Title:
|
| | |
FINDING: EXEMPTION SECTIONS
|
|
Wording
|
| | |
The proposal is consistent with Exemptons Section 3.402(6) of the Jefferson-Port Townsend Shoreline Management Master Program.
|
|
|
Title:
|
| | |
FINDING: MDNS ISSUED
|
|
Wording
|
| | |
This project was originally reviewed under SEPA by Jefferson County acting as lead agency. A Determination of Non-significance was issued by Jefferson County on March 22, 1993. A shoreline substantial development permit was issued (permit #SDP93-02.
|
|
|
Title:
|
| | |
bald eagle roost
|
|
Wording
|
| | |
New information from WA Dept. of Fish and Wildlife, regarding the Big Quilcene Bald Eagle Roost Complex, was submitted to the Development Review Division on May 15, 1997. This information indicates that bald eagles, a protected species, utilize the area of the subject property during Fall and Winter months for feeding and roosting purposes. Established bald eagle roost sites are considered a priorty habitat and, as such, are a critical area. Based on this new information, the shoreline exemption will be conditioned appropriately.
|
|
|
Title:
|
| | |
APPROVAL ONLY FOR J-PTSMMP
|
|
Wording
|
| | |
This approval pertains to Jefferson-Port Townsend Shoreline Management Master Program requirements only. The approval of any other agency with jurisdiction or any other required permits shall be obtained prior to undertaking the project.
|
|
|
Title:
|
| | |
OTHER WORK/SEPARATE APPROVAL
|
|
Wording
|
| | |
Work within the jurisdiction of the Shoreline Program other than as described above shall receive separate review from this office.
|
|
|
Title:
|
| | |
NO FILL OR OTHER MATERIAL
|
|
Wording
|
| | |
No fill or other material may be placed in the waters or intertidal areas of Jefferson County.
|
|
|
Title:
|
| | |
FISHERIES & HYDRAULICS CODE
|
|
Wording
|
| | |
Prior to commencing construction, proponent should contact the Washington State Department of Fisheries at (360) 895-4757 to determine whether this action is subject to the Washington State Hydraulics Code.
|
|
|
Title:
|
| | |
NOTIFICATION PRIOR TO BEGINNING
|
|
Wording
|
| | |
The proponent shall notify the Jefferson County Permit Center, (360) 379-4450, Development Review Division 48 hours in advance prior to commencing construction in order to allow monitoring and ensure conformance with project conditions.
|
|
|
Title:
|
| | |
timing restrict
|
|
Wording
|
| | |
No heavy equipment operations shall occur during the critical bald eagle roosting season from November 1 - March 1 of any given year.
|
|