Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
12/29/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Close case
|
|
Date Completed:
|
| | |
12/10/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Type I Permit-U
|
|
Date Completed:
|
| | |
4/27/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
3/26/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
3/26/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
3/13/2001
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
4/27/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
4/27/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
4/27/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
4/27/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
4/27/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
Other Work/Separate Approval
|
|
Wording
|
| | |
Work within the jurisdiction of the Shoreline Master Program other than as described above shall receive separate review from this Department.
|
|
|
Title:
|
| | |
Min Use of Hazardous Materials
|
|
Wording
|
| | |
The design, location, and construction of docks, piers, and floats, as well as their subsequent use, shall avoid adverse effects on fish, shellfish, wildlife, marine vegetation, water quality, and geohydraulic processes. Construction methods shall minimize the use of materials hazardous to the environment. All work will take place six hundred feet offshore. A biological assesment has been prepared by Steve Thiesfield, a Habitat Biologist with the Department of Fish and Wildlife.
|
|
|
Title:
|
| | |
Treated Materials Must be Cured
|
|
Wording
|
| | |
All lumber and other materials treated with preservative shall be sufficiently cured to minimize leaching into the water or shore bed, in accordance with the Best Management Practices approved by the Washington Department of Fish and Wildlife.
|
|
|
Title:
|
| | |
Exempt Maintenance Condition
|
|
Wording
|
| | |
The development shall be essentially the same as the original in location, size, configuration, and external appearance.
|
|
|
Title:
|
| | |
No Fill or Other Material
|
|
Wording
|
| | |
No fill or other material may be placed in the waters or intertidal areas of Jefferson County.
|
|
|
Title:
|
| | |
Comply with HPA
|
|
Wording
|
| | |
In addition to Jefferson County permit conditions, the project proponent shall comply with all conditions set forth by the Washington Department of Fish and Wildlife through Hydraulic Project Approval.
|
|
|
Title:
|
| | |
Army Corps Check
|
|
Wording
|
| | |
Prior to commencing development activity, the proponent is responsible for informing the US Army Corps of Engineers (COE) in order for COE to determine whether a Department of the Army permit or review is required. Generally, review is required for construction and dredging in or around navigable waters of the US and for work or fill in hydrologically connected wetlands. Contact the US Army Corps of Engineers, Seattle District Regulatory Branch, PO Box 3755, Seattle WA 98124, (206) 764-3495, for more information.
|
|
|
Title:
|
| | |
F-Custom Universal Finding
|
|
Wording
|
| | |
The proposal is is defined as an Exemption under Section 3.40(6) of the Jefferson County Shoreline Master Program. The applicant will perform general maintenance by installing two rubber tire mats on rock outcroppings to protect two anchor cables from wear due to the rubbing .
|
|
|
Title:
|
| | |
F-Custom Universal Finding
|
|
Wording
|
| | |
The work is scheduled to take place the Summer of 2001, and will require an estimated 10 days to complete the project.
|
|
|
Title:
|
| | |
F-SEPA Exempt
|
|
Wording
|
| | |
Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(3). The project has been defined as maintenance/repair to an existing bridge.
|
|
|
Title:
|
| | |
F-SDP Exemption Section
|
|
Wording
|
| | |
The Development Review Division finds that this proposal is consistent with Shoreline Master Program Section 3.402.(6) and is consequently exempt from the substantial development permit (SDP) requirements. Exemptions from the substantial development permit requirements do not exempt a proposed development from compliance with the applicable policies and standards of the Shoreline Master Program or other applicable Federal, State, or local permit or license requirements.
|
|