Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
11/7/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - FINAL FINAL Building
|
|
Date Completed:
|
| | |
10/15/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Inspection Reminder Sent (2nd)
|
|
Date Completed:
|
| | |
10/11/2019
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Inspection Reminder Sent (1st)
|
|
Date Completed:
|
| | |
8/18/2019
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Issue Revised Bldg Pmt (F)
|
|
Date Completed:
|
| | |
6/3/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
5/22/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
5/13/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Initiate Revision
|
|
Date Completed:
|
| | |
5/13/2019
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
5/10/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
5/6/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
9/14/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
9/14/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Miscellaneous
|
|
Date Completed:
|
| | |
9/19/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Final Planning Approval
|
|
Date Completed:
|
| | |
9/19/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
A Clock Interrupt
|
|
Date Completed:
|
| | |
9/11/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-DRD
|
|
Date Completed:
|
| | |
9/10/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Invoice for DCD Sent
|
|
Date Completed:
|
| | |
9/5/2018
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
DRD Reviewer Letter (F)
|
|
Date Completed:
|
| | |
8/6/2018
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Miscellaneous
|
|
Date Completed:
|
| | |
10/11/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
5/7/2018
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
5/7/2018
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Framing
|
|
Date Completed:
|
| | |
10/11/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
10/11/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Miscellaneous
|
|
Date Completed:
|
| | |
10/11/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
1/22/2018
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Additional Info Request-DRD
|
|
Date Completed:
|
| | |
8/6/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
A Clock Interrupt
|
|
Date Completed:
|
| | |
8/6/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-BLD
|
|
Date Completed:
|
| | |
1/22/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
5/10/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
9/5/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
9/5/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
5/9/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
1/22/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
5/9/2017
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
5/9/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
REDUCE UPPER DECK
|
|
Wording
|
| | |
The proponent shall reduce the width of the upper deck from 8 feet to a 5-foot walkway as proposed.
|
|
|
Title:
|
| | |
GEOLOGY HAZARD ASSESSMENT
|
|
Wording
|
| | |
A Geology Hazard Assessment and Update prepared by Stratum Group and dated July 8, 2009 and April 26, 2017 was submitted in conjunction with the permit application. The proposal shall comply with the recommendations made in the Geologic Hazard Assessment and update.
|
|
|
Title:
|
| | |
FENCE DEMO
|
|
Wording
|
| | |
The portion of the fence proposed for removal on the approved site plan shall be demolished prior to receiving a building final certificate of occupancy for stairs construction BLD17-00203.
|
|
|
Title:
|
| | |
NO NET LOSS AND MITIGATION PLAN
|
|
Wording
|
| | |
The applicant shall implement the Final Addendum to No Net Loss and Mitigation plan, dated May 3, 2018, except that (1) four additional shrubs from the list shall be installed five feet on center in the area exposed by the narrowed stair platform; (2) The six Leyland cypress trees installed adjacent to the fence shall be removed and replaced with ten native trees installed ten feet on center; and (3) the invasive weed, yellow archangel Lamaiastrum galeobdolon, located at the inner corner between the pathway and the stairs cut into the slope, shall be removed and replaced with one native shrub.
|
|
|
Title:
|
| | |
MONITORING
|
|
Wording
|
| | |
An annual monitoring report shall be prepared in the summer and submitted to DCD prior to October 31st for five years following issuance of building final certificate of occupancy. The monitoring report shall ensure the mitigation complies with the following performance standards: 1) Year One: Survival of 100% of the installed plants, 2) Year two: Survival of at least 90% of the installed plants, 3) Years 3-5: Survival of at least 80% of the installed plants, and 4) At no point during five year monitoring shall nonnative plants encroach more than 5% into the mitigation areas.
|
|
|
Title:
|
| | |
MITIGATION AREAS
|
|
Wording
|
| | |
DCD shall review and approve the mitigation areas prior to building final. Contact the planning department (Emma Bolin, 360-379-4484) or the staff biologist (Donna Frostholm, 360-379-4466) to schedule a site visit. A BUILDING FINAL CERTIFICATE OF OCCUPANCY SHALL NOT BE ISSUED UNTIL DCD HAS REVIEWED AND APPROVED THE MITIGATION AREA FOR COMPLIANCE WITH THE APPROVED MITIGATION PLAN AND ALL PERMIT CONDITIONS.
|
|
|
Title:
|
| | |
SHORELINE EXEMPTION
|
|
Wording
|
| | |
This project was reviewed and approved as a Shoreline Exemption under JCC 18.25.560(1) and (8).
|
|
|
Title:
|
| | |
ESAS
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County Department of Community Development staff for the potential presence of Critical Areas under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following Critical Areas were confirmed to be present on the subject property: nearshore marine Fish and Wildlife Habitat Conservation Area, unstable recent slide slope stability, eagle habitat/nest buffer, slight landslide hazard area, susceptible aquifer recharge area, coastal seawater intrusion protection zone.
|
|
|
Title:
|
| | |
NO NET LOSS REPORT
|
|
Wording
|
| | |
A No Net Loss Report was submitted dated April 2017 with an Addendum submitted dated November 2017 by Olympic Wetland Resources LLC in conjunction with this application. A final addendum was submitted dated May 3, 2018. The addendum includes impacts analysis and mitigation for a new approximately 44’ x 3’ cut trail, vegetation removed for new trail steps cut into the slope leading to the stairway, privacy fence removal (100 ft) and retained area (50 ft), vegetation alteration for the lower stairs platform, impacts of the posts and pier from the original mitigation, impacts from lower stair removal, and impacts from new elevated platform with 9 posts.
|
|
|
Title:
|
| | |
SEPA
|
|
Wording
|
| | |
Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(1)(b)(i).
|
|
|
Title:
|
| | |
SITE PLAN
|
|
Wording
|
| | |
The revised site plan as submitted with the permit application on April 29, 2019 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved revised site plan dated May 22, 2019 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
APPROVAL FOR
|
|
Wording
|
| | |
This approval is for an after the fact permit for a beach access structure with a walkway platform reduced to a width of no more than 5 feet wide and a reconfigured lower stairway to the beach only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
CONDITIONAL USE PERMITS
|
|
Wording
|
| | |
The building permit has been reviewed in association with the Shoreline Conditional Use Permits approved under MLA17-00037/SDP17-00008 and shall be in compliance with the permit conditions under this shoreline permit.
|
|
|
Title:
|
| | |
STORMWATER
|
|
Wording
|
| | |
The applicant is proposing to create or add 188 square feet of impervious surface and 188 square feet of land disturbing activities. JCC 18.30.060 and 18.30.070 require your proposal comply with Minimum Requirement #2 (Construction Stormwater Pollution Prevention) of the Department of Ecology Stormwater Management Manual for Western Washington to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
Do Not Disturb Buffer
|
|
Wording
|
| | |
All construction activities shall encroach upon the 150 foot shoreline and fish and wildlife habitat conservation area buffer to the minimum extent practcal. This includes the storage or preparation of materials.
|
|
|
Title:
|
| | |
Aquifer Recharge Conditions (SFR)
|
|
Wording
|
| | |
Critical Aquifer Recharge Areas may require special protection measures to mitigate water quality degradation. The submitted proposal does not require additional aquifer protection measures. However, during construction the project shall follow the Best Management Practices (BMPs) and facility design standards as identified and defined in the Stormwater Management Manual for the Puget Sound Basin.
|
|
|
Title:
|
| | |
Seawater Intrusion Areas
|
|
Wording
|
| | |
To help prevent seawater from intruding landward into underground aquifers, all new development activity on Marrowstone Island, Indian Island and within 1/4 mile of any marine shoreline shall be required to infiltrate all stormwater runoff onsite.
|
|
|
Title:
|
| | |
Coastal & At Risk SIPZ-Water Con
|
|
Wording
|
| | |
VOLUNTARY MEASURES OF COASTAL & AT RISK SIPZ:
Water conservation measures:
1. Roof and other intercepted precipitation shall be routed to on-site detention ponds and/or other approved means and allowed to be released to the soil slowly.
2. Water collected from Storm water and roof catchments may be used for watering lawns and gardens. Unless catchment water has been treated to meet drinking water standards, there shall be no cross connections allowed between the potable supply and impounded water.
3. Water withdrawn from wells on each property shall not be used for watering of lawns and/or gardens.
4. Ground water withdrawn from each property shall be restricted to a rate of three (3) gallons per minute.
5. Installation of water conserving fixtures such as low flow toilets, faucets and shower restrictors and other water saving plumbing fixtures.
6. Landscaping plan (xeriscaping, native vegetation with minimal amounts of irrigation).
Please NOTE that the above listed measures are not intended to be exhaustive, but rather is intended to be illustrative of the types of water conservation measures.
|
|
|
Title:
|
| | |
Coastal & At Risk SIPZ-Measures
|
|
Wording
|
| | |
VOLUNTARY MEASURES OF COASTAL & AT RISK SIPZ:
1. Installation of a flow meter.
2. On-going well monitoring for chloride concentration.
3. Submittal of monitoring data to County.
|
|
|
Title:
|
| | |
Coastal SIPZ-Mand Potable Water
|
|
Wording
|
| | |
MANDATORY MEASURES FOR COASTAL SIPZ:
1. For proof of potable water on a building permit application, applicant must utilize DOH-approved public water system if available.
2. If public water is unavailable, an individual well may be used as proof of potable water subject to the following requirement:
a. Chloride concentration of a laboratory-certified well water sample submitted with building permit application.
b. Installation of source-totalizing meter (flow).
3. If public water is unavailable, a qualifying alternative system may be used as proof of potable water.
|
|
|
Title:
|
| | |
BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
C-Small Stormwater
|
|
Wording
|
| | |
The project shall comply with Construction Stormwater Pollution Prevention (SWPP) Elements #1 through #12 of the Department of Ecology's Stormwater Management Manual for Western Washington to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|