Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
9/15/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Override - Parcel Holds
|
|
Date Completed:
|
| | |
9/15/2022
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
9/15/2022
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Override - Parcel Holds
|
|
Date Completed:
|
| | |
9/15/2022
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Miscellaneous
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
9/12/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
9/12/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
9/12/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
9/15/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
9/9/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
8/5/2022
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Title:
|
| | |
APPROVAL
|
|
Wording
|
| | |
THIS APPROVAL IS FOR A MODIFICATION TO AN EXISTING CELL TOWER INLCUDING: SMARTSKY INSTALL NEW MICROWAVE DISH; INSTALL (1) COMMSCOPE - l-IP8-107-D4M MW DISH; INSTALL (1) POWER CABLE (1/4"), INSTALL (1) POER CABLE (3/8") ; INSTALL (1) 2-1/2" SCH 40 (2-7/8" 0.0.) BY 8'-0" LONG GALV. PIPE W CROSSOVER HARDWARE; INSTALL (1) SITE PRO 1 - RS PIPE TO PIPE MOUNT. NO GROUND WORK TO AN EXISTING CELL TOWER. ANY FUTURE PERMITS ON SITE ARE SUBJECT TO REVIEW FOR CONSISTENCY WITH APPLICABLE CODES AND ORDINANCES AND DOES NOT PRECLUDE REVIEW AND CONDITIONS WHICH MAY BE PLACED ON FURTURE PERMITS.
|
|
|
Title:
|
| | |
SITE PLAN CHANGES
|
|
Wording
|
| | |
The site plan as submitted with the modification to existing cell tower application on JULY 27 2022 by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the revised stamped, approved site plan dated SEPTEMBER 12, 2022 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
BMPS
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
SEPA EXEMPT
|
|
Wording
|
| | |
The proposal is SEPA Exempt under WAC197-11-800(25)(a)(i).
|
|
|
Title:
|
| | |
EXEMPT
|
|
Wording
|
| | |
The proposal meets JCC18.42.020 (2) (d) which exempts the following from the provisions of the Chapter 18.42 JCC. Emergency or routine repairs, reconstruction, or routine maintenance of previously approved facilities, or replacement of transmitters, antennas, or other components of previously approved facilities which do not create a change in visual impact.
|
|
|
Title:
|
| | |
COLOCATION
|
|
Wording
|
| | |
JCC 18.42.080 identifies the following as a permitted outright use: Attached or collocated wireless communications facilities on existing structures in designated forest lands and all commercial and industrial districts.
|
|
|
Title:
|
| | |
NOISE LEVELS
|
|
Wording
|
| | |
The installed permitted equipment will be compliant with Jefferson County Code 18.42.090 (g). SMARTSKY NETWORKS will be responsible for not exceeding the maximum environmental noise levels set forth in WAC Chapter 173-60.
|
|
|
Title:
|
| | |
NOISE 2
|
|
Wording
|
| | |
oise generated by the wireless telecommunication facility shall not exceed the maximum environmental noise levels established in Chapter 173-60, Washington Administrative Code, as it is now in effect or in effect or hereafter amended. All noise emitting equipment that cannot in any way operate below the maximum permitted noise level shall be housed in a sound-attenuating structure, unless otherwise stipulated in the project approval. The applicant may be required to submit sound attenuation plans for review and approval by the department.
|
|