Case Number:SDP2001-00004 Case Status:Finaled Date Received:2/2/2001
Description:This three stage project has been initiated as a result of seasonal flooding that occurs over this section of highway. Stage one construction, which was completed in September 1995, raised the roadway from 0 to 4 feet. Since then, the highway has sunk as much as four feet. In stage two, we are proposing to raise the elevation of the road 0 to 4 feet again. This will require removal and resetting of the existing guardrail, and installing a culvert. The culvert installed under Stage 1 will remain in place. The fill will be placed within the same footprint as the previous fill. 1) The proposal is consistent with the Exemptions Section 3.402(6) of the Jefferson-Port Townsend Shoreline Management Master Program. 2) The original fill of the road bed was done under Corps of Engineers Nationwide Permit 23 (ref. #95-4-00107). Off-site mitigation was also done at that time. As the fill was placed on top of the previously permitted fill and no additional diversion will be needed, the Army Corps of Engineers representative has stated that no additional permit will be required. 3) The Department of Transportation issued a SEPA decision on April 7, 1995. Date Issued:3/13/2001
Applicant: WA ST DOT Expiration Date:3/13/2002 12:00:00 AM
Site Address: STREET NAME Case Finaled:
Parcel No:000000220 Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: File Archived
Date Completed: 12/29/2003
Disposition: DONE
Description: Close case
Date Completed: 12/9/2003
Disposition: DONE
Description: Issue Exemption
Date Completed: 3/13/2001
Disposition: DONE
Description: App Substantially Complete (F)
Date Completed: 2/14/2001
Disposition: DONE
Description: Case Entered
Date Completed: 2/2/2001
Disposition:
Description: Stormwater Review
Date Completed: 3/13/2001
Disposition: DONE
Description: Shoreline Planner Review
Date Completed: 3/13/2001
Disposition: DONE
Description: Env. Sensitive Area Review
Date Completed: 3/2/2001
Disposition: DONE
Description: Consistency Review
Date Completed: 3/2/2001
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: SMP JURISDICTION
Wording This approval pertains to Jefferson-Port Townsend Shoreline Management Master Program requirements only. The approval of any other agency with jurisdiction or any other reqired permits shall be obtained prior to undertaking the project.

Title: STORMWATER
Wording An Erosion and Sediment Control Plan shall be submitted and approved prior to commencement of any land disturbing activity.

Title: SHORELINE
Wording Work within the jurisdiction of the Shoreline Program other than described above shall receive seperate review from the Department of Community Development.

Title: No Fill or Other Material
Wording No fill or other material may be placed in the waters or intertidal areas of Jefferson County.