Description:
|
| | |
Status updtd - Energov Convrsn
|
|
Date Completed:
|
| | |
10/4/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Permit-UF
|
|
Date Completed:
|
| | |
10/5/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Permit-UF
|
|
Date Completed:
|
| | |
10/4/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
1/6/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
10/4/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
10/4/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
10/4/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
10/4/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
10/4/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
1/6/2021
|
|
Disposition:
|
| | |
|
|
|
Title:
|
| | |
APPROVAL FOR TEMP HOUSING FACILIT
|
|
Wording
|
| | |
This APPROVAL is for a temprary housing facility only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
SITE PLAN CHANGES
|
|
Wording
|
| | |
The site plan as submitted with the Temorary Housing VIllage application on March 2, 2021 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated September 1, 2021 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
CRITICAL AREAS
|
|
Wording
|
| | |
The Geographic Information Systems mapping review identified the following Critical Areas on the subject property: CARA - SARPA + SUSC.
|
|
|
Title:
|
| | |
CARA
|
|
Wording
|
| | |
Critical Aquifer Recharge Area: Aquifer Recharge Areas in Jefferson County are characterized by porous geological formations that allow percolation of the surface water into the soils and the underlying zone of saturation. Aquifers are geologic formations that contain sufficient saturated permeable material to yield significant quantities of water to wells and springs. Aquifers serve as the source of drinking water within most of the rural portions of Jefferson County. Critical Aquifer Recharge Areas may require special protection measures to mitigate water quality degradation. The submitted proposal does not require additional aquifer protection measures. However, during construction the project shall follow the Best Management Practices (BMPs) and facility design standards as identified and defined in the Stormwater Management Manual for the Puget Sound Basin.
|
|
|
Title:
|
| | |
MEDIUM STORMWATER
|
|
Wording
|
| | |
Medium Stormwater: The applicant is proposing to create or add 4247 square feet of impervious surface and 4552 square feet of land disturbing activities. JCC 18.30.060 and 18.30.070 require the project applicant submit a stormwater plan meeting Minimum Requirements #1 through #5 of the Department of Ecology Stormwater Management Manual for Western Washington.
|
|
|
Title:
|
| | |
ENGINEERED STORMWATER
|
|
Wording
|
| | |
A Stormwater Plan has been submitted and approved by the Department of Community Development. Once the subject permit has been issued the applicant shall fully implement the provisions of the submitted plan. A Certificate of Occupancy will not be issued until the Department receives a letter from Evergreen Engineering (engineer of record) that verifies plan compliance. No clearing for roadways or utilities shall occur on the project site until clearing necessary for the installation of temporary sedimentation and erosion control measures have been completed.
|
|
|
Title:
|
| | |
LETTER FROM ENGINEER
|
|
Wording
|
| | |
PRIOR TO FINAL BUILDING OCCUPANCY, PROPONENT SHALL SUBMIT A WRITTEN LETTER FROM ERVERGREEN ENGINEERING (engineer of record) STATING THAT THE STORMWATER FACILITY HAS BEEN CONSTRUCTED IN ACCORDANCE WITH THE REQUIREMENTS OF THE ENGINEERED PLAN SUBMITTED (MARCH 2, 2021) AND APPROVED (MARCH 3, 2021).
|
|
|
Title:
|
| | |
FULL DISPERSION
|
|
Wording
|
| | |
The applicant has proposed and been approved to utilize BMP T5.30: full dispersion, requiring 100 feet natural vegetative flow path, which is required to be permanently preserved.
|
|
|
Title:
|
| | |
F-SEPA DNS
|
|
Wording
|
| | |
SEPA was detemination of Non-significance was issued on August 27, 2021. Noticing was sent out on July 19, 2021, with no comments of significance returned.
|
|
|
Title:
|
| | |
F-APPROVAL OF TEMP HOUSING
|
|
Wording
|
| | |
The proponents have met or exceeded all standards set in Emergency Ordinance 10-1221.
|
|
|
Title:
|
| | |
F-OPERATIONS PLAN ACCEPTABLE
|
|
Wording
|
| | |
The proponents have enacted a code of conduct and operations plan acceptable to ensure resident and neighborhood satey concerns.
|
|
|
Title:
|
| | |
F-COMPLIANCE W WA WATER REGS
|
|
Wording
|
| | |
The proponents have a plan in place to supply potable water and sanitary and hygienge stations for residents along with solid waste disposal. County Health Department regulations for all will be inspected as necessary to maintain regulations.
|
|
|
Title:
|
| | |
F-FOOD PREPARATION STATIONS.
|
|
Wording
|
| | |
food preparation and service tents to maintain County Health regulations along with receptacles for solid waste and proper disposal.
|
|