Permit Case Summary

Case Number: Search Help

Case Number:BLD2008-00517 Case Status:Finaled Date Received:12/24/2008
Description:TEMPORARY BUS SHELTER @ SHINE PIT PARK & RIDE Date Issued:1/21/2009
Applicant: POPE RESOURCES Expiration Date:1/21/2010 12:00:00 AM
Site Address:1072 ROCKTOGO RD Case Finaled:4/30/2009
Parcel No:821312001 Other Cases Parcel Data Map It More Details

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: File Archived
Date Completed: 3/3/2010
Disposition: DONE
Description: Insp - FINAL FINAL Building
Date Completed: 4/29/2009
Disposition: DONE
Description: Insp - Framing
Date Completed: 4/29/2009
Disposition: DONE
Description: Issue Building Permit (F)
Date Completed: 1/21/2009
Disposition: DONE
Description: Approve Permit-UF
Date Completed: 1/14/2009
Disposition: DONE
Description: Review Complete-U
Date Completed: 1/14/2009
Disposition: DONE
Description: Insp - Final Building
Date Completed: 4/29/2009
Disposition: DONE
Description: Insp - Erosion Control
Date Completed: 4/29/2009
Disposition: DONE
Description: Insp - Setbacks
Date Completed: 4/29/2009
Disposition: DONE
Description: Building Permit Application(F)
Date Completed: 12/29/2008
Disposition: DONE
Description: App Substantially Complete-U
Date Completed: 1/5/2009
Disposition: DONE
Description: Case Entered
Date Completed: 12/29/2008
Disposition:
Description: Plan Check
Date Completed: 1/6/2009
Disposition: DONE
Description: Septic Review Complete-U
Date Completed: 1/14/2009
Disposition: DONE
Description: Potable Water Approval
Date Completed: 12/29/2008
Disposition: DONE
Description: Contractor License/Bond Info
Date Completed: 12/29/2008
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 1/5/2009
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 1/5/2009
Disposition: DONE
Description: Consistency Review-U
Date Completed: 1/14/2009
Disposition: DONE
Description: RAP Review Complete-U
Date Completed: 12/29/2008
Disposition: DONE
Description: Final Planning Approval
Date Completed:
Disposition:
Description: Final Public Works Approval
Date Completed:
Disposition:
Description: DRD Approval (Zoning)
Date Completed: 1/14/2009
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: SEPTIC CONDITION
Wording THIS APPROVAL IS ONLY FOR THE TEMPORARY USE OF SANI CANS AT THIS SITE. NO PERMINANT PLUMBING FIXTURES HAVE BEEN REVIEWED OR APPROVED FOR THIS PROJECT BY JEFFERSON COUNTY PUBLIC HEALTH. ADDITIONAL REQUIREMENTS WILL APPLY IF PERMINANT PLUMBING IS PROPOSED.

Title: Unlicensed/Inoperable Vehicles
Wording Not more than 2 unlicensed vehicles shall be stored on any lot unless totally screened from view of neighboring dwellings and rights-of-way. Such screening shall meet all applicable performance and development standards specific to the district in which the storage is kept, and shall be in keeping with the character of the area. Screening shall meet the requirements of Chapter 18.30 JCC. Outdoor storage of 3 or more junk motor vehicles is prohibited except in those districts where specified as an automobile wrecking yard or junk (or salvage) yard and allowed as a permitted use in Table 3-1 or Chapter 18.18 JCC, and such storage shall meet the requirements of JCC 18.20.100, Automobile wrecking yards and junk (or salvage) yards. In no case, shall any such junk motor vehicles be stored in a critical area.

Title: STORMWATER PLAN
Wording A Stormwater Drainage Report dated September 7, 2007 prepared by Team4 Engineering has been submitted and approved under ZON07-00078 by the Department of Community Development. Final inspection and approval of the stormwater plan will be required by the Department of Public Works prior to final building approval.

Title: 150% Wetland Setback
Wording The project is located in close proximity to an identified wetland and is subject to the delineation provisions of Section 18.15.340 of the Jefferson County Code. Based upon the proposed location of the project in relation to the identified wetland, the applicant has agreed to maintain a buffer (setback) that exceeds the standard buffer requirements by fifty (50) percent. The applicant acknowledges the additional setback and agrees to maintain the extra 50 percent buffer, therefore, waiving the wetland delineation requirements of the Jefferson County Code.

Title: BMPs
Wording The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.

Title: C-Small Stormwater
Wording The project shall comply with Construction Stormwater Pollution Prevention (SWPP) Elements #1 through #12 of the Department of Ecology's Stormwater Management Manual for Western Washington to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-ZON07-00078
Wording Zoning approval was issued March 5, 2008 under ZON07-00078 for the park & ride parking area in conjuntion with this temporary building permit.

Title: F-Confirmed ESAs
Wording The application was reviewed by the Jefferson County Department of Community Development staff on September 24, 2007 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Jefferson County Code (JCC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: Osprey; Stream; Wetland; Rare Plants; Seismic; Landslide hazard area 1 & 2; SUSC aquifer recharge area. (West Shine Creek is about .75 miles NE and about 200 feet lower thatn the proposed park and ride. Pheasant Lake is about .25 miles south of the Shine Pit mining boundary. Thorndyke Creek is about 1.2 miles west of the proposed park and ride).

Title: F-Aquifer Recharge Area
Wording Aquifer Recharge Areas in Jefferson County are characterized by porous geological formations that allow percolation of the surface water into the soils and the underlying zone of saturation. Aquifers are geologic formations that contain sufficient saturated permeable material to yield significant quantities of water to wells and springs. Aquifers serve as the source of drinking water within most of the rural portions of Jefferson County.

Title: F-Susc. Aquifer Recharge Area
Wording Susceptible Aquifer Recharge Areas are those with geologic and hydrologic conditions that promote rapid infiltration of recharge waters to groundwater aquifers.

Title: F-Geohazard Area
Wording Geologically Hazardous Areas in Jefferson County are characterized by slope, soil type, geologic material, and groundwater that may combine to create problems with slope stability, erosion, and water quality during and after construction or during natural events such as earthquakes or severe rainstorms.

Title: F-Streams
Wording A Type 1 & 2 Stream (Fish and Wildlife Habitat Area) has been identified on the subject property. The Type 1 & 2 streams will require a setback of 150-feet. The setback shall be measured horizontally from the Ordinary High Water Mark (OHWM). Fish and Wildlife Habitat Areas shall also have Buffers and Building Setbacks established.

Title: F-Buffers
Wording Stream, wetland and landslide hazard area buffers are areas that shall be maintained in their natural condition, however, minor pruning or alteration of vegetation may be permitted as long as the function and character of the buffer are not diminished.

Title: F-Native Vegetation List
Wording Among the native conifer species which may be used in buffers or for re-vegetation include, but are not limited to: Grand Fir (Aibes grandis), Sitka Spruce (Picea sitchensis), Shore Pine (Pinus contorta), Douglas Fir (Pseudotsuga menziesii), Western Red Cedar (Thuja plicata), and Western Hemlock (Tsuga heterophylla). Among native tree species which may be used includes: Vine Maple (Acer circinatum), Big-Leaf Maple (Acer macrophyllum), Red Alder (Alnus rubra), Pacific Madrone (Arbutus menziesii), Quaking Aspen (Populus tremula), Black Cottonwood (Populus trichocarpa), Bitter Cherry (Prunus emarginata), Oregon White Oak (Quercus garryana), Cascara (Rhamnus purshiana), Pacific Willow (Salix lasiandra), and Scouler's Willow (Salix scouleriana). Among the native shrub species which may be used are: Sevice-Berry (Amalanchier alnifolia), Red Osier Dogwood (Cornus stolonifera) Salal (Gaultheria shallon), Ocean Spray (Holodiscus discolor), Indian Plum (Oemlaria cerasiformis), Pacific Ninebark (Physocarpus capitus), Red Flowering Currant (Ribes sanguineum), Wild Rose (Rosa nutkana), Swamp Rose (Rosa pisocarpa), Willows (Salix ssp.), Red Elderberry (Sambucus racemosa), Snowberry (Symphoricarpos albus), Evergreen Huckleberry (Vaccinium ovatum), Red Huckleberry (Vaccinium parvifolium).

Title: F-Wetland Delineation Waiver
Wording The project components are more than 250' from the mapped/identified wetland. The requirement for a wetland delineation and report is waived based on maintenance of a 225 foot buffer from the wetland per JCC Table 3-3.

Title: F-Small Stormwater
Wording The applicant is proposing to create or add 540 square feet of impervious surface and zero square feet of land disturbing activities. JCC 18.30.060 and 18.30.070 require your proposal comply with Minimum Requirement #2 (Construction Stormwater Pollution Prevention) of the Department of Ecology Stormwater Management Manual for Western Washington to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.

Title: F-DNS Issued
Wording Reviewed under the State Environmental Policy Act (SEPA) by Jefferson County acting as lead agency under ZON07-00078. A Determination of Non-Significance (DNS) was issued on March 5, 2008.

Title: F-Site Plan Changes
Wording The site plan as submitted with the building permit application on December 24, 2008 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated January 14, 2009 shall be resubmitted for review and approval by Jefferson County Department of Community Development.

Title: F-Approval for _____ Only
Wording This approval is for a 540 square foot temporary canopy structure only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.