Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
8/23/2013
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Close Case: Project Complete
|
|
Date Completed:
|
| | |
8/23/2013
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Permit-UF
|
|
Date Completed:
|
| | |
8/2/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Review Complete-U
|
|
Date Completed:
|
| | |
8/2/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
8/1/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
7/24/2007
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
8/1/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
8/2/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
8/2/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
8/2/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
Landslide Vegetative Buffer
|
|
Wording
|
| | |
A vegetative buffer of 30-feet shall be permanently maintained from the top or edge of the Landslide Hazard Area. All buffers shall be measured perpendicularly from the top or toe of the Landslide Hazard Area.
|
|
|
Title:
|
| | |
Slide Buffer-Native Vegetation
|
|
Wording
|
| | |
Landslide Hazard Areas and their associated buffers shall remain naturally vegetated. Should buffer disturbance occur during construction, the Unified Development Code (UDC) Administrator shall require replanting with native vegetation. No alterations shall be made to the Landslide Hazard Area or its associated buffer without prior authorization by the UDC Administrator.
|
|
|
Title:
|
| | |
Permanent Landslide Boundary
|
|
Wording
|
| | |
The applicant shall permanently separate the boundary of the Landslide Hazard Area Buffer from the remainder of the subject property through installing logs, trees, a hedge row, or any other prominent physical marking approved by the UDC Administrator.
|
|
|
Title:
|
| | |
Aquifer Recharge Conditions (SFR)
|
|
Wording
|
| | |
Critical Aquifer Recharge Areas may require special protection measures to mitigate water quality degradation. The submitted proposal does not require additional aquifer protection measures. However, during construction the project shall follow the Best Management Practices (BMPs) and facility design standards as identified and defined in the Stormwater Management Manual for the Puget Sound Basin.
|
|
|
Title:
|
| | |
Seawater Intrusion Areas
|
|
Wording
|
| | |
To help prevent seawater from intruding landward into underground aquifers, all new development activity on Marrowstone Island, Indian Island and within 1/4 mile of any marine shoreline shall be required to infiltrate all stormwater runoff onsite.
|
|
|
Title:
|
| | |
Comply with Water Con Measures
|
|
Wording
|
| | |
The property owner shall comply with Water Conservation Measures (per list maintained by the UDC Administrator).
|
|
|
Title:
|
| | |
BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
PREVIOUS TRIMMING
|
|
Wording
|
| | |
Approximately seven years ago the owners of Lot 53, Kala Point No. 1, wer granted permission by the county and KPOA to top the same alders to two feet below the bank level. This request is for the same to allow enhanced view of the bay and if the alders were allowed to grow taller, the wind then could cause more swaying of the trees which could loosen the roots and eventually could cause the soil to slide. Owner of Lot 53 states that they have not had any erosion of the bank since the last topping.
|
|
|
Title:
|
| | |
NOT SENT TO WDFW
|
|
Wording
|
| | |
The proposal was not sent to WDFW for potential impacts to Eagles, as the request is to top clusters of alders that are only minimal inches in diameter.
|
|
|
Title:
|
| | |
NO GEOTECH
|
|
Wording
|
| | |
A geotechnical report was not required for this request as the proposal is to top small clusters of alders that are minimal inches in diameter. KPOA has there own requirements for tree topping by a licensed/bonded professional.
|
|
|
Title:
|
| | |
F-Confirmed ESAs
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County Department of Community Development staff on Augst 12, 2007 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: conservancy/suburban shoreline designation; minimal seismic to the north; landslide 1, 2, & 3; unstable & unstable recent slide shoreline slope stability; SARPA & SUSC aquifer recharge area; coastal SIPZ.
|
|
|
Title:
|
| | |
F-Aquifer Recharge Area
|
|
Wording
|
| | |
Aquifer Recharge Areas in Jefferson County are characterized by porous geological formations that allow percolation of the surface water into the soils and the underlying zone of saturation. Aquifers are geologic formations that contain sufficient saturated permeable material to yield significant quantities of water to wells and springs. Aquifers serve as the source of drinking water within most of the rural portions of Jefferson County.
|
|
|
Title:
|
| | |
F-Susc. Aquifer Recharge Area
|
|
Wording
|
| | |
Susceptible Aquifer Recharge Areas are those with geologic and hydrologic conditions that promote rapid infiltration of recharge waters to groundwater aquifers.
|
|
|
Title:
|
| | |
F-Critical Aquifer Recharge Area
|
|
Wording
|
| | |
Critical Aquifer Recharge Areas are defined as Seawater Intrusion Areas, and Special Aquifer Recharge Protection Areas and the following land uses located within Susceptible Aquifer Recharge Areas (1) All Industrial Land Uses (2) All Commercial Uses (3) All Rural Residential Land Uses requiring a Discretionary Use or Conditional Use Permit (4) All Rural Residential Land Uses with nonconforming uses that would otherwise require a Discretionary Use or Conditional Use Permit (5) Unsewered Planned Rural Residential Developments (6) Unsewered residential development with gross densities greater than one unit per acre. All of the above listed uses shall be subject to the applicable requirements and standards of the Jefferson County Unified Development Code.
|
|
|
Title:
|
| | |
F-Geohazard Area
|
|
Wording
|
| | |
Geologically Hazardous Areas in Jefferson County are characterized by slope, soil type, geologic material, and groundwater that may combine to create problems with slope stability, erosion, and water quality during and after construction or during natural events such as earthquakes or severe rainstorms.
|
|
|
Title:
|
| | |
F-Approval for _____ Only
|
|
Wording
|
| | |
This approval is for vegetation trimming of small clumps of alders only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
ZONING
|
|
Wording
|
| | |
The parcel has been designated as RR 1:5 under the Jefferson County Comprehensive Land Use Map effective August 28, 1998.
|
|