Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
3/3/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - FINAL FINAL Building
|
|
Date Completed:
|
| | |
4/29/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Framing
|
|
Date Completed:
|
| | |
4/29/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
3/9/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Permit-UF
|
|
Date Completed:
|
| | |
3/5/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Review Complete-U
|
|
Date Completed:
|
| | |
3/5/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
4/29/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Setbacks
|
|
Date Completed:
|
| | |
4/29/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
12/29/2008
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
1/5/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
12/29/2008
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
1/6/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
3/5/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Potable Water Approval
|
|
Date Completed:
|
| | |
12/29/2008
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
12/29/2008
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
1/5/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
1/5/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
3/5/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
12/29/2008
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Final Public Works Approval
|
|
Date Completed:
|
| | |
1/5/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
DRD Approval (Zoning)
|
|
Date Completed:
|
| | |
1/5/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
Unlicensed/Inoperable Vehicles
|
|
Wording
|
| | |
Not more than 2 unlicensed vehicles shall be stored on any lot unless totally screened from view of neighboring dwellings and rights-of-way. Such screening shall meet all applicable performance and development standards specific to the district in which the storage is kept, and shall be in keeping with the character of the area. Screening shall meet the requirements of Chapter 18.30 JCC. Outdoor storage of 3 or more junk motor vehicles is prohibited except in those districts where specified as an automobile wrecking yard or junk (or salvage) yard and allowed as a permitted use in Table 3-1 or Chapter 18.18 JCC, and such storage shall meet the requirements of JCC 18.20.100, Automobile wrecking yards and junk (or salvage) yards. In no case, shall any such junk motor vehicles be stored in a critical area.
|
|
|
Title:
|
| | |
SETBACKS
|
|
Wording
|
| | |
Shoreline building setback is 30 feet from OHWM. Frontyard set back is 20 feet, side yard setback is 5 feet.
|
|
|
Title:
|
| | |
BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
Stormwater Plan
|
|
Wording
|
| | |
A CSWPPP Plan has been submitted and approved by the Department of Community Development. Once the subject permit has been issued the applicant shall fully implement the provisions of the submitted plan and contact the Jefferson County Department of Community Development to arrange a schedule to inspect the property for plan compliance. A Certificate of Occupancy will not be issued until the Department verifies plan compliance. No clearing for roadways or utilities shall occur on the project site until clearing necessary for the installation of temporary sedimentation and erosion control measures have been completed.
|
|
|
Title:
|
| | |
C-Small Stormwater
|
|
Wording
|
| | |
The project shall comply with Construction Stormwater Pollution Prevention (SWPP) Elements #1 through #12 of the Department of Ecology's Stormwater Management Manual for Western Washington to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
F-SDP02-00039
|
|
Wording
|
| | |
A shoreline exempton permit (SDP02-00039) has been approved in conjunction with this temporary building permit.
|
|
|
Title:
|
| | |
F-Confirmed ESAs
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County Department of Community Development staff on January 5, 2009 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: Suburban shoreline designation; Wetlands; Seismic zone; Flood Zone; Susceptible Aquifer Recharge Area; High Risk SIPZ.
|
|
|
Title:
|
| | |
F-Aquifer Recharge Area
|
|
Wording
|
| | |
Aquifer Recharge Areas in Jefferson County are characterized by porous geological formations that allow percolation of the surface water into the soils and the underlying zone of saturation. Aquifers are geologic formations that contain sufficient saturated permeable material to yield significant quantities of water to wells and springs. Aquifers serve as the source of drinking water within most of the rural portions of Jefferson County.
|
|
|
Title:
|
| | |
F-Geohazard Area
|
|
Wording
|
| | |
Geologically Hazardous Areas in Jefferson County are characterized by slope, soil type, geologic material, and groundwater that may combine to create problems with slope stability, erosion, and water quality during and after construction or during natural events such as earthquakes or severe rainstorms.
|
|
|
Title:
|
| | |
F-High Risk SIPZ
|
|
Wording
|
| | |
The parcel is located within a High Risk SIPZ (seawater intrusion protection zone) according to the County GIS map. There are mandatory measures identified in the Jefferson County Seawater Intrusion Policy (Resolution 44-22, effective September 23, 2002) that apply to well drilling proposals and building permit applications on existing lots of record.
A High Risk SIPZ is defined as: areas within 1,000 feet of a groundwater source with a history of chloride analyses above 200 milligrams per liter (mg/L).
|
|
|
Title:
|
| | |
F-Small Stormwater
|
|
Wording
|
| | |
The applicant is proposing to create or add 540 square feet of impervious surface and zero square feet of land disturbing activities. JCC 18.30.060 and 18.30.070 require your proposal comply with Minimum Requirement #2 (Construction Stormwater Pollution Prevention) of the Department of Ecology Stormwater Management Manual for Western Washington to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
F-SEPA Exempt
|
|
Wording
|
| | |
Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(1)(b).
|
|
|
Title:
|
| | |
F-Site Plan Changes
|
|
Wording
|
| | |
The site plan as submitted with the Building Permit application on December 24, 2008 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated March 5, 2009 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
F-Approval for _____ Only
|
|
Wording
|
| | |
This approval is for a 540 square foot temporary canopy structure with sanican facilities only, thru approximately June 15, 2009. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
NO PLUMBING REV.OR APPVD
|
|
Wording
|
| | |
No plumbing has been reviewed or approved for this project by Jefferson County Public Health. Additional requirements may apply if plumbing is proposed. Septic for temporary facilities only, no employees or clients onsite for more than 2 hours.
|
|