Case Number | | CAM2022-00493
|
|
Description | | Current permitted mining operation that would like to expand operations by 15 acres. Operations would be conducted in phases with 10 acres of active mining occurring at a time. Please see attached documents for quick reference.
What is required to expand operations?
Can operations mine within the water table? If so what requirements will be needed for approval?
How long does the permitting process take?
|
|
Last Name | | MAHR
|
|
Received Date | | 11/9/2022 4:20:13 PM
|
|
Status | | Pending
|
|
| | |
|
|
Case Number | | BLD2022-00523
|
|
Description | | CELL TOWER MODIFICATION- modify existing cell t-mobile tower, remove and replace antenna on the tower and ground equipment: Tower Scope of Work: Remove (3) antennas; Install (3) antennas, (1) HCS 2.0 J-box W / breakout pendant, (1) 1-1/2" hybrid cable, (1) bird excluder (designed by others). Ground Scope of Work: Remove (1) existing cabinet: (1) SSC cabinet, (1) existing AMOE rack, (1) existing PPC/Telco cabinet; Relocate from (E) SSC cabinet to HPL3 cabinet (1) Raycap voltage booster W / (3) amplifiers; Relocate from existing AMOE rack TO HPL3 cabinet: (1) ASIL & (1) ABIO; Install (1) Purcell HPL3 cabinet W / (1) CSR IXRE V2 router, (1) Purcell LB3 battery cabinet W / (4) battery strings, (1) HCS 2.0 J-box, (1) HÂframe, (1) 200A PPC cabinet W / Camlok, (1) Vertiv cube, (1) ice bridge and post as needed, (1) 12" diving board, (2) tech light w/ timer, (1) conduit strut step over behind HPL3.
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 9/7/2022 9:59:44 AM
|
|
Status | | Pending
|
|
| | |
|
|
Case Number | | CAM2022-00363
|
|
Description | | I would like to confirm if a separate land use entitlement is required, or if building plan check review only is needed for a proposed 6409(a) eligible facilities request modification to the existing T-Mobile wireless facility at 1442 Shine Ridge Rd. (lying SW of SR104), Oak Bay, WA 98365.
The scope of work will consist of:
Tower scope of work: Remove (2) antennas; Install (2) antennas, (1) HCS 2.0 J-Box w/ breakout pendant, (1) 1-1/2" hybrid cable.
Ground scope of work: Remove Existing SSC Cabinet, (1) AMOB Rack, (1) 100A PPC Cabinet; Relocate (1) 200A Meter; Install (1) Purcell HPL3 Cabinet W/: (1) voltage booster W/ (3) amplifiers & (1) CSR IXRE V2 router; Install (1) Purcell LB3 Battery Cabinet W/ (4) battery strings; Install (1) HCS 2.0 J-Box, (1) 8'-0" H-frame, (1) Vertiv cube, (1) 200A PPC cabinet, (1) CIENA box, (1) tech light, (1) grip step over, (1) 24" ICE bridge W/ 12" diving board.
There will be no change in tower dimensions (height or width), no new excavation, and no increase in equipment lease area. There will be a net increase of (1) equipment cabinet.
Please advise if a Land Use application needs to be filed, or if I can proceed with Building review.
Thank you,
|
|
Last Name | | LEW
|
|
Received Date | | 8/18/2022 1:29:02 PM
|
|
Status | | Withdrawn
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | BLD2022-00456
|
|
Description | | CELL TOWER-SMARTSKY INSTALL NEW MICROWAVE DISH; INSTALL (1) COMMSCOPE - l-IP8-107-D4M MW DISH; INSTALL (1) POWER CABLE (1/4"), INSTALL (1) POER CABLE (3/8") ; INSTALL (1) 2-1/2" SCH 40 (2-7/8" 0.0.) BY 8'-0" LONG GALV. PIPE W CROSSOVER HARDWARE; INSTALL (1) SITE PRO 1 - RS PIPE TO PIPE MOUNT. NO GROUND WORK.
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 8/5/2022 3:51:04 PM
|
|
Status | | Approved
|
|
| | |
|
|
Case Number | | USR2021-00052
|
|
Description | |
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 11/16/2021 3:41:32 PM
|
|
Status | | Pending
|
|
| | |
|
|
Case Number | | BLD2021-00668
|
|
Description | | MEMBRANE STRUCTURE FOR FUTURE CMT MILL
SEP2000-00122
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 11/10/2021 2:04:35 PM
|
|
Status | | Withdrawn
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | BLD2021-00667
|
|
Description | | REMODEL -POLE BUILDING FOR FUTURE CMT MILL
SEP00-00122
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 11/10/2021 1:45:47 PM
|
|
Status | | Withdrawn
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | ZON2021-00057
|
|
Description | | CONDITIONAL USE ADMINISTRATIVE PERMIT (C(a)) for a temporary interim commercial mass timber ("CMT") lumber mill located on land zoned as commercial forest 80 (CF 80). The interim CMT mill will operate as a small scale lumber mill with forest product processing on a repurposed gravel mine site, with accessory office, storage, and parking. The interim CMT mill will establish proof of concept for using CMT modules for mid rise and high rise construction, refine design and production techniques, and allow assembly of construction modules for a demonstration project to establish market position. The interim proposal will use the existing 3,500 square foot building, the existing on site 640 square foot office, and include a new separate tent structure up to 7,500 square feet located on top of the existing impervious surface. The noise generated will be minimal such as typical traffic noise levels of trucks and up to 20 employees, entering and exiting the site, during the hours of 7 AM to 7 PM. There is no smoke generated on site, a dust collection system will control sawdust, there are no fumes or odors anticipated, and there will be no vibrations of equipment outside of the workspace. Most operations will occur inside the existing buildings. There are no critical areas located on site and the parcel is surrounded by forestry and mining operations. This project is categorically exempt from SEPA for minor new construction of equal to or less than 12,000 square feet and fewer than 40 parking spaces under Washington Administrative Code (WAC) 197 11 800(1)(a)(i) through (iv) and Jefferson County Code (JCC) 18.40.750(1)(d) that identifies the size thresholds.
|
|
Last Name | | DAHLGREN INDUSTRIAL
|
|
Received Date | | 9/8/2021 1:59:53 PM
|
|
Status | | Withdrawn
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | SUB2021-00018
|
|
Description | | LOT CERTIFICATION
|
|
Last Name | | PROPERTIES LLC - JON ROSE
|
|
Received Date | | 8/10/2021 8:41:42 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | BLD2021-00460
|
|
Description | | CELL TOWER MOD- INSTALL THREE ANTENNAS AT ELEVATION RAD CENTER 170' AGL ON THE TOWER
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 8/10/2021 12:00:00 AM
|
|
Status | | Withdrawn
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | PRE2021-00023
|
|
Description | | CMT FACILITY
|
|
Last Name | | OSTERMAN
|
|
Received Date | | 7/6/2021 8:24:39 AM
|
|
Status | | M
|
|
| | |
|
|
Case Number | | ZON2021-00033
|
|
Description | | CODE INTERPRETATION - Lumber Mills Definition includes CMT mills.
|
|
Last Name | | OPG PROPERTIES LLC
|
|
Received Date | | 5/25/2021 8:57:26 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | CAM2020-00357
|
|
Description | | want to develop a wood product manufacturing plant with visitors center and 110 -120 employees
|
|
Last Name | | HARM
|
|
Received Date | | 12/8/2020 1:43:17 PM
|
|
Status | | INP
|
|
| | |
|
|
|
Case Number | | CAM2020-00062
|
|
Description | | CAM Meeting: Questions regarding adding generator to cell tower sites. Looking for decibel information, and class.
|
|
Last Name | | SAULS
|
|
Received Date | | 2/12/2020 2:16:38 PM
|
|
Status | | M
|
|
| | |
|
|
Case Number | | CAM2019-00542
|
|
Description | | Permit needed for new structure at seed farm? Need Critical Area review.
|
|
Last Name | | STAFFORD
|
|
Received Date | | 9/26/2019 11:40:44 AM
|
|
Status | | M
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | BLD2019-00345
|
|
Description | | CELL TOWER - REMOVE 2 PANEL ANTENNAS AND 2 TMAs; INSTALL 4 PANEL ANTENNAS AND 3 RRUs; REPLACE 3 EQUIPMENT CABINETS ON GROUND; NO INCREASE IN HEIGHT OR EXPANSION OF FOOTPRINT.
|
|
Last Name | | CROWN CASTLE
|
|
Received Date | | 8/2/2019 5:06:02 PM
|
|
Status | | Finaled
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | CAM2019-00434
|
|
Description | | STAFF CONSULTATION MEETING- NEED TO CONFIRM IF A CONSISTENCY REVIEW LAND USE PLANNING REVIEW WILL BE REQUIRED FOR SCOPE OF WORK
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 7/12/2019 11:06:09 AM
|
|
Status | | M
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | BLD2019-00174
|
|
Description | | MODIFICATION TO EXISTING CELL TOWER - UPGRADE EXISTING 1+1 HSBY OFF -AIR MW TO RLAG 94=0) REPLACING ALL EXISTING ODU'S WITH NEW HQAM ODUS AND EQUAL SPLIT COUPLERS.
NO GROUND DISTRUBANCE
|
|
Last Name | | CROWN CASTLE
|
|
Received Date | | 4/30/2019 2:34:44 PM
|
|
Status | | Canceled
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | BLD2019-00080
|
|
Description | | EXISTING CELL TOWER - REMOVE AND REPLACE EQUIPEMENT -NO INCREASE IN HEIGHT
|
|
Last Name | | VERIZON
|
|
Received Date | | 3/7/2019 11:20:49 AM
|
|
Status | | Finaled
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | BLD2017-00460
|
|
Description | | NEW CO-LOCATION EXSTING CELL TOWER- 1- MICROWAVE ANTENNA W/ ANCILLARY EQUIPMENT. 6 PANEL ANNTENNAS, 6 RRH- WITH GROUND WORK- CABINET WITH GPS ANTENNA 1 UTILITY FRAME & ICE BRIDGE
|
|
Last Name | | CROWN CASTLE
|
|
Received Date | | 10/6/2017 12:48:00 PM
|
|
Status | | Canceled
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | BLD2017-00236
|
|
Description | | REMOVAL AND REPLACEMENT OF 3 PANEL ANTENNAS- ZERO GROUND WORK
|
|
Last Name | | ON BEHALF OF SPRINT
|
|
Received Date | | 6/5/2017 2:32:37 PM
|
|
Status | | Finaled
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | BLD2016-00439
|
|
Description | | EXISTING CELL TOWER - REPLACE 3 EXISTING MOUNTS WITH 3 NEW MOUNT, REPLACE 3 EXISTING PANEL ANTENNAS WITH 3 NEW PANAL ANTENNAS AND INSTALL 3 RRH'S
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 10/4/2016 11:42:35 AM
|
|
Status | | Finaled
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | FPA2614438
|
|
Description | | 124 ac Harvest
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 8/4/2016 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2614248
|
|
Description | | 65 ac Harvest
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 5/16/2016 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | BLD2015-00228
|
|
Description | | REPLACEMENT OF 2 PANEL ANTENNAS AND REMOVE 2 TMAS ON THE EXISTING TOWER- INSTALL 2 FRLB AND 1 FBBC IN EXISTING CABINETS ON THE GROUND
|
|
Last Name | | ON BEHALF OF T-MOBILE
|
|
Received Date | | 7/6/2015 11:02:47 AM
|
|
Status | | Finaled
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | BLD2015-00184
|
|
Description | | REPLACE MICROWAVE DISH ANTENNA ON EXISTING WIRELESS COMMUNICATIONS TOWER
|
|
Last Name | | VERIZON WIRELESS
|
|
Received Date | | 6/4/2015 12:52:09 PM
|
|
Status | | Canceled
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | FPA2613325
|
|
Description | | Harvest 59 acres, 6100 ft of road construction
Amendment 4/8/2015 - Add Biomass harvest on Unit 3
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 12/3/2014 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | BLD2013-00063
|
|
Description | | MODIFICATION TO ADD 2 EQUPMENT CABINETS -REMOVE4 CABINETS, ADD 3 PANEL ANTENNAS-REMOVE 6 PANEL ANTENNA, & 1 MICROWAVE ANTENNAS
|
|
Last Name | | SPRINT
|
|
Received Date | | 2/20/2013 3:39:33 PM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | BLD2012-00381
|
|
Description | | MODIFICATION TO EXISTING CELL TOWER. UPGRAGE & REPLACE EXISTING 3 PANEL ANTENNAS AND NEW CABINET WITHIN EXISTING CONCRETE PAD
|
|
Last Name | | AT&T MOBILITY C/O RYKA CONSULTING
|
|
Received Date | | 11/26/2012 2:02:14 PM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | BLD2012-00049
|
|
Description | | REMOVE 1 MICROWAVE DISH & ADD 3 NEW MICROWAVE DISHES TO EXISTING TOWER
|
|
Last Name | | AT&T
|
|
Received Date | | 2/16/2012 12:00:00 AM
|
|
Status | | Canceled
|
|
| | |
|
|
Case Number | | FPA2611580
|
|
Description | | 2012 fertilization: 435-acres.
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 1/25/2012 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2611268
|
|
Description | | 470-acre spray.
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 7/5/2011 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | BLD2011-00140
|
|
Description | | REMOVE (1) 6' ANTENNA ON EXISTING 105' TOWER, ADD (1) 8' ANTENNA ON EXISTING 190' TOWER, REMOVE (6) AND ADD (6) NEW ANTENNAS ON EXISTING 190' TOWER AND ADD (6) NEW ANTENNAS
|
|
Last Name | | VERIZON WIRELESS
|
|
Received Date | | 6/7/2011 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2610872
|
|
Description | | 69-acre timber harvest and 700 feet of road construction
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 12/15/2010 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | BLD2010-00403
|
|
Description | | CO-LOCATE ON EXISTING TOWER
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 12/8/2010 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | BLD2010-00118
|
|
Description | | ADD (3) PANEL ANTENNAS-1 PER SECTOR, (3) TMA's, (6) RUNS OF COAX & (3) DIPLEXERS - PERMIT CANCELLED DUE TO NON-PYMNT UNDER AMNESTY PROG
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 4/20/2010 12:00:00 AM
|
|
Status | | Canceled
|
|
| | |
|
|
Case Number | | BLD2008-00517
|
|
Description | | TEMPORARY BUS SHELTER @ SHINE PIT PARK & RIDE
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 12/24/2008 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | PRE2008-00030
|
|
Description | | Proposal to install 2 temporary shelters and sanicans during hood canal bridge closure.
|
|
Last Name | | ZEIGLER
|
|
Received Date | | 6/25/2008 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | BLD2008-00117
|
|
Description | | Stormwater w/SEPA: Stormwater Permit with SEPA: Fred Hill Material Inc. (FHM) leases from Pope Resources who owns the 72,000 acre Hood Canal Tree Farm. FHM mineral extraction and processing areas (referred to as the Shine Hub) totals 211.5 acres and is designated a Mineral Resource Overlay District (MRL).
The current proposal by FHM is to add 10 acres of additional mineral extraction area (pit area), adjacent to the Shine Hub. These areas would be comprised of two 5-acre segments (V & W). This would bring the total area to 221.5 acres currently regulated under a DNR Reclamation permit. This area has been logged by Pope Resources through Forest Practice Application (FPA). The additional pit area is located in a Commercial Forest designation, where mining is a permitted activity provided that no more than 10 acres is disturbed at any one time. Disturbed area is defined by RCW 78.44.031(5) and is determined by the WA State Department of Natural Resources through their Reclamation Permit.
The current mineral extraction is occurring in Segments R, S, T, & U where a good deposit of gravel had been located. This area is located behind a berm south of the Shine Hub. The proposed expansion (Segments V & W) are located north of Segments R, S, T, & U (see Reclamation Sequence Map). The extraction would start at the west boundary of the existing Shine Pit and continue eastward through two reclamation segments of approximately 5 acres each. The mining will utilize the cut-to-grade method. The grade of the mining slopes will "daylight" at the edge of the boundary of the new mining area, without a reclamation setback. The maximum depth of mining within this expansion will be approximately 50 feet. The finished floor of the mine will have a vertical separation of more than 100 feet above the seasonal high groundwater table (see cross sectional map for more details). Final reclamation will be done in a manner to emulate the natural sinuous lopes of the surrounding terrain. The final floor and finished slopes of the mine will be contoured to vary in elevation and be graded to naturally sweep into adjacent terrain. After the area is mined, stored topsoil would be spread over the area, forest debris spread over the area, a cover crop established, and then replanted with Douglas Fir for the subsequent use for timber production. It is anticipated that all of the mineral extraction (segments V & W) south of the Shine Hub would be reclaimed by winter of 2008 (per the Reclamation Sequence Map).
The Wahl Extraction area (approved through MLA03-377 on July 18, 2005) is located near Thorndyke Creek and its unnamed Tributary. The applicant has indicated that they are not seeking to mine within the Wahl Extraction Area at the present time because they want to obtain base line surface and groundwater monitoring data before mineral extraction occurs. This will help ensure that the impacts associated with mineral extraction can be separated from the natural hydraulic conditions.
Jefferson County has a Stormwater Permit to review and is the lead agency for the environmental review of the proposal under SEPA. Jefferson County is issuing a MDNS for this proposal.
The threshold determination for this proposal incorporates the Final Modified MDNS issued for Ace Paving Conditional Use Application (ZON 98-41) within the 144 acre mineral extraction and processing area, which was issued by Jefferson County DCD on June 1, 1999. Documents referenced in this notice are available the Jefferson County DCD during office hours.
The applicant will require an amended WA State DNR Reclamation Permit and an amended NPDES General Sand and Gravel permit from the WA State Department of Ecology.
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 3/27/2008 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2609166
|
|
Description | | 705 acres of chemical spray
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 3/13/2008 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2608928
|
|
Description | | 7 acres of timber harvest
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 11/1/2007 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | ZON2007-00078
|
|
Description | | WSDOT Temporary Public Park and Ride located at the Fred Hill Materials' Shine Pit consisting of approximately 12.2 acres of gravel parking area and 2.1 acres of paved access road. The park and ride will operate during May/June 2009 when the Hood Canal Bridge is scheduled for closure. The park and ride area will be leased from August 1, 2008 - September 30, 2009. Construction of the park and ride may occur as early as spring 2008. Individuals using the park and ride will be shuttled to a temporary water shuttle at South Point that provides service to Kitsap County. The park and ride will be accessed via Rock-to-Go Road and an existing on-site access road. Impervious asphalt surfaces have been minimized to include only the shuttle bus turnaround area, ADA parking and a portion of the access road. The parking area will be compacted gravel. Stormwater from the park and ride asphalt and gravel areas will be directed to a spill containment oil-water separator and will be conveyed to existing process water settling ponds for water quality treatment. These existing settling ponds are not a requirement of the existing permit, but have been constructed to provide additional settling prior to infiltration of existing stormwater. Two of the four settling ponds will be dedicated to water quality treatment for impervious surfaces related to the park and ride area. Stormwater will then be infiltrated to groundwater at the existing infiltration area to the north end of the site consistent with the existing stormwater permit. Stormwater will be directed to the existing process water settling ponds for water quality treatment prior to entering the site's existing stormwater infiltration area. All asphalt and gravel will be removed after the bridge is re-opened. The site will be replanted and reclaimed per WDNR standards.
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 9/21/2007 12:00:00 AM
|
|
Status | | E
|
|
| | |
|
|
Case Number | | PRE2007-00028
|
|
Description | | DOT temporary park & ride 19 acre site of which 3 acres will be asphalt and stormwater facilities.
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 7/16/2007 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2608490
|
|
Description | | 68 acres of timber harvest, 500 feet of road construction
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 5/1/2007 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2608276
|
|
Description | | 460 acre fertilizer.
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 2/7/2007 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2606545
|
|
Description | | Harvest of 7 acres
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 2/28/2005 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | BLD2004-00664
|
|
Description | | CELL TOWER CO-LOCATE
|
|
Last Name | | KDC ARCHITECTS.ENGINEERS, P.C.
|
|
Received Date | | 10/20/2004 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2605722
|
|
Description | | Aerial chemical application
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 11/3/2003 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2605703
|
|
Description | | Aerial Chemical Application
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 10/15/2003 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | BLD2003-00153
|
|
Description | | CELL TOWER REPLACEMENT
|
|
Last Name | | CINGULAR WIRELESS
|
|
Received Date | | 3/10/2003 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2604910
|
|
Description | | Aerial Chemical Application
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 9/26/2002 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | SOM2000-00122
|
|
Description | |
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 6/5/2002 12:00:00 AM
|
|
Status | | RCR
|
|
| | |
|
|
Case Number | | ZON2002-00049
|
|
Description | | Comprehensive Plan Land Use Map designation of approximately 6,240 acres as Mineral Resource Overlay District.
|
|
Last Name | | FRED HILL MATERIALS INC
|
|
Received Date | | 4/30/2002 12:00:00 AM
|
|
Status | | DAP
|
|
| | |
|
|
|
Case Number | | BLD2002-00119
|
|
Description | | CO LOCATE WIRELESS TELECOMMUNICATION ANTENNE
|
|
Last Name | | CINGULAR WIRELESS
|
|
Received Date | | 3/7/2002 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | BLD2002-00120
|
|
Description | | PROPANE TANK INSTALLATION
|
|
Last Name | | CINGULAR WIRELESS
|
|
Received Date | | 3/7/2002 12:00:00 AM
|
|
Status | | Canceled
|
|
| | |
|
|
Case Number | | USR2001-00083
|
|
Description | |
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 12/18/2001 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2604213
|
|
Description | | Chemical Application
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 10/5/2001 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | BLD2001-00550
|
|
Description | | NO MLA REQ'D - MICROWAVE REPLACEMENT ON EXISTING TOWER
|
|
Last Name | | AT&T WIRELESS
|
|
Received Date | | 10/2/2001 12:00:00 AM
|
|
Status | | Canceled
|
|
| | |
|
|
Case Number | | PRE2001-00051
|
|
Description | | Pre-Application to construct a stump grinding facility to recycle wood products.
Woody debris will be trucked in via Rock-to-go Rd. Tub grinders will be utilized to chip woody debris. Chips may be used for mining reclamation on-site or hauled off-site.
|
|
Last Name | | FRED HILL MATERIALS
|
|
Received Date | | 8/1/2001 12:00:00 AM
|
|
Status | | Canceled
|
|
| | |
|
|
Case Number | | ZON2001-00003
|
|
Description | | Installation of twelve, approx 1' x 8' directional panel antennas and one 6' diameter dish antenna at the 136 and 123-foot levels of an existing 195' tall Voicestream lattice communications tower. The project also includes the installation of an approx 220 SF equipment shelter located near the base of the tower.
|
|
Last Name | | NEXTEL COMMUNICATIONS
|
|
Received Date | | 1/31/2001 12:00:00 AM
|
|
Status | | CLS
|
|
| | |
|
|
Case Number | | FPA2603617
|
|
Description | | Road construction to cross a 15' wide forested wetland. Road is for installation of underground electrical lines.
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 1/31/2001 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2602047
|
|
Description | | Renewal for road construction portion of original permit
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 12/21/2000 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
|
Case Number | | SEP2000-00122
See SOM case for current septic system activity.
|
|
Description | |
|
|
Last Name | | OLYMPIC RESOURCE MANAGEMENT
|
|
Received Date | | 5/26/2000 12:00:00 AM
|
|
Status | | Finaled
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | BLD1999-00398
|
|
Description | | Colocate wireless communication equipment & antennas on Voice Stream new tower.
|
|
Last Name | | VOICE STREAM WIRELESS
|
|
Received Date | | 6/23/1999 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | BLD1999-00351
|
|
Description | | 195' lattice tower for wireless communications including 2 dish antennas and up to 9 panel antennas.
|
|
Last Name | | VOICE STREAM WIRELESS
|
|
Received Date | | 6/11/1999 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | ENV1999-00003
|
|
Description | | to construct a 195-foot lattice tower to support a three-sector antenna array with (3) antennas per sector (9 antennas total). In addition, Voice Stream may elect to mount two microwave dishe antennas (1 @ 4' diameter & 1 @ 8' diameter) onto the tower in the future. This lower power minor communications facility will transmit and receive radio signals for digital wireless (PCS) communications.
|
|
Last Name | | VOICE STREAM WIRELESS STE 101
|
|
Received Date | | 6/11/1999 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | PRE1999-00012
|
|
Description | | Construct 195' lattice tower for wireless communications including 2 dish antennas and up to 9 panel antennas.
|
|
Last Name | | VOICE STREAM WIRELESS
|
|
Received Date | | 4/22/1999 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | FPA2602045
|
|
Description | | Forest practice application.
|
|
Last Name | | POPE RESOURCES
|
|
Received Date | | 11/16/1998 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | ZON1998-00041
|
|
Description | | Establish an asphalt batch plant. The batch plant is proposed to be used to mix hot asphalt with gravel, to produce a material suitable for road surfacing. The plant is of modular construction and includes a 10 foot by 30 foot bag house, a 10 foot by 30 foot dryer, and a 16 foot by 18 foot tower mixer. The tower height is 60 feet.
|
|
Last Name | | ACE PAVING
|
|
Received Date | | 11/6/1998 12:00:00 AM
|
|
Status | | Finaled
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | FPA2601984
|
|
Description | | Forest practice application.
|
|
Last Name | | POPR RESOURCES
|
|
Received Date | | 10/1/1998 12:00:00 AM
|
|
Status | | Denied
|
|
| | |
|
|
Case Number | | CAR1998-00241
|
|
Description | | establish an asphalt batch plant
|
|
Last Name | | ACE PAVING
|
|
Received Date | | 9/11/1998 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | PRE1998-00023
|
|
Description | | establish an asphalt batch plant
|
|
Last Name | | ACE PAVING
|
|
Received Date | | 6/8/1998 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | BLD1997-00803
|
|
Description | | Erect a portable asphalt plant
|
|
Last Name | | ACE PAVING
|
|
Received Date | | 12/18/1997 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | CAR1997-00275
|
|
Description | | pole building shop, maintenance building
|
|
Last Name | | FRED HILL MATERIALS, INC
|
|
Received Date | | 9/29/1997 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | BLD1997-00624
|
|
Description | | pole building shop, maintenance building
|
|
Last Name | | FRED HILL MATERIALS, INC
|
|
Received Date | | 9/23/1997 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | PRE1997-00007
|
|
Description | | erect a temporary asphalt & concrete batch plant
|
|
Last Name | | FRED HILL MATERIALS, INC
|
|
Received Date | | 2/25/1997 12:00:00 AM
|
|
Status | | Canceled
|
|
LaserFiche Links | | View LaserFiche Documents |
|
|
Case Number | | CAR1994-00118
|
|
Description | |
|
|
Last Name | | US WEST NEW VECTOR GROUP INC
|
|
Received Date | | 9/15/1994 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|
|
Case Number | | BLD1994-00657
|
|
Description | | premanufactured building for telephone equipment, US WEST
|
|
Last Name | | US WEST NEW VECTOR GROUP INC
|
|
Received Date | | 9/15/1994 12:00:00 AM
|
|
Status | | Finaled
|
|
| | |
|