Title:
|
| | |
DEPTH 30"
|
|
Wording
|
| | |
Minimum cover allowed over utility lines placed accross or parallel to the roadway shall be no less than 30" below the level of the ditch.
|
|
|
Title:
|
| | |
PUSH DAMAGE
|
|
Wording
|
| | |
If any damage to the roadway occurs as a result of a utility road bore or push, the applicant shall repair by open cutting the roadway and backfilling with (C.D.F.) or a Concrete Density Slurry and compacted in 12 inch lifts. The final lift shall be 3 inches of asphalt concrete pavement. The joints shall be sealed with a petroleum based oil such as C.S.S. #1 or a similar product.
|
|
|
Title:
|
| | |
TRENCHCUT
|
|
Wording
|
| | |
The utility trench shall be backfilled and mechanically compacted.
|
|
|
Title:
|
| | |
NOTINSHOULDER
|
|
Wording
|
| | |
The applicant shall not place any utilities in the roadway shoulder.
|
|
|
Title:
|
| | |
INSPECTION
|
|
Wording
|
| | |
The applicant must contact the Public Works Department for a final inspection prior to completion.
|
|