Description:
|
| | |
Status updtd - Energov Convrsn
|
|
Date Completed:
|
| | |
10/4/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Permit-UF
|
|
Date Completed:
|
| | |
12/17/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
A Clock Interrupt
|
|
Date Completed:
|
| | |
12/2/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-DRD
|
|
Date Completed:
|
| | |
12/2/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
11/19/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
11/5/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
11/5/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
11/19/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Potable Water Approval Req
|
|
Date Completed:
|
| | |
11/5/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
10/20/2020
|
|
Disposition:
|
| | |
|
|
|
Title:
|
| | |
F-PROPOSAL
|
|
Wording
|
| | |
The applicant is proposing to replace existing signs at the Port Hadlock QFC with illuminated signs, as shown sheets Signs A through F submitted on October 20, 2020, and Sign P submitted on December 2, 2020. The square footage of the existing signs at the QFC exceed that allowed in JCC 18.30.150 for commercial uses. The administrator has determined that the total square footage of the illuminated signs may increase up to 10 percent and be processed as a Type I application, as allowed in JCC 18.20.260.
|
|
|
Title:
|
| | |
F-Confirmed ESAs
|
|
Wording
|
| | |
The Geographic Information Systems mapping review identified the following Critical Areas on the subject property: critical aquifer recharge area (special aquifer recharge protection area) and seawater intrusion protection zone (coastal). The Jefferson County Code does not require the applicant to submit a report for an application to change signs in these types of critical areas.
|
|
|
Title:
|
| | |
F-Stormwater
|
|
Wording
|
| | |
The proposal will not result in ground-disturbing activity or an increase in impervious surface.
|
|
|
Title:
|
| | |
F-SEPA Exempt
|
|
Wording
|
| | |
Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(2)(c).
|
|
|
Title:
|
| | |
F-Site Plan Changes
|
|
Wording
|
| | |
The site plan, as submitted with the sign (zoning) application on October 20, 2020, has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated December 16, 2020 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
F-Approval for _____ Only
|
|
Wording
|
| | |
This approval is for a installation of illumated signs (to replace existing signs) only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
F-General PMT Notice
|
|
Wording
|
| | |
NOTICE: This permit does not excuse the proponent from complying with other local, state, and federal ordinances, regulations, or statutes applicable to the proposed development, but consistent with RCW 90.58. Development pursuant to this permit shall be undertaken subject to the applicable policies and performance standards of the Jefferson County Shoreline Management Master Program and the Jefferson County Unified Development Code.
|
|