatory Branch, PO Box 3755, Seattle WA 98124, (206) 764-3495, for more information.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-No ESAs Found
Wording The application was reviewed by the Jefferson County Department of Community Development for the presence of Environmentally Sensitive Areas (ESAs). The Department conducted a review and has concluded that the property DOES NOT contain Environmentally Sensitive Areas. However, future proposals will be subject to a new ESA review and conditions may be added if new ESAs are found on the property.

Title: F-HPA Issued
Wording The Washington Department of Fish and Wildlife issued Hydraulic Project Approval (HPA) for this activity on 12/26/02 under Log Number SP-E1552-01. The HPA expires on 12/26/07.

Title: F-SEPA Exempt
Wording Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(18).

Title: F-SDP Exemption Section
Wording The Development Review Division finds that this proposal is consistent with Shoreline Master Program Section 3.402.6 and is consequently exempt from the substantial development permit (SDP) requirements. Exemptions from the substantial development permit requirements do not exempt a proposed development from compliance with the applicable policies and standards of the Shoreline Master Program or other applicable Federal, State, or local permit or license requirements.