Case Number:SDP2002-00014 |
Case Status:Finaled |
Date Received:3/22/2002 |
|
Description:Nolan Creek Bridge Replacement located on SR 101. The project includes construction of a new bridge over Nolan Creek, removal of the existing bridge, and realignment of the highway in the vicinity of the bridge. The new alignment will situate the bridge east of the current alignment. The scope of work includes excavation and embankment, surfacing placement, asphalt concrete, new guardrail, landscaping the slopes, and installing large woody debris. A new bridge will be constructed with a longer span than the existing bridge. The existing bridge will not be removed until after the new one is constructed, allowing traffic to use the old alignment during construction. The new bridge will completely span the creek, with no in-water piers. Removal of the old bridge will require some work within the high water level of Nolan Creek. Large excavators will be used to remove riprap that currently is protecting the existing bridge from scour. Voids created by removal will be partially filled with a gravel backfill. Heavy equipment will be utilized to construct both the temporary diversion/bypass structure and the installation of engineered log jams. In addition, temporary falsework on streambed gravel (dry, but within OHWL) will be necessary for girder installation. A Wetland Biology Report and Environmental Mitigation Plan have been submitted in conjunction with the application. The Washington Department of Transportation prepared the State Environmental Policy Act (SEPA) checklist and issued a Determination of Non-Significance (DNS). The comment period expired on December 29, 2000. In accordance with WAC 197-11-600(4)(c) an addendum to the DNS has been prepared to address the potential impacts to an existing wetland. The application may be subject to the following permitting.
- Shoreline Conditional Use Permit
- Jefferson County Unified Development Code
- Hydraulic Project Approval from the Department of Fish and Wildlife
- National Marine Fisheries Service
- Washington State Department of Ecology
- U.S. Army Corps of Engineers
|
Date Issued:8/27/2002 |
|
Applicant: WA ST DOT |
Expiration Date:6/19/2004 12:00:00 AM |
|
Site Address: .................... |
Case Finaled: |
|
Parcel No:000000220
|
Other Cases |
Parcel Data |
Map It |
Parcels |
Images |
|
Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
3/24/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Close case
|
|
Date Completed:
|
| | |
9/30/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve SDP Permit-UF
|
|
Date Completed:
|
| | |
8/27/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve SDP Permit-UF
|
|
Date Completed:
|
| | |
6/19/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Review Complete-U
|
|
Date Completed:
|
| | |
6/19/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Hearing Exam PH Notice-APO-UF
|
|
Date Completed:
|
| | |
5/15/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Hearing Exam PH Notice-Pub-UF
|
|
Date Completed:
|
| | |
5/15/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Ntc of App +30-APO-UF
|
|
Date Completed:
|
| | |
4/10/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Ntc of App +30-Publish-UF
|
|
Date Completed:
|
| | |
4/10/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
4/10/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
3/27/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-U
|
|
Date Completed:
|
| | |
4/8/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
3/22/2002
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
5/15/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
3/27/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
5/15/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
5/15/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
5/15/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
5/15/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Application Received-UF
|
|
Date Completed:
|
| | |
3/22/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
Notification Prior to Beginning
|
|
Wording
|
| | |
The proponent shall notify the Jefferson County Department of Community Development at (360) 379-4450 forty-eight (48) hours prior to commencing construction in order to allow monitoring and ensure compliance with permit conditions.
|
|
|
Title:
|
| | |
Other Work/Separate Approval
|
|
Wording
|
| | |
Work within the jurisdiction of the Shoreline Master Program other than as described above shall receive separate review from this Department.
|
|
|
Title:
|
| | |
Site Plan
|
|
Wording
|
| | |
Construction shall be in substantial compliance with the site plan submitted on 3/21/02 as it exists now or is hereafter amended by Jefferson County and/or the Washington Department of Ecology. In addition, the Revegetation Plan submitted on 6/18/02 has been approved.
|
|
|
Title:
|
| | |
Progress towards completion
|
|
Wording
|
| | |
Substantial progress towards completion of the project shall be performed within two years of the issuance of the permit.
|
|
|
Title:
|
| | |
Custom Universal Condition
|
|
Wording
|
| | |
The applicant shall follow all of the permit conditions rendered through the public hearing on 6/4/02. The Hearing Examiners conditions are the following:
1. The applicant shall follow all conditions of the Hydraulic Project Approval (HPA) issued by the Department of Fish and Wildlife.
2. As a condition of the required Jefferson County Stormwater Management Permit associated with the proposal, the applicant shall submit a Temporary Erosion and Sediment Control Plan prior to commencing construction.
3. Construction shall be in substantial compliance with the submitted site plan as it exists now or is hereafter amended by Jefferson County and/or the Department of Ecology.
4. Submit and have approved a Spill Prevention Control and Countermeasures Plan addressing hazardous materials containment and storage.
5. Prior to the bridge demolition and rip rap removal the applicant shall tightline the creek through the project area through a temporary culvert, WSDOT biologists will remove any fish which may be present.
6. Stream banks and the construction corridor shall be replanted with native vegetation as stipulated through the revised restoration plan.
7. All trash, food waste, and other items shall be picked up and removed from the project area on a daily basis, for projects in or within 1.0 miles of suitable or critical marbled murrelet nesting habitat.
8. Best Management Practices (BMPs) shall be used to ensure that no foreign material such as oil or fuel from construction equipment will enter any wetlands, flowing or standing water.
9. Road drainage shall be designed to control the dispersal of surface runoff from roads and exposed soils in order to minimize turbid water from draining into waterways.
10. Earthworks shall be designed to provide waste and borrow areas that will produce a minimum of erosion, water turbidity, and aesthetic damage.
11. Cut and fill slopes shall be designed at the normal angle of repose or less.
12. Waterway crossings shall be designed to provide minimal disturbance to banks.
13. Waterway crossings shall be designed so the integrity of the naturally occurring geohydraulic process is maintained.
14. Roads, bridges, culverts, and similar devices shall afford maximum protection for fisheries resources.
15. Excess material shall be deposited in stable location and not into stream corridors where such materials degrade water quality, impede floodwaters, or alter naturally occurring geohydraulic processess.
16. The applicant shall be responsible for stormwater monitoring all fill material being deposited offsite.
17. Mechanical apparatus, rather than chemicals, shall be used for brush clearing maintenance wherever practicable.
18. Equipment used for transportation, storage, or application of chemicals shall be maintained in leak-proof condition. If there is evidence of chemical leakage, the further use of such equipment must be suspended until the deficiency has been satisfactorily corrected.
19. Pesticides shall be used, handled, and disposed in accordance with provisions of the Washington State Pesticide Application Act (RCW 15.57) and the Washington State Pesticide Application Act (RCW 17.21) unless the provision of this Master Program are stringent, in which case the higher standard will apply.
20. Whenever water is taken from any waterway or water impoundment for use in the mixing of chemicals, precautions shall be taken to prevent contamination of the water source. A portable pump shall be used with the necessary suction hose and check valves to supply water from streams; such a pump is to be used only for water.
21. Application of fertilizers shall assure that no fertilizers is deposited into waterways.
|
|
|
Title:
|
| | |
Hydraulic Code/HPA Check
|
|
Wording
|
| | |
Prior to commencing development activity, proponent is responsible for informing the Washington Department of Fish and Wildlife (WDFW) in order for WDFW to determine whether this action is subject to the Washington State Hydraulic Code (Chapter 220-10 WAC). Hydraulic Project Approval (HPA) is required for all hydraulic projects, which are defined as construction or performance of other work that will use, divert, obstruct, or change the natural flow or bed of any of the salt or fresh waters of the state.
|
|
|
Title:
|
| | |
Comply with HPA
|
|
Wording
|
| | |
In addition to Jefferson County permit conditions, the project proponent shall comply with all conditions set forth by the Washington Department of Fish and Wildlife through Hydraulic Project Approval.
|
|
|
Title:
|
| | |
Army Corps Check
|
|
Wording
|
| | |
Prior to commencing development activity, the proponent is responsible for informing the US Army Corps of Engineers (COE) in order for COE to determine whether a Department of the Army permit or review is required. Generally, review is required for construction and dredging in or around navigable waters of the US and for work or fill in hydrologically connected wetlands. Contact the US Army Corps of Engineers, Seattle District Regulatory Branch, PO Box 3755, Seattle WA 98124, (206) 764-3495, for more information.
|
|