Case Number:ZON2009-00070 |
Case Status: |
Date Received:6/8/2009 |
|
Description:ROCK CRUSHING PLANT as an accessory use to an existing, on-going concrete manufacturing facility on approximately 33 acres. Previously, the site had been used for a surface mine covering approximately 20 acres. Mining activity has terminated, but the concrete manufacturing plant has continued operation under current ownership since 1980 together with a wash plant that sorts imported raw mineral resource material into round rock sized for concrete and oversize waste rock. Existing improvements include a maintenance shop, stormwater collection and treatment system, a wash plant process water treatment system, and outdoor storage for various formed concrete products. It is important to note that a rock crushing plant was located legally on the property in the mid-1980s and that a berm constructed along the southern property line to attenuate noise from the crushing plant to Jefferson County standards remains in place today. The proposed crusher would operate approximately six hours per day on average, depending on the season and market demand for the aggregate. The proposed crusher will be powered by electricity so that a generator and on-site fuel storage will not be required. Appropriate materials are stored on site to clean up accidental spills or leaks. |
Date Issued:2/17/2010 |
|
Applicant:JOHN SHOLD TRUSTEE |
Expiration Date:2/17/2013 12:00:00 AM |
|
Site Address:121 POMWELL RD |
Case Finaled: |
|
Parcel No:901112002
|
Other Cases |
Parcel Data |
Map It |
Parcels |
Images |
|
Description:
|
| | |
Status updtd - Energov Convrsn
|
|
Date Completed:
|
| | |
10/4/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
4/6/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Permit-UF
|
|
Date Completed:
|
| | |
2/17/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Ntc of Dec Apprvl/Appl Inst-UF
|
|
Date Completed:
|
| | |
2/17/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Hearing Exam PH Notice-Pub-UF
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Hearing Exam PH Notice-Pub-UF
|
|
Date Completed:
|
| | |
1/10/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Hearing Exam PH Notice-APO-UF
|
|
Date Completed:
|
| | |
1/10/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-U
|
|
Date Completed:
|
| | |
1/10/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Ntc of App +14-Publish-U
|
|
Date Completed:
|
| | |
1/10/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Ntc of App +14-APO-U
|
|
Date Completed:
|
| | |
1/10/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
8/14/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
6/9/2009
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
1/10/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Potable Water Approval Req
|
|
Date Completed:
|
| | |
1/10/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
8/14/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
1/10/2010
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
1/10/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
1/14/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
8/14/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
C-SITE PLAN
|
|
Wording
|
| | |
The proposal shall be implemented in conformance with the approved site plans.
|
|
|
Title:
|
| | |
C-SEPA CONDITIONS
|
|
Wording
|
| | |
The proposal shall comply with the Mitigation Measures as specified in the Final Mitigation Determination of Non-Significance dated January 11, 2010.
a. In order to reduce noise levels, screening equipment shall be oriented in such a way that the sidewalls of the screen act as a noise barrier.
b. In order to reduce noise levels, polyurethane or polyurethane coated screens instead of typical metal screens shall be used at the site.
c. Once the screens are installed at the site, noise measurements shall be taken at all the original points as identified in the Environmental Noise Assessment dated May 27, 2009 prepared by DSA, Inc. and a report provided to the county with an analysis of the findings and recommendations and if additional mitigation is required.
d. If noise meter readings exceed the state requirements after orienting the crusher and facility so that the sidewalls of the crushing plant curtail noise radiating to the eastern and southern property lines, a noise barrier shall be installed/constructed as described in the Environmental Noise Assessment dated May 27, 2009 prepared by DSA, Inc.
e. Dust emissions from the crusher operations shall be controlled to meet the Olympic Region Clean Air Agency permit standards.
f. The existing exempt well can expand and grow into the 5,000 gallons a day exemption limit relative to the industrial uses and the proposed expansion of the rock crusher.
|
|
|
Title:
|
| | |
C-EXISTING BERM
|
|
Wording
|
| | |
The existing berm located parallel to the southern property boundary shall remain in tact and maintained in a healthy growing condition for the life of the project. Any dead or dying plants/trees shall be replaced with evergreen trees to create a "full screen" adjacent to the southern property boundary.
|
|
|
Title:
|
| | |
C-NO ADDITIONAL CONCRETE PLANTS
|
|
Wording
|
| | |
No additional concrete/asphalt batch plants are permitted at the site.
|
|
|
Title:
|
| | |
C-NOISE STANDARDS
|
|
Wording
|
| | |
The proposal shall comply with noise standards outlined by WAC 173-60-040, which were adopted by Jefferson County by Resolution 67-85.
|
|
|
Title:
|
| | |
C-NOTICE OF CONSTRUCTION
|
|
Wording
|
| | |
Prior to rock crushing occurring on site, a Notice of Construction shall be obtained from the Olympic Region Clean Air Authority.
|
|
|
Title:
|
| | |
C-LIGHTING
|
|
Wording
|
| | |
If lighting should be installed for this project in the future, the lighting shall be required to conform to JCC 18.30.140 standards. Lighting shall not exceed thirty (30) feet in height from finished grade. In addition, lighting shall not be directed towards adjacent properties and shall be shielded in a manner to mitigate glare.
|
|
|
Title:
|
| | |
C-ARCHAEOLOGICAL UNCOVERED
|
|
Wording
|
| | |
If during excavation or development of the site an area of potential archaeological significance is uncovered, all activity in the immediate area shall be halted, and the Administrator shall be notified at once.
|
|