Title:
|
| | |
FINDING: EXEMPTION SECTIONS
|
|
Wording
|
| | |
The proposal is consistent with Exemptons Section 3.402(6) of the Jefferson-Port Townsend Shoreline Management Master Program.
|
|
|
Title:
|
| | |
CUSTOM FINDING
|
|
Wording
|
| | |
A site inspection was conducted by Permit Center staff on 3/26/98.
|
|
|
Title:
|
| | |
CUSTOM FINDING
|
|
Wording
|
| | |
All portions of the above ground pipeline will be removed and replaced with new piping. The portions of the pipeline which are located below ground will be refurbished with insertion of a resin liner within the existing pipe.
|
|
|
Title:
|
| | |
APPROVAL ONLY FOR J-PTSMMP
|
|
Wording
|
| | |
This approval pertains to Jefferson-Port Townsend Shoreline Management Master Program requirements only. The approval of any other agency with jurisdiction or any other required permits shall be obtained prior to undertaking the project.
|
|
|
Title:
|
| | |
OTHER WORK/SEPARATE APPROVAL
|
|
Wording
|
| | |
Work within the jurisdiction of the Shoreline Program other than as described above shall receive separate review from this office.
|
|
|
Title:
|
| | |
NO FILL OR OTHER MATERIAL
|
|
Wording
|
| | |
No fill or other material may be placed in the waters or intertidal areas of Jefferson County.
|
|
|
Title:
|
| | |
FISHERIES & HYDRAULICS CODE
|
|
Wording
|
| | |
Prior to commencing construction, proponent should contact the Washington State Department of Fisheries at (360) 895-4757 to determine whether this action is subject to the Washington State Hydraulics Code.
|
|
|
Title:
|
| | |
NOTIFICATION PRIOR TO BEGINNING
|
|
Wording
|
| | |
The proponent shall notify the Jefferson County Permit Center, (360) 379-4450, Development Review Division 48 hours in advance prior to commencing construction in order to allow monitoring and ensure conformance with project conditions.
|
|
|
Title:
|
| | |
RECEIPT OF DISPOSAL
|
|
Wording
|
| | |
The applicant shall provide the Permit Center with a receipt from the Olympic View Sanitary Landfill, which verifies all pipe waste materials were properly disposed of.
|
|
|
Title:
|
| | |
temp.not over water
|
|
Wording
|
| | |
The temporary by-pass shall not be installed over water.
|
|
|
Title:
|
| | |
flush line
|
|
Wording
|
| | |
The effluent line shall be flushed with clean water for a minimum of 20 minutes to insure that no waste is released to the shoreline waters while the pipe is being removed.
|
|
|
Title:
|
| | |
emergency response
|
|
Wording
|
| | |
Should an accidental spill occur during this maintenance activity, the applicant shall fully implement the "Port Townsend Paper Corporation Environmental Response Manual" Attachment B, dated Revised 1996.
|
|
|
Title:
|
| | |
contain around joints
|
|
Wording
|
| | |
Spill catchment containers shall be placed under the joints (weak points) of the piping during removal.
|
|