Case Number:SDP2002-00005 Case Status:Finaled Date Received:1/29/2002
Description:Emergency Bank Protection. Approximately 400 feet of river bank had eroded due to recent high waters. Date Issued:1/31/2002
Applicant: STATE OF WASHINGTON - DOT Expiration Date:1/31/2003 12:00:00 AM
Site Address: .................... Case Finaled:
Parcel No:000000220 Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: File Archived
Date Completed: 2/18/2004
Disposition: DONE
Description: Close case
Date Completed: 9/30/2002
Disposition: DONE
Description: Det. of Completeness-UF
Date Completed: 1/31/2002
Disposition: DONE
Description: Issue Exemption
Date Completed: 1/31/2002
Disposition: DONE
Description: Case Entered
Date Completed: 1/29/2002
Disposition:
Description: Septic Review Complete-U
Date Completed: 1/31/2002
Disposition: DONE
Description: App Substantially Complete-U
Date Completed: 1/31/2002
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 1/31/2002
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 1/31/2002
Disposition: DONE
Description: Consistency Review-U
Date Completed: 1/31/2002
Disposition: DONE
Description: RAP Review Complete-U
Date Completed: 1/31/2002
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: Other Work/Separate Approval
Wording Work within the jurisdiction of the Shoreline Master Program other than as described above shall receive separate review from this Department.

Title: Treated Materials Must be Cured
Wording All lumber and other materials treated with preservative shall be sufficiently cured to minimize leaching into the water or shore bed, in accordance with the Best Management Practices approved by the Washington Department of Fish and Wildlife.

Title: Progress towards completion
Wording Substantial progress towards completion of the project shall be performed within two years of the issuance of the permit.

Title: Comply with HPA
Wording In addition to Jefferson County permit conditions, the project proponent shall comply with all conditions set forth by the Washington Department of Fish and Wildlife through Hydraulic Project Approval.

Title: Army Corps Check
Wording Prior to commencing development activity, the proponent is responsible for informing the US Army Corps of Engineers (COE) in order for COE to determine whether a Department of the Army permit or review is required. Generally, review is required for construction and dredging in or around navigable waters of the US and for work or fill in hydrologically connected wetlands. Contact the US Army Corps of Engineers, Seattle District Regulatory Branch, PO Box 3755, Seattle WA 98124, (206) 764-3495, for more information.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-HPA Issued
Wording The Washington Department of Fish and Wildlife issued Hydraulic Project Approval (HPA) for this activity on 1/17/02 under Log Number 00-E9750-01. The HPA expires on 1/28/02.

Title: F-SEPA Exempt
Wording Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-880(Emergencies).

Title: F-Custom Case Specific Finding
Wording The proposal is classified as an Exemption under section 3.402(8) of the Jefferson County Shoreline Master Program.

Title: F-SDP Exemption Section
Wording The Development Review Division finds that this proposal is consistent with Shoreline Master Program Section 3.402.(8) and is consequently exempt from the substantial development permit (SDP) requirements. Exemptions from the substantial development permit requirements do not exempt a proposed development from compliance with the applicable policies and standards of the Shoreline Master Program or other applicable Federal, State, or local permit or license requirements.