Description:
|
| | |
Final Inspection
|
|
Date Completed:
|
| | |
7/26/2000
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
FINAL sign-off
|
|
Date Completed:
|
| | |
7/26/2000
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RENEWAL NOTICE Sent (F)
|
|
Date Completed:
|
| | |
6/20/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Final Planning Appr
|
|
Date Completed:
|
| | |
6/8/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RENEWAL NOTICE Sent (F)
|
|
Date Completed:
|
| | |
6/7/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
6/5/2000
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Stormwater Review
|
|
Date Completed:
|
| | |
3/30/2000
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
DRD Approval (Zoning)
|
|
Date Completed:
|
| | |
10/27/1999
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
10/7/1999
|
|
Disposition:
|
| | |
P
|
|
|
Description:
|
| | |
Critical Area Review
|
|
Date Completed:
|
| | |
10/27/1999
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
6/24/1999
|
|
Disposition:
|
| | |
|
|
|
Title:
|
| | |
STORM WATER MANAGEMENT
|
|
Wording
|
| | |
The Stormwater Management Ordinance requires proponents of development that include construction of less than 5,000 square feet of impervious surface to implement a Small Parcel Erosion and Sediment Control Plan that applies the Small Parcel Minimum Requirements from the Washington Department of Ecology Stormwater Management Manual for the Puget Sound Basin. A Small Parcel Erosion and Sediment Control Plan that meets these requirements shall be submitted to the Jefferson County Department of Public Works for review and approval prior to commencing any land disturbing activty.
|
|
|
Title:
|
| | |
COSTS INCIDENTIAL TO REVIEW
|
|
Wording
|
| | |
In accordance with the Jefferson County Department of Public Works Fee Schedule, the applicant shall pay all costs of work incidential to review of the project before final approval in granted. The Department's review fee is currently $49.00 per hour.
|
|
|
Title:
|
| | |
LIGHTING CONDITION
|
|
Wording
|
| | |
The intensity or brightness of all lighting, during construction and after project completion shall not adversely affect the use of surrounding properties or adjoining rights-of-way.
|
|
|
Title:
|
| | |
EXTERIOR LIGHTING CONDITION
|
|
Wording
|
| | |
Exterior flashing, moving, or blinking lighting is prohibited, except as required by local, state, or federal standards.
|
|
|
Title:
|
| | |
NOISE CONDITION
|
|
Wording
|
| | |
The intensity emitted by any commericial activity shall not exceed levels established by the Washington State Department of Ecology under Chapter 173-60 WAC, and by Jefferson County under Resolution No. 67-85, "Establishment of Environmental Designations for Noise Abatement Areas of Jefferson County."
|
|