Description:
|
| | |
Final Plumbing/BLD Inspection
|
|
Date Completed:
|
| | |
11/14/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
10/21/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Review Complete-U
|
|
Date Completed:
|
| | |
8/29/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Permit-UF
|
|
Date Completed:
|
| | |
8/29/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
4/1/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Application Received-UF
|
|
Date Completed:
|
| | |
3/12/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
3/12/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
3/11/2002
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
3/18/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
8/29/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
4/1/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
4/1/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
4/1/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
3/11/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Final Planning Appr
|
|
Date Completed:
|
| | |
8/29/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
DRD Approval (Zoning)
|
|
Date Completed:
|
| | |
4/1/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
3/11/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
TF-Noise
|
|
Wording
|
| | |
Noise generated by the wireless telecommunication facility shall not exceed the maximum environmental noise levels established in Chapter 173-60, Washington Administrative Code, as it is now in effect or in effect or hereafter amended. In the event the applicant adds an emergency generator in the future, the applicant shall notify Jefferson County and provide noise generation data for the installed generator. All noise emitting equipment that cannot in any way operate below the maximum permitted noise level shall be housed in a sound-attenuating structure, unless otherwise stipulated in the project approval. The applicant may be required to submit sound attenuation plans for review and approval by the department.
|
|
|
Title:
|
| | |
TF-Maintenance
|
|
Wording
|
| | |
The applicant shall protect the facility from unauthorized access consistent with the purpose of protecting the public health, safety and welfare. The applicant shall maintain the facility in a good and safe condition and preserve its original appearance and concealment or camouflage elements incorporated into the design at the time of approval. Maintenance shall include, but not be limited to, such items as painting, structural repair, repair of equipment and maintenance of landscaping.
|
|
|
Title:
|
| | |
TF-Building Permit
|
|
Wording
|
| | |
The type "A" land use permit for this facility shall automatically expire and become void if the applicant fails to obtain a building permit within one year of the effective date of the land use permit. The Director may extend the permit for a period of one year, provided that the applicant files a written request for extension not less than 60 days prior to the expiration that specifies good cause for the extension.
|
|
|
Title:
|
| | |
TF-Expenses
|
|
Wording
|
| | |
The applicant shall be responsible for all direct and indirect expenses incurred related to review and compliance with conditions of approval. All fees shall be as authorized by County Ordinance.
|
|
|
Title:
|
| | |
TF-Emergency Response
|
|
Wording
|
| | |
Prior to operation of the telecommunication facilities, the applicant shall document that the system has been integrated into the County's Emergency Response System as required by Section 18.42.050. The applicant shall officially certify that they have the capacity to meet FCC mandate that all the industry must be able to locate a wireless telephone when it dials 911.
|
|
|
Title:
|
| | |
TF-Other Requirements
|
|
Wording
|
| | |
Construction of the wireless telecommunication facilities is subject to the requirements of the County Building Code, Chapter 15.05 JCC, and all Building Code (UBC), the Electrical Code (NEC), the requirements of the National Electronics Industries Association/Telecommunications Industries Association (EIA/TIA) 222 Revision F Standard entitled "Structural Standards for Steel Antenna Supporting Structures" and any additional applicable standards published by the Electronics Industries Association, the Uniform Fire Code and the Jefferson County Critical Areas Ordinance.
|
|
|
Title:
|
| | |
BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
F-No ESAs Found
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County Department of Community Development for the presence of Environmentally Sensitive Areas (ESAs). The Department conducted a review and has concluded that the existing tower location lease property DOES NOT contain Environmentally Sensitive Areas. However, future proposals will be subject to a new ESA review and conditions may be added if new ESAs are found on the property.
|
|
|
Title:
|
| | |
F-Stormwater
|
|
Wording
|
| | |
The applicant is proposing to create or add 150 square feet of impervious surface and 200 square feet of land disturbing activities. Sections 6.6 and 6.7 of the Jefferson County Unified Development Code requires that your proposal submit a Stormwater Calculation Sheet. The applicant submitted a SCS.
|
|
|
Title:
|
| | |
F-SEPA Exempt
|
|
Wording
|
| | |
Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(1)(b)(i).
|
|
|
Title:
|
| | |
F-APPROVAL FOR CO-LOCATE ONLY
|
|
Wording
|
| | |
This approval is for a Cingular Wireless COLOCATED WIRELESS TELECOMMUNICATION ANTENNA only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
F-TOWER SPECIFIC FINDING
|
|
Wording
|
| | |
Jefferson County SEPA Responsible Official issued a Determination of Non-Significance August 31, 1999 for the Voice Stream tower that the colocated antennas are being placed on for Cingular Wireless.
|
|
|
Title:
|
| | |
F-EXISTING TOWER SPECIFIC FINDING
|
|
Wording
|
| | |
A building permit application (BLD99-00351) was issued by Jefferson County for construction of a 195 foot lattice tower for wireless communications that included 2 dish antennas and up to 9 panel antennas. The permit was issued September 9, 1999 and finaled November 12, 1999.
|
|
|
Title:
|
| | |
F- ZONING STATUS
|
|
Wording
|
| | |
The parcel is a legal conforming lot that is designated as Commercial Forest (CF-80) under the Jefferson County Comprehensive Plan Land Use Map effective August 28, 1998.
|
|