Description:
|
| | |
Inspection Reminder Sent (2nd)
|
|
Date Completed:
|
| | |
12/15/2021
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Inspection Reminder Sent (1st)
|
|
Date Completed:
|
| | |
9/3/2021
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
7/2/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Foundation Footing
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
6/23/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
DRD Approval (Zoning)
|
|
Date Completed:
|
| | |
7/1/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Address Review Complete
|
|
Date Completed:
|
| | |
6/23/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
7/1/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
7/1/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
7/1/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
6/23/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
6/30/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
6/23/2020
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
6/23/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
C-APPROVAL FOR NEW GENERATOR ONLY
|
|
Wording
|
| | |
This approval is for a new generator addition only to an existing cell tower. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
C-SITE PLAN CHANGES
|
|
Wording
|
| | |
The site plan as submitted with the modification to existing cell tower application on June 22, 2020 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the revised stamped, approved site plan dated July 1, 2020 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
C-BMPS
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
C-WIRELESS EXEMPTION
|
|
Wording
|
| | |
The proposal meets JCC18.42.020(2)(d) which exempts the following from the provisions of the Chapter 18.42 JCC. Emergency or routine repairs, reconstruction, or routine maintenance of previously approved facilities, or replacement of transmitters, antennas, or other components of previously approved facilities which do not create a change in visual impact.
|
|
|
Title:
|
| | |
C-COLOCATION
|
|
Wording
|
| | |
JCC 18.42.080 identifies the following as a permitted outright use: Attached or collocated wireless communications facilities on existing structures in designated forest lands and all commercial and industrial districts.
|
|
|
Title:
|
| | |
C-NOISE COMPLIANT
|
|
Wording
|
| | |
The installed permitted equipment will be compliant with Jefferson County Code 18.42.090 (g). AT&T will be responsible for not exceeding the maximum environmental noise levels set forth in WAC Chapter 173-60.
|
|
|
Title:
|
| | |
C-SEPA EXEMPT
|
|
Wording
|
| | |
This proposal is SEPA exempt under WAC 197-11-800(25)(a)(i).
|
|
|
Title:
|
| | |
C-NOISE EMITTING MACHINERY
|
|
Wording
|
| | |
All noise emitting machinery that cannot in any other way operate below the maximum permitted noise level shall be housed in a sound-attenuating structure.
|
|
|
Title:
|
| | |
C-NOISE
|
|
Wording
|
| | |
Noise generated by the wireless telecommunication facility shall not exceed the maximum environmental noise levels established in Chapter 173-60, Washington Administrative Code, as it is now in effect or in effect or hereafter amended. All noise emitting equipment that cannot in any way operate below the maximum permitted noise level shall be housed in a sound-attenuating structure, unless otherwise stipulated in the project approval. The applicant may be required to submit sound attenuation plans for review and approval by the department.
|
|
|
Title:
|
| | |
C-NOISE STUDY
|
|
Wording
|
| | |
An Acoustical Report was submitted by SSA Acoustics dated March 24, 2020 stating the emergency diesel generator will run once a week during daytime hours for maintenance and testing and will comply with the State of Washington Administrative Code (WAC) Chapter 173-60.
|
|