Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
11/21/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Override - Parcel Holds
|
|
Date Completed:
|
| | |
11/21/2022
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Override - Parcel Holds
|
|
Date Completed:
|
| | |
11/21/2022
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Override - Parcel Holds
|
|
Date Completed:
|
| | |
11/21/2022
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Override - Parcel Holds
|
|
Date Completed:
|
| | |
11/21/2022
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Override - Parcel Holds
|
|
Date Completed:
|
| | |
11/21/2022
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
11/21/2022
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
A Clock Interrupt
|
|
Date Completed:
|
| | |
11/21/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-DRD
|
|
Date Completed:
|
| | |
11/21/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Miscellaneous
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
10/3/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
9/28/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Override - Parcel Holds
|
|
Date Completed:
|
| | |
9/28/2022
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Override - Parcel Holds
|
|
Date Completed:
|
| | |
9/28/2022
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
DRD Approval (Zoning)
|
|
Date Completed:
|
| | |
11/21/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Final Planning Approval
|
|
Date Completed:
|
| | |
11/21/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Address Review Complete
|
|
Date Completed:
|
| | |
9/28/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
11/21/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
11/21/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
11/21/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
10/3/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
10/7/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
9/28/2022
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
9/28/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
APPROVAL
|
|
Wording
|
| | |
This approval is to install one 48kW diesel generator with 240 gallon fuel tank and one 4'x9' (36.00 square foot) concrete generator slab only to an existing cell tower. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
SITE PLAN
|
|
Wording
|
| | |
The site plan as submitted with the modification to existing cell tower application on September 28, 2022 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the revised stamped, approved site plan dated November 21, 2022 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
CRITICAL AREAS
|
|
Wording
|
| | |
The Geographic Information Systems mapping review identified the following Critical Areas on the subject property: Wetlands, Critical Aquifer Recharge Areas. All critical areas on the parcel are well removed from the proposed project site and do not require special reports.
|
|
|
Title:
|
| | |
BEST MANAGEMENT PRACTICES
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
SMALL STORMWATER
|
|
Wording
|
| | |
The applicant is proposing to create or add 36 square feet of impervious surface and 36 square feet of land disturbing activities. JCC 18.30.060 and 18.30.070 require your proposal comply with Minimum Requirement #2 (Construction Stormwater Pollution Prevention) of the Department of Ecology Stormwater Management Manual for Western Washington to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
FOREST SETBACKS
|
|
Wording
|
| | |
All property lines are adjacent to Commercial Forest land. This requires a 250 foot setback. Construction within the approved fenced area is exempt from the setbacks.
|
|
|
Title:
|
| | |
FOREST LAND
|
|
Wording
|
| | |
Jefferson County has determined that the use of real property for agriculture and forestry operations is a high priority and favored use in the county. The county will not consider to be a nuisance those inconveniences or discomforts arising from such operations, if such operations are consistent with commonly accepted best management practices in compliance with local, state, and federal laws. If your real property includes or is within five hundred (500) feet of real property designated as Rural Residential 1:10 or 1:20, Rural Industrial, Rural Commercial, Agriculture, or Forestry, you may be subject to inconveniences or discomforts arising from such farming and forestry operations, including but not limited to noise, tree removal, odors, flies, fumes, dust, smoke, the operation of farm and forestry machinery during any 24-hour period, the storage and disposal of manure, and the application of permitted fertilizers and permitted pesticides. One or more of these inconveniences may occur as a result of agricultural and forestry operations which are in conformance with existing laws and regulations.
|
|
|
Title:
|
| | |
SEPA EXEMPT
|
|
Wording
|
| | |
The proposal is SEPA Exempt under WAC197-11-800(25)(a)(i).
|
|
|
Title:
|
| | |
REPAIRS
|
|
Wording
|
| | |
The proposal meets JCC18.42.020 (2) (d) which exempts the following from the provisions of the Chapter 18.42 JCC. Emergency or routine repairs, reconstruction, or routine maintenance of previously approved facilities, or replacement of transmitters, antennas, or other components of previously approved facilities which do not create a change in visual impact.
|
|
|
Title:
|
| | |
PERMITTED OUTRIGHT
|
|
Wording
|
| | |
CC 18.42.080 identifies the following as a permitted outright use: Attached or collocated wireless communications facilities on existing structures in designated forest lands and all commercial and industrial districts.
|
|
|
Title:
|
| | |
NOISE LEVELS
|
|
Wording
|
| | |
The installed permitted equipment will be compliant with Jefferson County Code 18.42.090 (g). T-Mobile will be responsible for not exceeding the maximum environmental noise levels set forth in WAC Chapter 173-60.
|
|
|
Title:
|
| | |
ACOUSTICAL REPORT
|
|
Wording
|
| | |
An Acoustical Report by the Greenbusch Group INC dated November 17, 2022 was submitted November 21, 2022 stating that the equipment cabinet installation and daytime testing of the emergency generator will comply with the State of Washington Administrative Code (WAC) Chapter 173-60.
|
|
|
Title:
|
| | |
WAC 173-60
|
|
Wording
|
| | |
WAC 173-60: Noise generated by the wireless telecommunication facility shall not exceed the maximum environmental noise levels established in Chapter 173-60, Washington Administrative Code, as it is now in effect or in effect or hereafter amended. All noise emitting equipment that cannot in any way operate below the maximum permitted noise level shall be housed in a sound-attenuating structure, unless otherwise stipulated in the project approval. The applicant may be required to submit sound attenuation plans for review and approval by the department.
|
|
|
Title:
|
| | |
PLANNER INITIALS
|
|
Wording
|
| | |
HS
|
|