Case Number:BLD2022-00523 |
Case Status:Pending |
Date Received:9/7/2022 |
|
Description:CELL TOWER MODIFICATION- modify existing cell t-mobile tower, remove and replace antenna on the tower and ground equipment: Tower Scope of Work: Remove (3) antennas; Install (3) antennas, (1) HCS 2.0 J-box W / breakout pendant, (1) 1-1/2" hybrid cable, (1) bird excluder (designed by others). Ground Scope of Work: Remove (1) existing cabinet: (1) SSC cabinet, (1) existing AMOE rack, (1) existing PPC/Telco cabinet; Relocate from (E) SSC cabinet to HPL3 cabinet (1) Raycap voltage booster W / (3) amplifiers; Relocate from existing AMOE rack TO HPL3 cabinet: (1) ASIL & (1) ABIO; Install (1) Purcell HPL3 cabinet W / (1) CSR IXRE V2 router, (1) Purcell LB3 battery cabinet W / (4) battery strings, (1) HCS 2.0 J-box, (1) Hframe, (1) 200A PPC cabinet W / Camlok, (1) Vertiv cube, (1) ice bridge and post as needed, (1) 12" diving board, (2) tech light w/ timer, (1) conduit strut step over behind HPL3. |
Date Issued: |
|
Applicant: POPE RESOURCES |
Expiration Date: |
|
Site Address:1442 SHINE RIDGE RD |
Case Finaled: |
|
Parcel No:821312001
|
Other Cases |
Parcel Data |
Map It |
More Details |
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
9/19/2022
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
A Clock Interrupt
|
|
Date Completed:
|
| | |
9/19/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-DRD
|
|
Date Completed:
|
| | |
9/19/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Miscellaneous
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
9/19/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
9/13/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
9/7/2022
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
9/19/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
APPROVAL
|
|
Wording
|
| | |
This approval is for modification to an existing cell tower to include: Tower Scope of Work: Remove (3) antennas; Install (3) antennas, (1) HCS 2.0 J-box W / breakout pendant, (1) 1-1/2" hybrid cable, (1) bird excluder (designed by others). Ground Scope of Work: Remove (1) existing cabinet: (1) SSC cabinet, (1) existing AMOE rack, (1) existing PPC/Telco cabinet; Relocate from (E) SSC cabinet to HPL3 cabinet (1) Raycap voltage booster W / (3) amplifiers; Relocate from existing AMOE rack TO HPL3 cabinet: (1) ASIL & (1) ABIO; Install (1) Purcell HPL3 cabinet W / (1) CSR IXRE V2 router, (1) Purcell LB3 battery cabinet W / (4) battery strings, (1) HCS 2.0 J-box, (1) Hframe, (1) 200A PPC cabinet W / Camlok, (1) Vertiv cube, (1) ice bridge and post as needed, (1) 12" diving board, (2) tech light w/ timer, (1) conduit strut step over behind HPL3 only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
SITE PLAN CHANGES
|
|
Wording
|
| | |
The site plan as submitted with the modification to existing cell tower application on September 2, 2022, approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the revised stamped, approved site plan dated September 19, 2022 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
BMPS
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
EXEMPT
|
|
Wording
|
| | |
The proposal meets JCC18.42.020 (2) (d) which exempts the following from the provisions of the Chapter 18.42 JCC. Emergency or routine repairs, reconstruction, or routine maintenance of previously approved facilities, or replacement of transmitters, antennas, or other components of previously approved facilities which do not create a change in visual impact.
|
|
|
Title:
|
| | |
COLOCATION
|
|
Wording
|
| | |
JCC 18.42.080 identifies the following as a permitted outright use: Attached or collocated wireless communications facilities on existing structures in designated forest lands and all commercial and industrial districts.
|
|
|
Title:
|
| | |
NOISE
|
|
Wording
|
| | |
The installed permitted equipment will be compliant with Jefferson County Code 18.42.090 (g). T-mobile will be responsible for not exceeding the maximum environmental noise levels set forth in WAC Chapter 173-60.
|
|
|
Title:
|
| | |
SEPA EXEMPT
|
|
Wording
|
| | |
This proposal is SEPA exempt under WAC197-11-800(25)(a)(i).
|
|