Case Number:BLD2022-00521 |
Case Status:Approved |
Date Received:9/6/2022 |
|
Description:CELL TOWER MODIFICATION-6409(a) modification to existing T-Mobile wireless facility to remove and replace antennas on the tower and ground equipment. Scope of work includes: Tower scope of work: Remove (2) antennas; Install (2) antennas, (1) HCS 2.0 J-Box w/ breakout pendant, (1) 1-1/2" hybrid cable. Ground scope of work: Remove Existing SSC Cabinet, (1) AMOE Rack, (1) 100A PPC Cabinet; Relocate (1) 200A Meter; Install (1) Purcell HPL3 Cabinet W /: (1) voltage booster W /(3) amplifiers & (1) CSR IXRE V2 router; Install (1) Purcell LB3 Battery Cabinet W / (4) battery strings; Install (1) HCS 2.0 J-Box, (1) 8'-o" H-frame, (1) Vertiv cube, (1) 200A PPC cabinet, (1) CIENA box, (1) tech light, (1) grip step over, (1) 24" ICE bridge W / 12" diving board. |
Date Issued:11/28/2022 |
|
Applicant: POPE RESOURCES |
Expiration Date:11/28/2023 12:00:00 AM |
|
Site Address:2805 LARSON LAKE RD |
Case Finaled: |
|
Parcel No:801122002
|
Other Cases |
Parcel Data |
Map It |
More Details |
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
11/28/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Override - Parcel Holds
|
|
Date Completed:
|
| | |
11/28/2022
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
9/19/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
A Clock Interrupt
|
|
Date Completed:
|
| | |
9/19/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-DRD
|
|
Date Completed:
|
| | |
9/19/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Miscellaneous
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
9/19/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
11/28/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
9/13/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
9/6/2022
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
9/19/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
APPROVAL
|
|
Wording
|
| | |
This approval is for modification to an existing cell tower to include: Tower scope of work: Remove (2) antennas; Install (2) antennas, (1) HCS 2.0 J-Box w/ breakout pendant, (1) 1-1/2" hybrid cable. Ground scope of work: Remove Existing SSC Cabinet, (1) AMOE Rack, (1) 100A PPC Cabinet; Relocate (1) 200A Meter; Install (1) Purcell HPL3 Cabinet W /: (1) voltage booster W /(3) amplifiers & (1) CSR IXRE V2 router; Install (1) Purcell LB3 Battery Cabinet W / (4) battery strings; Install (1) HCS 2.0 J-Box, (1) 8'-o" H-frame, (1) Vertiv cube, (1) 200A PPC cabinet, (1) CIENA box, (1) tech light, (1) grip step over, (1) 24" ICE bridge W / 12" diving board only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
SITE PLAN CHANGES
|
|
Wording
|
| | |
The site plan as submitted with the modification to existing cell tower application on September 2, 2022 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the revised stamped, approved site plan dated September 19, 2022 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
BMPS
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
EXEMPT
|
|
Wording
|
| | |
The proposal meets JCC18.42.020 (2) (d) which exempts the following from the provisions of the Chapter 18.42 JCC. Emergency or routine repairs, reconstruction, or routine maintenance of previously approved facilities, or replacement of transmitters, antennas, or other components of previously approved facilities which do not create a change in visual impact.
|
|
|
Title:
|
| | |
COLOCATION
|
|
Wording
|
| | |
JCC 18.42.080 identifies the following as a permitted outright use: Attached or collocated wireless communications facilities on existing structures in designated forest lands and all commercial and industrial districts.
|
|
|
Title:
|
| | |
NOISE
|
|
Wording
|
| | |
The installed permitted equipment will be compliant with Jefferson County Code 18.42.090 (g). T-Mobile will be responsible for not exceeding the maximum environmental noise levels set forth in WAC Chapter 173-60.
|
|
|
Title:
|
| | |
SEPA EXEMPT
|
|
Wording
|
| | |
This proposal is SEPA exempt under WAC197-11-800(25)(a)(i).
|
|