Cases Associated with Parcel No: 901023006

This may not be a complete listing of information that exists for this parcel. There may be other information pertinent to the property on file. Please contact the Department of Community Development for additional information.



Case Number  SDP2022-00014
Description  Construction of a wastewater facility serving the Port Hadlock/Irondale Urban Growth Area (UGA). Project elements include construction of a pressure sewer system for wastewater collection, installation of two modular membrane bioreactor (MBR) wastewater treatment units for a treatment facility using ultraviolet (UV) disinfection and producing Class A reclaimed water for land application & groundwater recharge via a percolation pond, and solids and/or decanted solids staged on-site before hauling for off-site handling. The Phase 1 facility startup design is 0.090 million gallons per day (MGD) of treatment capacity serving the initial project service area (estimated in 2024). Construction duration is anticipated to be about 24 months. The wastewater facility will occupy approximately 3 acres of a 25.6-acre site owned by Jefferson County. The system design is approved by Washington Department of Ecology to meet regulatory requirements and population growth in the UGA through 2041. The initial Phase 1 service area is the Port Hadlock Commercial Core Area along State Route 116 and Chimacum Rd. The Department of Community Development (DCD) is reviewing the permit in accordance with Chapter 18.18 JCC, beginning as a conditional discretionary (C(d)) permit approval process. DCD anticipates final approval of the project under an administrative conditional use permit (C(a)). The project has undergone review under the State Environmental Policy Act (SEPA). DCD is using the Optional DNS Process outlined in WAC 197-11-355.
Last Name  REINDERS
Received Date  5/23/2022 10:42:11 AM
Status  Approved
  

Case Number  ZON2022-00018
Description  Construction of a wastewater facility serving the Port Hadlock/Irondale Urban Growth Area (UGA). Project elements include construction of a pressure sewer system for wastewater collection, installation of two modular membrane bioreactor (MBR) wastewater treatment units for a treatment facility using ultraviolet (UV) disinfection and producing Class A reclaimed water for land application & groundwater recharge via a percolation pond, and solids and/or decanted solids staged on-site before hauling for off-site handling. The Phase 1 facility startup design is 0.090 million gallons per day (MGD) of treatment capacity serving the initial project service area (estimated in 2024). Construction duration is anticipated to be about 24 months. The wastewater facility will occupy approximately 3 acres of a 25.6-acre site owned by Jefferson County. The system design is approved by Washington Department of Ecology to meet regulatory requirements and population growth in the UGA through 2041. The initial Phase 1 service area is the Port Hadlock Commercial Core Area along State Route 116 and Chimacum Rd. The Department of Community Development (DCD) is reviewing the permit in accordance with Chapter 18.18 JCC, beginning as a conditional discretionary (C(d)) permit approval process. DCD anticipates final approval of the project under an administrative conditional use permit (C(a)). The project has undergone review under the State Environmental Policy Act (SEPA). DCD is using the Optional DNS Process outlined in WAC 197-11-355.
Last Name  JEFFERSON COUNTY
Received Date  5/23/2022 10:32:23 AM
Status  Approved
LaserFiche Links  View LaserFiche Documents

Case Number  PRE2022-00003
Description  Port Hadlock Wastewater Facility conditional use permit pre-application conference.
Last Name  JEFFERSON COUNTY
Received Date  1/24/2022 2:07:09 PM
Status  Pending
LaserFiche Links  View LaserFiche Documents

Case Number  ZON2021-00021
Description  SEPA for Port Hadlock Sewer Plant Plan
Last Name  JEFFERSON COUNTY PUBLIC WORKS
Received Date  3/31/2021 11:52:58 AM
Status  Withdrawn
  

Case Number  BLD2013-00342
Description  HADLOCK WASTE WATER FACILITY, TREATMENT FACILITY
Last Name  JEFFERSON COUNTY
Received Date  10/31/2013 9:53:50 AM
Status  Canceled
LaserFiche Links  View LaserFiche Documents

Case Number  SDP2013-00043
Description  CONDITIONAL USE PERMIT *ZON13-00045
Last Name  JEFFERSON COUNTY
Received Date  10/9/2013 4:55:39 PM
Status  E
  

Case Number  ZON2013-00045
Description  CONDITIONAL USE PERMIT *hadlock waste water facility
Last Name  JEFFERSON COUNTY
Received Date  10/9/2013 4:52:39 PM
Status  Canceled
  

Case Number  ZON2013-00044
Description  PERCOLATION POND/STORMWATER **third parcel incomplete...needs to be attached 90111201...
Last Name  JEFFERSON COUNTY
Received Date  10/9/2013 4:24:10 PM
Status  Canceled
  

Case Number  BLD2013-00322
Description  ADMINISTRATION BUILDING FOR HADLOCK WASTE WATER FACILITY.
Last Name  JEFFERSON COUNTY
Received Date  10/9/2013 2:09:15 PM
Status  Canceled
LaserFiche Links  View LaserFiche Documents

Case Number  PRE2012-00020
Description  CONSTRUCT CENTRALIZED WASTEWATER TREATMENT/RECLAIMED WATER FACILITY AND COLLECTION SYSTEM FOR THE IRONDALE/PORT HADLOCK URBAN GROWTH AREA
Last Name  JEFFERSON COUNTY PUBLIC WORKS
Received Date  9/27/2012 10:27:05 AM
Status  M
  

Case Number  RAP2012-00010
Description  Tree removal - Upland Ct within County Property APN 901023006
Last Name  SUKERT
Received Date  4/5/2012 12:00:00 AM
Status  Finaled
  

Case Number  FPA2602899
Description  Forest practice application.
Last Name  LOPEMAN
Received Date  9/15/1999 12:00:00 AM
Status  Finaled